样题二
注意事项
1. PMP课堂模拟题是团队针对PMP知识点提炼出来。
2. 本套模拟题共有200道单项选择题,测试时间为3个小时,闭卷答题!正确率要求答对140题(70%)或以上。(正式考试为4个小时)
3. 本套模拟题尽可能地覆盖PMP考试的题型,请学员们集中精力在4个小时内完成,达到全真的模拟效果
4. 模拟考试过程中,调整思维,揣摩考题的意图;考试结束后,认真总结。 5. 解题策略:TKSC策略
T(topic)真正读懂题目 K(key)迅速抓住考点 S(source)准确找到出处 C(choice)果断做出选择
6. PMP课堂模拟题,版权归清晖所有,未经清晖许可,不得复制或抄袭。 7. 对试题或参考答案如有疑问:
? 把试题整理好发给您的教务班主任,班主任会把您的疑问转给讲师为您解答。 ? 清晖傅老师解答:
E-mail:
QQ:249286414
1.A contractor installs the last product and receives payment. The project manager discovers flaws in the installation and requests that the contractor complete the repairs at no cost. Which of the following arguments should the contractor use to refuse the project manager’s request? A. contractual closure was approved
B. installation was improperly performed by the project team C. contractor’s quality policy does not allow for this situation D. financial closure was approved
1. 承包商安装最新产品并接收付款。项目经理发现安装有缺陷,并要求承包商免费完成修
理。承包商应使用下列哪一个论据,拒绝项目经理的请求? A. 合同收尾已批准
B. 项目团队执行的安装不当
C. 供应商的质量政策不允许发生这种情况 D. 财务收尾已批准
2.A business analyst collects requirements for a new project. Stakeholders are from different departments and have various requirements. The project budget is limited and can only deliver half of the requirements A. Facilitated workshops B. Focus groups
C. Group decision making techniques D. Group creativity techniques
2. 业务分析员为一个新项目收集需求。干系人来自不同部门并且需求也各不相同。项目预
算有限只能交付一半需求。
为确保应包含那些需求,业务分析员应使用下列哪一项? A. 引导式讨论会 B. 焦点小组 C. 群体决策技术 D. 群体创新技术
3.After a quality assurance audit, a project manager receives a formal change request proposing a modification to a component drawing. which of the following plans should the project manager review first?
A. Project management plan B. Change management plan
C. Configuration management plan D. Quality management plan
3. 在质量保证审计之后,项目经理收到一份正式的变更请求,提出修订一封部件图纸。项
目经理先查看下列那一份计划? A. 项目管理计划 B. 变更管理计划 C. 配置管理计划 D. 质量管理计划
4.To increase trust and improve interpersonal relationships, the project manager of virtual team
schedules an off-site building activity. However, due to a scheduling conflict, a key team member cannot attend the activity.
To avoid this conflict, what should the project manager have reviewed? A. Project staff assignment B. Resource calendar C. Project schedule
D. Project organization chart
4. 为提高信任度和改善人际关系,一个虚拟团队的项目经理安排了一次非现场团队的建设
活动。然而,由于进度冲突,一名关键团队成员不能参加活动。 为避免这个冲突,项目经理应已经审查那些内容? A. 项目人员配备 B. 资源日历 C. 项目进度 D. 项目组织图
5.A project manager negotiates contract terms with an external vendor that will provide additional resources to complete a critical project task. To minimize project risk, what type of contract should the project manager select? A. Cost-reimbursable B. Firm-fixed-price
C. Fixed-price-incentive-fee D. Time and material
5. 项目经理与将提供额外资源完成关键项目任务的外部供应商协商合同条款。为了减少项
目风险,项目经理应选择什么合同类型? A. 成本补偿合同 B. 固定总价合同
C. 总价加激励费用合同 D. 工料合同
6.A project team completes a project to transition from an old database to a new database. Regarding lessons learned, what should the project manager do next? A. Present to the sponsor at the stakeholder closeout meeting B. Present to the client to ensure agreement C. Ensure information is stored in a project file
D. Ensure information is stored in a corporate knowledge base
6. 项目团队完成了一个从就数据库转变到新数据库的项目。在经验教训方面,项目经理下
一步该怎么做?
A. 在干系人收尾会议上提交给发起人 B. 提交给客户确保协议
C. 确保信息储存在一份项目文件中 D. 确保信息储存在公司知识库中
7.During the project execution phase, a project manager learns that the customer’s organization could be acquired by another organization. What should the project manager do next?
A. B. C. D. Revisit the project charter Perform a risk reassessment
Ask for the project sponsor’s guidance Discuss the issue with stakeholders
7. 在项目执行阶段,项目经理了解到客户所在组织可能被另一个组织收购。项目经理下一
步该怎么做? A. 查看项目章程 B. 执行风险再评估
C. 寻求项目发起人的知道 D. 与干系人讨论这个问题
8.How should the effectiveness of a project’s quality control activities be determined? A. Evaluate the quality assurance plan against market benchmarks B. Implement a quality audit strategy
C. Conduct a quality audit of the deliverables D. Evaluate the cost of quality
8. 应如何确定项目质量控制活动的有效性?
A. 对照市场标杆评估质量保证计划 B. 实施质量审计策略
C. 对可交付成果实施质量审计 D. 评估质量成本
9.At a project kick-off meeting, the chief executive officer(CEO) requests changes that will impact the project scope. How should the project manager respond?
A. Advise the ceo that the project team will estimate the impact of the change request
B. Inform the CEO that the scope cannot implement the change because the project scope is
finalized
C. Accept the changes according to CEO’s request
D. Consider the CEO’s change during the project execution phase-
9. 在项目启动大会上,首席执行官(CEO)提出的变更将会影响项目范围。项目经理应如
何响应。
A. 通知CEO项目团队将调查所建议变更的影响 B. 通知CEO,范围已最终确定,无法变更 C. 按CEO请求,接受变更
D. 在项目实施阶段考虑CEO的变更
10.Which task has the correct assignment in the RACI chart? 序 1 2 3 4 Task Unit test Integration test Team member #1 Team member #2 Team member #3 Team member #4 Team member #5 R I I R A A R A I C C C C A I I A R A A System test User acceptance test A. Task 1 B. Task 2
C. Task 3 D. Task 4
10. 那一个任务在RACI图中的分配正确? 序 1 2 3 任务 单位测试 集成测试 系统测试 用户验收测4 试 A. 任务1 B. 任务2 C. 任务3 D. 任务4
团队成员#1 R I I R 团队成员#2 A A R A 团队成员#3 I C C C 团队成员#4 C A I I 团队成员#5 A R A A
11.At the end test part 4, the project manager reviews a control chart. What does the chart indicate?
A. Quality is in line with expectations
B. Quality expectations are not achievable
C. Quality has not improved since the beginning of the tests D. Quality is not in line with expectations
11. 在测试零件4结束时,项目经理查看了控制图。这个控制图会说明说明?
A. B. C. D.
质量符合预期 质量预期不可实现
自从测试开始起,质量未得到改善 质量与预期不符
12.During a project’s implementation, several providers participate in the project. The project manager meets with stakeholders, external consultants, and subject matter experts to define the project scope.
The project manager should include which items as part of the project scope statement?
A. Requirements traceability matrix, risk register, stakeholder register,
activity list
B. Constraints, schedule, assumptions and work breakdown structure C. Scope description, acceptance criteria, constraints and deliverable D. Technical reference, exceptions, deliverable and scope baseline
12. 在项目实施期间,多名供应商参与项目。项目经理与项目干系人、外部顾问和主题专家
一起开会定义项目范围。
项目经理应该将那些项内容包含作为项目范围说明书的组成部分? A. 需求跟踪矩阵、风险登记册、干系人登记册和活动清单 B. 制约因素、进度计划、假设和工作基准结构 C. 范围说明、验收标准、制约因素和可交付成果 D. 技术参考、例外情况、可交付成果和范围基准
13.A project team installs a new operating system. Before implementation, the team tests the system on a smaller, isolated network and discovers some issues. After
finding solutions to these issues, the team still encounters implementation issues. However, the number and severity of issues are greatly reduced Which of the following does the project team use? A. Transferring risk B. Mitigating risk C. Accepting risk D. Avoiding risk
13. 项目团队安装一个新的操作系统。实施之前,该团队在一个较小独立的网络中测试该系
统,并发现一些问题。发现这些问题的解决方案之后,团队仍然碰到实际问题。然后,问题数量和严重程度大大降低。项目团队使用的是下列哪一项? A. 转移风险 B. 减轻风险 C. 接受风险 D. 规避风险
14.A new project manager takes over a project in the execution phase. The project manager learns that the customer did not provide the correct product requirements The project manager should apply activities from which of the following plans? A. Scope management plan B. Change management plan
C. Configuration management plan D. Requirements management plan
14. 新项目经理接管了一个处于执行阶段的项目。项目经理了解到客户没有提供正确的产品
需求。项目经理应采用下面哪一项计划中的活动? A. 范围管理计划 B. 变更管理计划 C. 配置管理计划 D. 需求管理计划
15.A bicycle company releases a new line of baskets with a five-year warranty. The material withstands extreme weather conditions. The product is well received by customers and is considered top of the line the design is basic with no additional features
Which of the following describes this product? A. High grade, high quality B. Low grade, low quality C. High grade, low quality D. Low grade, high quality
15. 一家自行车公司发布了一款拥有五年质保期的新车蓝系列。材料能抵御极端天气条件。
产品广受用户接受,且视为是系列中的顶级产品。产品只有基本设计,无额外功能。 下列哪一项是该产品的描述? A. 高档、高质 B. 低档、低质 C. 高档、低质
D. 低档、高质
16.A project contains several stakeholders, 50 team members, a number of job sites, and stakeholders and project team member may review a lot of information and documents anytime during the project period, what communication method the project manager should use to solve the information requirement of project? A. Interactive communication B. Push communication C. Pull communication D. Send-receive
16. 一个项目包含多名干系人,50名团队成员,多个工作现场,以及干系人和团队成员可能
需要在项目过程中任何时间查看的大量信息文件。若要解决项目的信息需求,项目经理应使用哪一个沟通方式? A. 交互式沟通 B. 推式沟通 C. 拉式沟通 D. 发送-接收
17.A project manager wants to develop a resource breakdown structure(RBS) for a new project. A team member states that the team already developed an RBS for similar, existing project. What should the project manager do next?
A. Compare the existing project’s RBS to the organization’s standard template B. Use the existing project’s RBS to save time
C. Create a new RBS using the organization’s standard template D. Use the applicable categories of the existing project’s RBS
17. 项目经理希望为一个新项目制定资源分解结构(RBS)。一名团队成员称该团队已经为
一个类似现有项目制定了RBS. 项目经理下一步该怎么做?
A. 将现有项目的RBS与组织的标准模板进行对比 B. 使用现有项目的RBS节约时间
C. 使用组织的标准模板创建一份新的RBS D. 使用现有项目RBS的适用类别
18.A project manager discovers that a key team member will leave the organization in two weeks. The team member works on tasks that are on the critical path What should the project manager do first? A. Evaluate the impact of losing this member B. Verify if can change the scope C. Update work breakdown structure D. Change the project team member
18. 项目经理发现一名关键团队成员将在两周内离开组织。该名团队成员正在为处于关键路
径上的任务工作。
项目经理首先应该做什么 A. 确定该名团队成员的影响
B. 核实是否能够变更范围 C. 更新工作分解结构 D. 更换团队成员
19.A company’s president asks a project manager to implement a new financial system. What technique should the project manager use to obtain a high-level project scope? A. Perform a make-or-buy analysis
B. Meet with the director of information technology to conduct an analysis C. Define requirement with the company’s finance experts and business owners D. Collect requirements from financial application vendors
19. 公司总监要求项目经理实施一个新的财务系统。项目经理应使用什么技术获得高层次项
目范围?
A. 开展自制或外购分析
B. 与信息技术总监开会开展一项分析
C. 与公司的财务专家和企业所有者定义需求 D. 收集财务应用程序供应商的需求
20.After negotiation with resource manager, project manager develops the project management plan. In the kick off meeting, resource manager says the resource only can be available in the late state of project period, what should the project manager do next?
A. Add the resource risk into risk register
B. Record the change, review and update the project management plan
C. Communicate the resource availability delay and manage the stakeholder
participation levels D. Do not take any action, since the issue has been discussed in the kick off meeting 20. 在于资源经理协商之后,项目经理制定项目管理计划。在项目启动大会上,资源经理称
一名资源在进度计划后期才可用。 项目经理下一步该怎么做?
A. 在风险登记册中添加该资源风险
B. 记录该变更,并审查和更新项目管理计划
C. 在资源可用性中沟通该延迟,并管理干系人的参与水平 D. 不采取其他行动,因为该问题已在项目启动大会上讨论过了
21.The conflict among some project member may delay the project, what should the project manager do next?
A. Solve the conflict in advance in private
B. Delay the conflict, and evaluate if it will impact the project in future C. Report the conflict to function manager
D. View the human resource management plan and take the corrective action 21. 一些团队成员的内部冲突可能延迟项目,项目经理下一步该怎么做?
A. 提前并私下解决冲突
B. 延迟冲突,评估其是否将会在后期影响项目 C. 将冲突上报给职能经理
D. 查看人力资源管理计划并采取纠正措施
22.A project is near completion and another US$120,000 is needed to finish the project. Even though US$1 million has already been spent on the project, the project sponsor requires the project manager to stop the project for various circumstances In this case the actual costs are: A. Direct costs for the project
B. Part of the project’s contingency reserve C. Indirect costs for the project
D. Sunk costs not taken into account for this decision
22. 项目接近完工,但另需120,000美元来完成该项目。虽然该项目已经花费100万美元,
处于各种情况,项目发起人要求项目经理停止该项目。 在这种情况下,实际成本为: A. 项目的直接成本
B. 项目应急储备的一部分 C. 项目的间接成本
D. 该决定不考虑沉没成本
23.A storm damages a data center, causing a delay to the project. as a result of this unexpected event, what should the project manager do next? A. Use management reserve funds to generate a workaround B. Delay the project and wait for management’s directions C. Update the schedule and advise the project sponsor
D. Meet with the project team to discuss the immediate response
23. 一场风暴损坏了数据中心,导致项目延迟。由于这是一个意外事件,项目经理下一步该
怎么做?
A. 使用管理储备金来生成一个权变措施 B. 延迟项目,并且等待管理层的只是 C. 更新进度,并且通知项目发起人 D. 与项目团队开会讨论直接的应对措施
24.A project manager works on a US$3 million project which involves two suppliers. The project manager creates a statement of work(SOW) for each supplier Which of the following needs SOW? A. Risk management plan B. Project charter
C. Procurement management plan D. Supplier scope statement
24. 项目经理正在管理价值300万美元,涉及两个供应商的项目。项目经理为每名供应商创
建了一份工作说明书(SOW). 下列哪一项需要SOW的信息 A. 风险管理计划 B. 项目章程 C. 采购管理计划
the project manager that some key stakeholders were forgotten during a previous similar project. The project sponsor mandates that the project manager ensure that all stakeholders be identified
What approach should the project manager take to gather the required information A. Consult the lessons learned from the previous project B. Consult the project charter from the previous project C. Start to prepare a stakeholder analysis from scratch
D. Obtain the project management plan from the previous project
53. 项目经理被任命管理一个新项目。项目发起人已经起草完项目章程的第一稿。项目发起
人通知项目经理在之前一个类似项目中某些关键干系人被遗漏了。项目发起人要求项目经理确保所有项目干系人均已识别。
若要收集必要信息,项目经理应该采取什么方式? A. 查询之前项目的经验教训 B. 查询之前项目的项目章程 C. 开始从头准备一份干系人分析 D. 获得之前项目的项目管理计划
54.After confirming the availability of human resource and obtaining teams for project assignments, the project manager discovers that the resources will not sufficiently meet the project schedule. The project manager meets with a functional manager who agrees to make additional resources available for the duration of the project
What tool or technique does the project manager use? A. Negotiation B. Acquisition C. Pre-assignment D. Co-location
54. 确认人力资源可用性并获得执行项目任务的团队后,项目经理发现资源不足以满足项目
进度计划,项目经理与职能经理开会,职能经理同意为项目工期增加可用资源。 项目经理是用的是什么工具或技术 A. 谈判 B. 招募 C. 预分派 D. 集中办公
55.As a result of financial issues, seller a will be late in delivering a critical product. According to the contingency plan, seller B is an approved vendor and could deliver a similar product
What should the project manager do next?
A. Submit a change request to the change control board B. Hold a bidder meeting with potential sellers
C. Review business case to ensure the return on investment D. Submit a change request to procurement department
55. 作为一个财务问题的结果,卖方A将延迟交付一项关键产品。按照应急计划,卖方B是
一家获批准卖方,可以提供类似产品。 项目经理下一步该怎么做?
A. 向变更控制委员会提交一项变更请求 B. 与潜在卖方召开投标人会议 C. 审查商业论证,确保投资回报 D. 向采购部门提交一份变更请求
56.Which one of the following techniques could be used to measure the compliance ofa project to the organizational policies and procedures? A. Benchmarking B. Delphi
C. Root cause analysis D. Quality audit
56. 下列哪一项技术可以用于衡量一个项目是否符合组织政策和程序?
A. 标杆对照 B. 德尔菲技术 C. 根本原因分析 D. 质量审计
57.A project manager completes a large project that requires equipment purchases from a local vendor. Which of the following activities would occur in the close procurements process?
A. Updating the procurement management plan
B. Updating the terms and conditions of the contract C. Archiving the contract documentation D. Archiving the project management plan
57. 项目经理完成了一个需要从当地供应商采购设备的大型项目。下列哪一项活动将发生在
结束采购过程中? A. 更新采购管理计划 B. 更新合同条款和条件 C. 合同文档存档 D. 项目管理计划存档
58.During an internal project team meeting, the scheduling assistant shares information that the project manager does not want shared with the other team members. The project manger immediately asks the assistant to stop discussing this topic and to meet privately after the team meeting has concluded The project manager uses what tape of conflict management? A. Smooth/accommodate
B. Collaborate/problem solve C. Force/direct D. Withdraw/avoid
58. 在一次内部项目团队会议中,进度安排助理分享了项目经理不希望与其他团队成员分享
的信息。项目经理立即让该助理停止讨论这个话题,并在团队会议结束后私下见面讨论。 项目经理使用的是那种冲突管理类型? A. 缓解/包容 B. 合作/解决问题 C. 强迫/命令 D. 撤退/回避
59.At the end of a project, a customer inquiries about a missing item. To ensure all items are completed, what should the them have referenced? A. Work breakdown structure B. Project scope C. Activities list
D. Project management plan
59. 在项目结束时,一名客户询问一个缺失项的情况。为确保所有各项工作均已完成,团队
应参考什么文件? A. 工作分解结构 B. 项目范围 C. 活动清单 D. 项目管理计划
60.Midaythrough a project’s execution, a customer requests additional
functionality that will be critical from a business perspective. Which of the following subsidiaries of the project management plan will be primarily impacted? A. Configuration management plan B. Scope management plan C. Risk management plan
D. Communications management plan
60. 在一个项目执行中途,客户要求增加从业务前景上看非常关键的功能。这将主要影响到
以下哪一个项目管理计划附件? A. 配置管理计划 B. 范围管理计划 C. 风险管理计划 D. 沟通管理计划
61.A project manager must provide performance data to the project sponsor. To ensure consistency with previous status reports, the project manager verifies the quality of the information.
What technique does the project manager use? A. Forecasting methods B. Variance analysis C. Information gathering D. Checklist analysis
61. 项目经理必须向项目发起人提供绩效数据。为确保之前的状态报告保持一致,项目经理
核实信息质量。项目经理使用的是什么技术? A. 预测技术 B. 偏差分析 C. 信息收集 D. 核对表分析
62.Due to an organizational change, some functional human resources will no longer be available work on the project. The organization lacks internal resource to fill the vacancies
What should the project manager do to address this resource issue?
A. Redistribute the workload across the remaining functional resources B. Assess external resource C. Reschedule the project
D. Escalate this human resource issue to the project sponsor
62. 由于组织变更,有些职能人力资源不再可能为项目工作。该组织缺乏内部资源来填补空
缺。
若要解决这个资源问题,项目经理应该怎么做? A. 在剩余的职能资源中重新分配工作量 B. 评估外部资源
C. 重新制定项目进度计划
D. 将这个人力资源问题上报给项目发起人
63.Before the bid or proposal submittals, a company meets with all prospective sellers. The company wants to ensure that all prospective sellers have a clear and common understanding on the procurement process
The company is in which of the following procurement management processes? A. Conduct procurements B. Plan procurements C. Control procurements D. Close procurements
63. 提交标书或建议书之前,一家公司与所有潜在卖方开会。公司希望确保所有潜在卖方对
采购流程有一个明确的共识。
该公司正处于下列哪一项采购管理过程组中? A. 实施采购 B. 计划采购 C. 控制采购 D. 结束采购
64.After completing the define scope process, which technique should the project manager use to generate a reliable estimation and manage cost and activity duration? A. Decomposition
B. Precedence diagramming method C. Earned value management
D. Establish a benchmark
64. 完成定义范围过程后,项目经理应使用哪项技术来生成可靠估算并管理成本和活动持续
时间? A. 分解
B. 紧前关键绘图法 C. 挣值管理 D. 确立基准
65.At a project status meeting, the vendor reports that they will miss the deadline to release software, which will be required for the project to move forward. What should the project manager do first? A. Update the project management plan
B. Negotiate a new release date with the vendor C. Perform the change control process D. Issue a change request for approval
65. 在状态会上,供应商报告他们将会延误软件发布期限,而发布软件是项目继续推进的一
个必要条件。
项目经理首先应该做什么? A. 更新项目管理计划
B. 与供应商协商一个新的发布日期 C. 执行变更控制过程 D. 签发变更请求获得批准
66.A web development firm delivers a product to the client on time and 20% over the original budget. The client is currently soliciting bids for a new web project. What should the web development firm’s project manager do during the closure phase to enhance customer relations?
A. Request requirements for the new web project B. Conduct a stakeholder analysis
C. Meet with the client to review lessons learned
D. Implement corrective actions of the budget controlling
66. 一家网络开发公司按时向客户交付产品,但超出原始预算20%。客户目前正在为一个新
网络项目投标。若要增强客户关系,网络开发公司的项目经理在收尾阶段应怎么做? A. 索取新网络项目的需求 B. 进行干系人分析
C. 与客户开会,审查经验教训 D. 执行预算控制的纠正措施
67.Theproject manager begins to close a supplier contract. In order to ensure the correct acceptance of the contract, which of the following completing sequence should the project manager follow?
A. Verify completed work, close financial work, close contract B. Close contract, verify completed work, close financial work C. Close financial work, close contact, verify completed work
96.Due to unexpected circumstances, a project stops during implementation. Six month later, the organization wants to finish the project and assigns the same project manager
What should the project manager do first?
A. Review all initiation and planning outputs and confirm any changes with the
project stakeholders
B. Review all initiation and planning outputs and revise the project management
plan
C. Review the project management plan and continue with the execution to finish
the project
D. Review all planning outputs and follow the change management plan
96. 由于意外情况,一个项目在执行期间停止。六个月后,该组织希望完成项目,并任命了
同一个项目经理。
项目经理首先应该做什么?
A. 审查所有启动和规划输出,并与项目干系人确认任何变更 B. 审查所有启动和规划输出,并修订项目管理计划 C. 审查项目管理计划并继续执行直到完成项目 D. 审查所有规划输出,并遵循变更管理计划
97.Midway through the project, the project manger must determine if the planned budget will be sufficient to complete the project. Which of the following should the project manager calculation and then compare with the original budget A. Estimate to complete B. Estimate at completion C. Earned value
D. Budget at completion
97. 在项目中途,项目经理必须决定计划预算是否足以完成该项目。项目经理应该计算下列
哪一项值再与原始预算对比? A. 完工尚需估算 B. 完工估算 C. 挣值 D. 完工预算
98.During the analysis phase of a company’s project, the project stalls because key stakeholders within various departments disagree on basic project requirements. With no prospective resolution, the project manager escalates the project risk. The project sponsor decides to terminate the project. Which of the following does this describe A. Risk avoidance B. Risk transfer C. Risk acceptance D. Risk mitigation
98. 在一家公司项目的分析阶段,由于不同部门的各个关键干系人对基本项目需求意见不一
致,项目停止不前。由于没有潜在的解决方案,项目经理上报了项目风险。项目发起人决定终止该项目。
下列哪一项是该行动的描述? A. 风险回避 B. 风险转移 C. 风险接受 D. 风险减轻
99.As a result of the quality control process, a change request is generated and approved by the change control board What should the project manager do next?
A. Arrange the implementation of the approved change
B. Evaluate the change request with change control board C. Evaluate the risk if not to implement the change
D. Perform root cause analysis to determine the cause of the change
99. 作为控制质量过程的结果,产生变更请求,并由变更控制委员会批准。项目经理下一步
该怎么做?
A. 安排批准变更的实施
B. 与变更控制委员会一起评估变更请求 C. 评估如果不实施变更的风险
D. 执行根本原因分析确定变更的缘由
100.After a detailed list of project activities is created, the project manager wants to estimate the project’s total cost without changing the project’s duration or deliverables. Which of the following estimating techniques should the project manager use? A. Three-point B. Bottom-up C. Analogous D. parametric
100. 在创建项目活动详细清单之后,项目经理希望在不更改项目持续时间或可交付成果的情
况下估算项目总成本。项目经理应使用下列哪一项估算技术? A. 三点估算 B. 自下而上 C. 类比估算 D. 参数估算
101. During project initiation, a key stakeholder claims the project is no longer viable. What should the project manager do to evaluate the project’s viability? A. Refer the stakeholder to the project sponsor.
B. Delay reassessment until project funding is exhausted at the end of initiation.
C. Check alignment with the business case and present to sponsor and key stakeholders. D. Start the project closure process immediately.
101.在项目启动期间,一名关键干系人声称项目不再可行。为评估项目的可行性,项目经理应该怎么做?
A.将该干系人推荐给项目发起人。
B.拖延项目再评估,直至项目资金在启动阶段结束时用完。
C.检查是否与商业论证保持一致,并提交给项目发起人和关键干系人。 D.立即开始项目收尾过程。
102. A project is delivered on-time, within the staffing budget, and is according to customer requirements. The project seems to be successfully launched. However, three months after the launch, the customer is concerned with the product and proposes a new project and design change. During project closing, what should the project manager have done? A. Validated scope
B. Measured customer satisfaction C. Reviewed test reports D. Standardized inspections
102.在人员配备预算内,项目按时交付,且符合客户要求。项目看起来成功推出。但是,就在推出后的三个月,客户对产品表示担心,并提出一个新项目和设计变更。在项目收尾期间,项目经理应该已完成什么? A.核实范围
B.衡量客户满意度 C.审查测试报告 D.标准化检查
103. A risk in the risk register is realized late in the project. What would be the most effective response to the situation?
A. Use the management reserve.
B. Perform a quantitative risk analysis. C. Perform a qualitative risk analysis. D. Use the contingency reserve.
103.在风险登记册中的一个风险在项目后期发生。应对这种情况的最有效措施是什么? A.使用管理储备。 B.执行定量风险分析。 C.执行定性风险分析 D.使用应急储备。
104. The sponsor asks the project manager to quickly implement the primary deliverables* The project manager attempts to allocateresources to the first tasks, but realizes resources are not available.To identify the required skills, which of the following documents should the project manager reference first. A. Resource calendars B. Project scope statement
C. Human resource management plan D, WBS dictionary
104.项目发起人要求项目经理快速实施主要可交付成果。项目经理尝试将资源分配给第一个
任务,但意识到资源不可用。为识别所需技能,项目经理应首先参考下列哪一份文件? A.资源日历
B.项目范围说明书 C.人力资源管理计划 D.WBS字典
105. A new team member joins a project. Because the new team member does not have any previous experience with the company, the project manager recommends that the team n*ember review project files from the company’s previous projects. This is an example of leveraging which of the following? A. Infrastructure
B. Project management information systems C. Organizational process assets D. Enterprise environmental factors
105.一名新团队成员加入项目。由于新团队成员之前在公司没有任何经验,项目经理建议团队成员查看公司之前项目的项目文件。这是利用下列哪一项的实例? A.基础设施
B.项目管理信息系统 C.组织过程资产 D.企业环境因素
106. A project is created to establish a new call center, and the development of training material is subcontracted to an external training services providers. The training provider accepts a fixed price contract for its services. Project risks associated with the subcontracted development of training materials is an example of which of the following strategies'? A. Mitigated B. Transferred C. Accepted D. Avoided
106.一个项目是为了设立一个新的呼叫中心,培训资料的编制外包给一家外部培训服务提供商。培训提供商接受为其服务签订一份固定总价合同。与分包编制培训资料有关的项目风险属于下列哪一项战略的实例? A.减轻 B.转移 C.接受 D.回避
107. When preparing a business case with a financial analyst, what key document is needed? A. Cost-benefit analysis B. Statement of work C. Contract
D. Project charter
107.在与财务分析师准备商业论证时,需要以下哪一份关键文件? A.成本效益分析
B.工作说明书 C.合同
D.项目章程
108. As a new project enters the development phase, the project manager is notified that the shipment of a key project component may be delayed; the project cannot be completed without this component. As a result, the project manager requests an extenuation to the project schedule to accommodate the delay. Which of the following was used to manage the risk? A. Avoid B. Mitigate C. Exploit D. Accept
108.在一个新项目进入开发阶段时,项目经理接到通知,一个关键项目组成部分的转运可能延期。而没有这个组成部分,项目则无法完成。因此,项目经理要求延长项目工期,来适应这个延期。这使用了下列哪一项来管理风险? A.回避 B.减轻 C.利用 D.接受
109. Aproject manager completes development of the project management plan. Approval is obtained from all the key stakeholders, with the exception of the sates manager. Should the project manager proceed with project execution?
A. No; the project manager should complete a risk register and escalate to the project sponsor. B. No; the project manager should continue to follow the process and obtain the sales manager's approval,
C. Yes; the project manager should proceed and inform the project sponsor of the situation. D. Yes; the project manager should proceed to avoid delay, and follow up with the sales manager as soon as possible.
109.项目经理完成项目管理计划的制定。已经获得除销售经理以外的所有关键干系人批准。项目经理是否应继续执行项目?
A.否:项目经理应完成一份风险登记册,并上报给项目发起人。 B.否:项目经理应继续遵循过程,并获得销售经理的批推。 C.是:项目经理应继续并将情况通知项目发起人。
D.是:项冒经理应继续,以避免延期,并尽快与销售经理跟进。
110. A project manager is assigned to a project to replace an outdated system. During installation the equipment is damaged and requires technical resources to repair it. What document must be updated to communicate this occurrence with the stakeholders? A. Issue log B. Status report
C. Incident management plan D. Resource allocation matrix
110.项目经理被任命管理一个更换过时系统的项目。在安装期间,设备损坏,并要求技术资
源修理。必须更新哪一份文件将这种情况与干系人沟通? A.问题日志 B.状态报告 c.事件管理计划 D.资源分配矩阵
111. Due to quality control issues, a project is behind schedule. There is no obvious pattern to the identified defects. Using a qualitative approach, which quality control tool should be used to determine the source of the defects? A. Histogram B. Pareto chart C. Scatter diagram
D. Cause and effect diagram
111.由于质量控制问题,项目落后于进度。没有识别缺陷的明显模式。使用定性方法,应使用哪一种质量控制工具来确定缺陷来源? A.直方图 B.帕累托图 C.散点图 D.因果图
112. A team member is impacting work performance with negative behavior. What technique should the project manager use to address this issue? A, performance appraisal B. Coaching
C. Conflict management D, Norming
112.一名团队成员采用消极行为影响工作绩效。项目经理应使用什么技术来解决这个问题?A.绩效评价 B.指导 C.冲突管理 D.规范
113. A project was completed one year ago, and the project manager and resources are assigned to another project, The customer emails the chief operations officer claiming that a deliverable is not within the expected quality level and requests a change to this deliverable, Before respondjn8 to the customer, what document should the chief operation officer review first? A. Requirements management plan B. Customer acceptance documents C. Quality inspection report D. Statement of work
113.项目已在一年前完工,项目经理和资源已分配到另一个项目。客户向首席运营官发送电子邮件,声称一个可交付成果不符合预期的质量级别,并请求对该可交付成果的变更。在答复客户之前,首席运营官应首先审查什么文件? A.需求管理计划
B.客户验收文件 C.质量检查报告 D.工作说明书
114. During the initiation phase of an international project, a project manager analyzes the project scope statement with experts; the experts inform the project manager that some project deliverables will not be practical due to import restrictions. What should the project manager do next?
A. Remove the impractical deliverables from the project scope statement and charter, and then initiate the project.
B. Initiate the project as originally planned, and if issues arise, transfer risk to an external party.
C. Initiate new scope and contract negotiation discussions with the project sponsor and the key stakeholders.
D. Incorporate the risk of import restrictions in the risk management plan and risk register. 114.在一个国际性项目的启动阶段,项目经理与专家们一起分析项目范围说明书。专家告知项目经理,由于进口限制,一些项目可交付成果不可实现。项目经理接下来应该怎么做? A. 将不可实现的项目可交付成果从项目范围说明书和项目章程中剔除,然后启动该项目。 B. 按原计划启动项目,且然后产生问题,则将风险转移给外部方。 C. 与项目发起人和关键干系人开展新的范围和合同谈判讨论。 D. 将进口限制风险包含近风险管理计划和风险登记册中。
115. During a company’s relocation to a new data center, a project team member discovers that the new data center’s power supply will not be sufficient. To support forecasted growth over the next three years, additional resources costing US$480,000 will be required. As the project manager had previously identified this as a risk, what tool should have been used to determine if the contingency budget would adequately cover this costs? A. Status meeting B. Reserve analysis C. Risk reassessment
D.Technical performance measurement
115.在公司迁址到一个新数据中心期间,一名项目团队成员发现新数据中心的电源不足。为了支持在未来三年内的预测增长,将需要US$48万的额外资源。由于项目经理之前已将此识别为一个风险,应使用什么工具来确定应急储备足以涵盖成本? A.状态会议 B.储备分析 C.风险再评估 D.技术绩效测量
116. A team member with key technical skills disagrees with the way in which the project is managed. What should the project manager do first?
A. Meet with the team member privately to discuss the issue.
B. Continue with the project because it will not affect the project’s progress. C. Acknowledge the team member’s contributions and ability on the project
D. Address the. Team member’s issue in a team meeting
116.一名拥有关键技术技能的团队成员对项目管理方式不认同。项目经理首先应该怎么做?A.与该名团队成员私下讨论该问题。 B.继续项目,因为这不影响项目进度。 c.认可团队成员对该项目的贡献和能力。 D.在团队会议上解决团队成员的问题。
117. After noticing a conflict within the team, the project manager attempts to resolve the conflict by emphasizing the areas on which the team agrees and de-emphasizing the areas on which the team disagrees, this is an example of which of the following conflict resolution techniques
A, Compromise/Reconcile B. Smooth/Accommodate C. Collaborate/Problem Solve D. Withdraw/Avoid
117.在得知团队中发生冲突之后,项目经理尝试通过强调团队达成共识的方面,而不强调未达成共识的方面来解决冲突。这属于以下哪一种冲突解决技术的范例? A妥协/调节 B.缓解/包容
C.合作/解决问题 D.撤退/回避
118. During development of the project’s budget plan, which of the following should assist the project manager in determining the total project costs? A. Resource calendar B. Earned value method C. Cost variance analysis D. Cost control process
118,在制定项目预算计划期间。下列哪一项将协助项目经理确定项目总成本? A.资源日历 B.挣值法
C.成本偏差分析 D.成本控制过程
119. A team member informs the project manager that an assigned task cannot be implemented by the established method. The team member suggests a new method that may require additional time and impact the project baseline. What should the project manager do first? A. Implement the change immediately to meet the schedule baseline. . B. Initiate the change request process.
C. Meet with the sponsor to explain the situation, D. Perform an impact analysis of the change request.
119.一名团队成员通知项目经理,一个已分解的任务不能通过常规方法实施。团队成员建议了一个新方法,但可能需要额外的时间,并不影响项目基准。项目经理首先应该怎么做? A.立即实施变更,满足进度基推。
B.开始变更请求过程
C.与发起人开会,说明这种情况。 D.执行变更请求的影响分析。
120. A project manager suspects there is a quality defect in a recently produced batch of products. However, a test for this defect will be destructive to the products. What should the company do next'?
A. Execute a design of experiments on the batch of products.
B. Randomly select units from the batch to measure the extent of the defect. C. Execute statistical sampling with pre-defined acceptance criteria. D. Release the current batch to sell at a discounted price,
120.项目经理怀疑最近生产的产品批次中存在一个质量缺陷。但是,对这个缺陷执行测试对产品将是破坏性的。公司下一步应该怎么做? A.对该产品批次执行实验设计。
B.从产品批次中随机选择几组来测量缺陷的范围。 C.使用预先定义的验收标准执行统计抽样 D.发布当前批次产品,按打折价销售。
121. Due to resource constraints, a project manager determines that a portion of the project work must be outsourced, Which of the following inputs are required to ensure the requirements and the timeline are met?
A. Qualified sellers’ list and scope B. Schedule and scope
C. Cost estimates and performance D. Cost estimates and schedule
121.由于资源约束条件,项目经理决定必须外包部分项目工作。为确保满足需求和时间线,需要下列哪一项输入? A.合格卖方清单和范围 B.进度和范围
C-成本估算和绩效 D.成本估算和进度
122. Remote project team members request that project meeting times are changed to a time within the remote team’s working hours, However, local team members do not agree with this proposal. What should the project manager do next?
A. Arrange a team meeting with all parties to determine a suitable time. B. Discuss with the sponsor to decide upon a suitable time. C. Accept the remote team’s request for a trial period.
D. Reject the remote team’s request as it is not in the communications management plan.
122.远程项目团队成员请求将项目会议时间更改为远程项目团队的工作时间内进行。然而,本地团队成员却不同意这项提议。项目经理接下来应该怎么做? A.安排一次与所有者方的团队会议,确定一个合适的时间。 B.与发起人讨论决定一个合适的时间。 C.接受远程团队的请求,并试行一段时间。
D.拒绝远程团队的请求,因为不包含在沟通管理计划中。
123. The project manager identifies that a finish-to-start dependency for an activity on the critical path is missing. The project schedule was already communicated to the customer. What should the project manager have done to avoid this issue? A. Reviewed the work breakdown structure B. Conducted a schedule network analysis C. Prepared a risk management plan D. Conducted an earned value analysis
123.项目经理发现关键路径上一项活动的开始到结束依赖关系遗漏了。项目进度计划已经与客户沟通。若要避免这个问题,项目经理应该事先做什么? A.审查工作分解结构 B.进行进度网络分析 c.制定风险管理计划 D.进行挣值分析
124. A project’s total cost is US$200,000. The project management requests a study to verify whether the project will run behind schedule. The project has a 35% chance ofincurring a penalty of US$20,000 due to a delay in completion. There is a 65% chance that the company will earn US$500,000 on the project. What is the expected monetary value? A. US$118,000 B. US$293,000 C. US$318, 000 D. US$325,000
124.项目总成本为US$200,000.项目管理办公室要求开展一项研究,来验证项目是否会落后于进度。项目有35%的机会发生因完工延期所导致的US$20,000罚款。还有65%的机会公司将在项目中获利US$500,000。那么预期货币价值是多少? A. US$118,000 B. US$293,000 C. US$318,000 D. US$325,000
125. During project execution, 'the project manager discovers that a key supplier is having .financial difficultyand could discontinue operations. What should the project manager do to address the issue?
A, Organize a vendor conference and select a new supplier,
B. Request a quote from another supplier for the outstanding work,
C. Cancel the existing contract and award a similar contract to another supplier. D. Implement the risk response plan to control the risk
125.项目执行过程中,项目经理发现一个关键供应商正经历财务困难,可能中断工作。项目经理应该如何解决这个问题?
A.组织一次供应商会议,并选择一个新的供应商。 B.请求另一个供应商对剩余工作报价。
C.取消现有合同并向另一个供应商授予类似合同。
D.实施风险应对计划,控制风险。
126. A project team reports that the peer review process has non-valued activities. The quality team must review the observations and process the overall adherence. Which of the following does the quality team perform? A. Quality adherence B. Quality audit C. Quality control D. Quality assurance
126.项目团队报告同行评审过程存在无价值的活动。质量团队必须审查观察结果并处理整体一致性。质量团队执行的是下列哪一项? A.质量一致性 B.质量审计 C.质量控制 D.质量保证
127. A project manager is assigned a project with a demanding client. The project is dynamic requires constant improvements and client feedback. Which of the following approaches should the project manager adopt for this project ?
A. Extreme project management approach, as the project’s goal is unclear: B. Agile project management approach, as it is fast and iterative
C. Traditional project management approach, as it is simple and intuitive D. Lean six-sigma management approach, as it fits the project constraints
127.项目经理被分配管理一个要求苛刻客户的项目,项目是动态的,要求持续改进以及客户反馈。
项目经理应该为该项目采用下列哪一个方法? A.极端项目管理方法,因为项目目标不明确 B.敏捷项目管理方法,因为其快速且具有重复性 C.传统项目管理方法,因为其简单且直观
D.精益六西格玛管理方法,因为其审核项目的约束和限制
128. During project closing, the project manager reviews the deliverables with the customer. The customer expresses concern about a deliverable, and both parties agree that it does not comply with the requirements specification document. What should the project manager do-next? A. Accept the issue as a defect and create a change request. B. Evaluate the change. And update project documents.
C. Use a requirement traceability matrix to verify completed requirements. D. Establish that deliverables were validated by a key user.
128.在项目收尾期间,项目经理与客户一起审查可交付成果。客户表示对其中一个可交付成果的担心,且双方都一致认为该可交付成果不符合需求规范文档。 项目经理接下来应该怎么做?
A. 接受这个问题为缺陷,并创建变更请求 B. 评价变更并更新项目文档
C. 使用需求跟踪矩阵,核实已完成的需求
D. 证明该可交付成果已经由一名关键用户核实
129. In a project to upgrade a company’s accounting application, the project manager sends weekly emails regarding the project’s status and the next activities. A key user of the application complains that application outages are affecting their work performance. What should the project manager do next?
A. Continue working according to planned activities. B. Report the key user to their supervisor.
C. Review the stakeholder analysis and update to include the key user.
D.Review the stakeholder analysis and inform all stakeholders to include the key user in all emails 129.在升级公司的会计应用程序项目中,项目经理每周发送一次有关项目状态以及后续活动的电子邮件。该应用程序的以为关键用户抱怨应用程序影响他们的工作绩效。 项目经理接下来应该怎么做? A. 按照计划活动继续工作
B. 向主管报告该关键用户的情况
C. 审查干系人分析并更新包含该关键用户
D. 审核干系人分析并通知所有干系人将该关键用户包含在所有电子邮件中
130. A team member complains to the project manager about the lack of praise for their achievements. To avoid this issue, what should the project manager have conducted in the develop project team phase? A. Personnel assessment tools B. Team performance assessment C. Recognition and rewards
D. Human resource management plan
130.一名团队成员向项目经理抱怨项目缺乏对他们所取得成就的鼓励。为避免这个问题,项目经理应在建设项目团队阶段开展哪一项? A. 人员评估工具 B. 团队绩效评估 C. 认可与奖励
D. 人力资源管理计划
131. After the project team has brainstormed project risks, what should the project manager do next?
A. Analyze and prioritize the risk. B, Assign risk owner
C. Identify risk mitigation strategies, D. Report the risks to the stakeholders.
131.在项目团队对项目风险头脑风暴后,项目经理下一步应该怎么做? A. 分析并进行风险有限排序 B. 分配风险负责人 C. 确定风险减轻战略 D. 向干系人报告风险
132. After completing the final development of the produce, the project manager is ready to
transfer the ownership of the project’s deliverables to the on-going support team. Which of the following is an input for the project’s next phase? A. lessons learned
B. Project scope statement C. Project management plan D. Completed milestone list 132.完成产品的最终开发之后,项目经理准备向项目可交付成果的所有权移交给持续支持团队。下列哪一项属于项目下一个阶段的输入? A.经验教训
B.项目范围说明书 C.项目管理计划
D. 已完成的里程碑清单
133. Local community leaders express concern regarding the start of a construction project, which could cause delays to the project. The project manager would like to analyze and document.
A. Power/interest grid
B. Communications management plan
C. Stakeholders engagement assessment matrix D. Stakeholder register
133.当地社区领导表达对开始一个施工项目的担忧,这可能会导致项目延期。项目经理想要分析并记录已识别关键项目干系人的想法。 项目经理应该使用下列哪一项? A. 权利/利益方格 B. 沟通管理计划
C. 干系人参与评估矩阵 D. 干系人登记册
134. A project manager obtains seller responses, as well as selects a seller to provide one of project’s key components. The project manager completed which of the following processes? A. Control Procurements
B. Direct and Manage Project Work C. Plan Procurement Management D. Conduct Procurements
134.项目经理获得供应商回复,并选择了一名供应商提供项目的其中一个关键组成部分。项目经理完成的是下列哪一个过程? A. 控制采购
B. 知道和管理项目工作 C. 规划采购管理 D. 进行采购
135. A project manager is asked to estimate an activity's duration. Using historical information, the project manager learns that this activity has routinely taken 12 days to complete. The project anger’s colleague works on a similar project and performed the activity in 10 days. However, the
functional area expert states that, due to challenges on the project, it will take 18 days to complete, IF the project manager uses PERT estimation, what would be the activity’s duration? A. 12days B. 12.7days C. 15.7days D. 18days
135.项目经理被要求估算一项活动的持续时间,利用历史信息,项目经理了解到这个项目活动通常需要12天时间完成。项目经理的同事正在管理一个类似项目,并在10天内执行了这项活动。但是,职能领域的专家指出,由于项目中的存在的挑战,将需要18天时间完成。 如果项目经理使用PERT估算,那么这项目活动的持续时间将是多少天? A.12天 B.12.7天 C.15.7天 D.18天
136. After a project review, the project manager asks a technical lead to conduct a causal analysis of all the incidents and then prioritize the incidents. Which of the following tools and techniques should be used? A. PERT analysis B. Monte Carlo C. Pareto chart D. Scatter diagram
136.项目审查之后,项目经理要求技术主管对所有事故开展因果分析,然后将事故排列优先顺序。应该使用下列哪一项工具和技术? A.PERT分析 B.蒙特卡洛分析 c.帕累托图 D.散点图
137. Due to an interpersonal conflict between two team members, team morale and productivity are negatively affected, what conflict management technique should the project manager use to resolve the conflict immediately? A. Smooth/Accommodate B. TVwithdraw/Avoid C. Compromise/Reconcile D. Force/Direct
137.由于两名团队成员之间的人际冲突,团队士气和生产力受到不利影响。项目经理应使用什么冲突管理技术来立即解决冲突? A.缓解/包容 B.撤退/回避 C.妥协/调节 D.强迫/命令
138. Each time a project component is tested, the component passes user acceptance testing and fulfills all requirements, what process did the project manager implement and execute repeatedly?
A. Control Quality
B. Perform Quality Assurance C. Configuration Analysis D. Sponsor Reviews
138.每次测试项目部件,该部件都通过用户的验收测试并满足所有需求。项目经理反复实施和执行哪一个过程? A.控制质量 B.执行质量保证 C.配置分析 D.发起人审查
139. A project change is identified. However, due to a high risk to the overall project, the change request board projects the change. What should the project manager do next? A. Communicate this to the project management office. B. Schedule a corrective action.
C. Record rejected change request in the change log.. D. Update the project scope statement.
139.一个项目变更已确定。但是,由于整个项目的风险较高,变更请求委员会拒绝变更。项目经理接下来应该怎么做? A.与项目管理办公室沟通。 B.安排纠正措施。
C.在变更日志记录拒绝的变更请求。 D.更新项目范围说明书。
140. A project manager schedules weekly team meetings according to the communications management plan. Some team members report conflicts with the time and- miss some of the meetings. What should the project manager do next? A. Provide minutes for all meetings.
B. Reschedule a compatible time for all team members.
C. Apologize and explain difficulty in aligning at team members. D. Meet with each team member separately
140.项目经理按照沟通管理计划安排了团队周会。一些团队成员提出由于时间上有冲突,缺席某些会议。项目经理接下来应该怎么做? A.提供所有会议的会议记录。
B.重新安排一个对所有团队成员都适合的时间。 C.道歉并说明协调所有团队成员的难度。 D.与每名团队成员单独开会。
141. During project execution, the project manager learns that the project sponsor will send a
正在阅读:
PMP考试官方样题03-04
泰戈尔《生如夏花》08-11
小学体育器材室管理制度01-25
成本会计实操110-08
机关干部2017年年度考核个人总结范文12-29
20XX年小学校健康教育计划12-02
全国2013年01月自学考试00159《高级财务会计》历年真题及参考答案01-30
5超说明书用药2012080305-18
第17章 屈曲分析05-09
- 多层物业服务方案
- (审判实务)习惯法与少数民族地区民间纠纷解决问题(孙 潋)
- 人教版新课标六年级下册语文全册教案
- 词语打卡
- photoshop实习报告
- 钢结构设计原理综合测试2
- 2014年期末练习题
- 高中数学中的逆向思维解题方法探讨
- 名师原创 全国通用2014-2015学年高二寒假作业 政治(一)Word版
- 北航《建筑结构检测鉴定与加固》在线作业三
- XX县卫生监督所工程建设项目可行性研究报告
- 小学四年级观察作文经典评语
- 浅谈110KV变电站电气一次设计-程泉焱(1)
- 安全员考试题库
- 国家电网公司变电运维管理规定(试行)
- 义务教育课程标准稿征求意见提纲
- 教学秘书面试技巧
- 钢结构工程施工组织设计
- 水利工程概论论文
- 09届九年级数学第四次模拟试卷
- 官方
- 考试
- PMP
- 宁夏观赏石研究会成立大会圆满成功
- 乡镇干部精神文明建设先进个人材料
- 未来函数
- 乡村公路养护工程施工组织设计
- 新课标人教版小学数学第八册教学计划
- 9排列组合、二项式定理、概率及统计
- 计算机组成原理课后答案(1)
- 19清华大学继续教育国际合作的实践与启示
- Unit 4 Keeping clean知识点归纳
- 七年级英语上册《Unit 4-5》导学案
- 云台小学学习教师职业道德规范方案
- 宏基因组实验计划 - 图文
- 自我介绍信模版
- 房地产新售楼部物料清单
- 中职语文职业模块教案
- Photoshop 中文教程 - 图文
- b浙江暴雨强度公式建设发2008(89)文件 - 图文
- 电功率计算公式精编汇总
- 会计11出纳实务试卷(B)评分标准
- 环境管理期末考试复习资料