恒大地产集团住宅室内装饰施工工艺和质量标准 - 图文

更新时间:2023-10-10 09:22:01 阅读量: 综合文库 文档下载

说明:文章内容仅供预览,部分内容可能不全。下载后的文档,内容与下面显示的完全一致。下载之前请确认下面内容是否您想要的,是否完整无缺。

目录

第一章 住宅室内装修工序间歇及工艺间歇标准······························3 1.1墙面各工序间歇及工艺间歇要求标准··································· ········3 1.2地面各工序间歇及工艺间歇要求标准············································3 1.3木地板施工基层要求标准································································4 1.4细部处理各工艺间歇要求标准························································4 1.5其它装修施工要求············································································4 第二章 住宅室内装修工艺流程标准·····················································5 第三章 住宅室内装修施工工艺和质量标准····························· ···········6 3.1场地移交····························································································6 3.2弹线···································································································10 3.3电线穿管····················· ······································································14 3.4卧室地面找平···················································································15 3.5墙面砖铺装·······················································································17 3.6墙面石材铺装···················································································23 3.7天花吊顶、石膏线安装·····································································28 3.8入户门安装·······················································································31 3.9地面砖、石材铺贴·············································································34 3.10窗台石铺贴·····················································································40 3.11天花墙面扇灰、涂饰乳胶漆···························································42 3.12墙面造型制作、安装·······································································47 3.13橱柜、卫浴安装················································································51 3.14户内门安装······················································································57 3.15木地板安装······················································································63 3.16墙面玻璃镜面安装·········································································70

1

3.17墙面木饰面造型油漆·····································································70 3.18墙纸贴铺·························································································73 3.19阳台护栏安装·················································································77 3.20低窗护栏安装·················································································78 3.21墙面软包制作安装·········································································80 3.22灯具、插座开关面板安装·······························································82 3.23卫生洁具安装·················································································97 3.24卫浴五金安装···············································································104 3.25淋浴隔断安装···············································································105 3.26细部处理·······················································································106 3.27石材镜面处理···············································································114 3.28卫生清理·······················································································116

2

恒大地产集团

住宅室内装修施工工艺和质量标准(试行)

施工工序原则:先上后下、先湿后干、先内后外、先粗后细、先制作后安装。

第一章 住宅室内装修工序间歇及工艺间歇标准

1.1墙面各工序间歇及工艺间歇要求标准

≥28天 ≥28天 ≥15-20天 ≥7天 砌体 墙面抹灰 主体结构工艺要求 工艺要求 工艺要求 刮腻子涂料 \\ 墙纸 小高层 结构至8层,中高 层、高层结构施 工至12层时,砌体可开始施工。 1、 一次砌 筑高度不大于1.8米,间歇1天后再砌筑施工。 2、 顶砖(或 顶膨胀混凝土浇筑)施工,须砌体完成7天后进行。 1、 南方地区: 秋、冬季墙面含水率不大于12﹪,春、夏季墙面含水率不大于14﹪时可刮装饰腻子。 2、 北方地区: 统一控制墙面含水率不大于12﹪时即可刮装饰腻子。 1、 根据墙 面基层平整度,可进行2~3遍刮装饰腻子。 2、 每两遍 装饰腻子施工干燥间歇时间为不小于48小时。 1、 南方春、夏 季基层含水率不大于12﹪,北方地区及南方秋、冬季基层含水率均不大于8﹪。 2、 每两遍涂 料(墙纸基层底油)间歇时间为不小于48小时。

1.2地面各工序间歇及工艺间歇要求标准

1、卧室木地板、地毯等基层地面找平完成后,可上人作业间歇时

3

间为不小于48小时。

2、客厅、餐厅、厨房、卫生间、阳台、电梯前室、首层大堂等地面砖、石材铺贴完成后,可上人作业间歇时间为不小于48小时。

3、室内地面砖、石材及地面找平完成后,墙面1米线以下墙体刮装饰腻子需要间歇不小于15-20天,其要求含水率不大于14﹪。

1.3木地板施工基层要求标准

木地板地面基层含水率标准一览表

地区 南 季节 春、夏 秋、冬

1.4细部处理各工艺间歇要求标准

1、厨房、卫生间、阳台、电梯前室、首层大堂等墙面砖采用湿贴工艺,砖缝水泥清理所需间歇时间为3-6小时。

2、墙面、地面、台面等湿贴作业完成后,需钻孔、打眼等间歇时间不小于14天。

3、各交界面细部处理打胶后,与卫生清理间歇时间不小于24小时。 4、入户门门框安装后,门扇安装所需间歇时间不小于72小时;户内门门框安装后,门扇安装所需间歇时间不小于24小时。

1.5其它装修施工要求

1、小高层结构至8层,中高层、高层结构施工至12层,砌体开始施工时,装修施工单位定标、不少于2名装修管理人员到位。 3、外立面装饰完成10层,外脚手架拆除上面5层,且卫生清理

4

北 ≤8﹪ ≤8﹪ ≤12﹪ ≤8﹪

完毕,进行场地移交,装修施工人员全部到位。

4、小高层分2批移交,每批5层,移交间歇时间15天;中高层、高层分3批移交,第1批5层,第2、3批移交10层左右,流水施工作业。

第二章 住宅室内装修工艺流程标准

电线穿管配线

天花吊顶、石膏线安装 入户门框安装 场地移交 弹线 卧室地面找平 厨卫墙砖、石材铺贴 墙面造型制作 橱柜、卫浴安装 入户门套、门扇、门锁及户内门框安装 地面砖、石材铺贴 天花、墙面扇灰涂饰底漆 窗台石铺贴 天花、墙面打磨涂饰面漆 墙面造型饰面安装 木地板基层安装 户内门套线安装 低窗护栏安装 灯具、开关面板、水龙头安装 墙纸铺贴 户内门扇安装 卫生清理 细部处理 交楼、安装室内五金配件 卫生清理至五星级标准 木地板、地脚线安装