标准化钢筋加工场方案
更新时间:2024-02-01 23:51:01 阅读量: 教育文库 文档下载
武汉城市圈环线高速公路洪湖段第二标段 目录
钢筋加工场标准化建设方案
1.工程概况 ························································································ 1 2.钢筋加工场布置原则 ········································································· 1 3.钢筋加工场选址 ··············································································· 1 4.场地建设 ························································································ 1 4.1 标准化钢筋加工场场地建设 ·························································· 1 4.1.1 1#标准化钢筋加工场建设 ························································· 2 4.1.2 2#标准化钢筋加工场建设 ························································· 3 4.2 下构钢筋加工场场地建设 ····························································· 5 4.2.1 1#下构钢筋加工场建设 ···························································· 5 4.2.2 2#下构钢筋加工场建设 ···························································· 6 4.2.3 3#下构钢筋加工场建设 ···························································· 7 4.2.4 4#下构钢筋加工场建设 ···························································· 7 4.2.5 5#下构钢筋加工场建设 ···························································· 8 5.钢筋加工设备及成品钢筋运输车配置 ···················································· 9 6.钢筋加工场人员配置 ········································································· 9 7.安全保障措施 ·················································································· 9 8.文明施工措施 ················································································· 10 9.环境保护 ······················································································· 11 10.附件: ························································································· 11
武汉城市圈环线高速公路洪湖段第二标段
武汉城市圈环线高速公路洪湖段第二标段 钢筋加工厂标准化建设方案
钢筋加工场标准化建设方案
1.工程概况
武汉城市圈环线高速公路洪湖段武汉城市圈环线高速公路的重要组成部分,路线总长19.796km,起点至洪湖东枢纽互通段采用双向四车道高速公路标准建设,设计时速100公里/小时,路基宽度26.0米;洪湖东枢纽互通至终点段采用双向六车道高速公路标准建设,设计时速100公里/小时,路基宽度33.5米。本标段为2标,标段号为HHTJ-2。起止桩号K185+681~K195+641,路线全长9.960km。全线设特大桥4座,大桥1座,设互通式立交1处,服务区1处。主要工程量为:钻孔灌注桩(直径1.5m或1.8m)1556根,共80864m;预制小箱梁2910片。合计钢筋制安6.39万吨。
2.钢筋加工场布置原则
根据《仙洪高速公路标准化建设实施细则》要求,遵循“因地制宜,节约土地,保护环境,安全可靠,规范有序,功能完备,布设合理,方便生活,满足生产”的原则。本标段共设两处标准化钢筋加工场五处下构钢筋加工场。
3.钢筋加工场选址
根据《仙洪高速公路标准化建设实施细则》要求,结合本标段的实际工程及地形情况,为配合箱梁预制施工,决定将两处标准化钢筋加工场与1#和2#箱梁预制场布置在一起,分别为1#和2#标准化钢筋加工场,另外设置五处下构钢筋加工场。钢筋加工场位置分别为:1#标准化钢筋加工场在K192+101处左侧(3000㎡);2#标准化钢筋加工场在K195+000处右侧(3600㎡);1#下构钢筋加工场在K185+801左侧(2900㎡);2#下构钢筋加工场在K189+671右侧(2000㎡);3#下构钢筋加工场在K192+780左侧(1350㎡);4#下构钢筋加工场在K195+080处右侧(1600㎡)。5#下构钢筋加工场在K187+001左侧(1600㎡)。
后附钢筋加工场平面位置示意图。
4.场地建设
4.1 标准化钢筋加工场场地建设
本标段设标准化钢筋加工场2个,分别设立于K192+101、K195+000,1#标准化钢筋加工场供大沙湖特大桥、大沙湖服务区盖梁、预制箱梁钢筋加工使用;
武汉城市圈环线高速公路洪湖段第二标段 1
武汉城市圈环线高速公路洪湖段第二标段 钢筋加工厂标准化建设方案
2#标准化钢筋加工场供宋家沟特大桥、燕窝互通、团结大桥盖梁、预制箱梁钢筋加工使用。
4.1.1 1#标准化钢筋加工场建设
1#标准化钢筋加工场设立于K192+101,与1#标准化梁场加工区及1#拌合站相邻,场区占地面积3000㎡,分HPB300钢筋堆放区、HPB300钢筋调直区、3个HRB400钢筋堆放区、3个HRB400钢筋加工区、6个半成品存放区,入门左侧HRB400钢筋加工区为“16筋”加工区,中间为“25筋”加工区,右侧为“12筋”加工区。场内设立2台10t龙门吊,左侧龙门吊供“16筋”加工区与“25筋”加工区使用,右侧龙门吊供“12筋”加工区与“25筋”加工区使用。
(1)场区处理:钢筋加工场内采用20cm厚毛渣回填,碾压密实后采用20cm厚C20混凝土硬化,横向每隔12m进行切缝处理,场地纵向6m处切缝处理,防止不均匀沉降造成场地开裂。
(2)场区道路采用:原地面采用30cm毛碴回填,碾压密实后场地采用厚度25cmC30混凝土进行硬化,路面宽4.5m,路面坡度为双向1.5%,两边设置0.5m排水沟,道路边线距离钢筋功能区0.5m,道路每隔30m设置沉降缝,路面每隔6m进行切缝处理。
(3)场区硬化为中间高,两侧低,坡比为1.5%,场内水流向外侧的排水沟(50cm×50cm)。排水沟采用“24砖”砌筑后M7.5砂浆抹面。
(4)场区顶棚使用彩钢瓦进行全面覆盖,钢筋棚起拱高度12m。钢筋加工场围墙设置在已经硬化的场地边缘,绕钢筋加工场一周,围墙使用彩钢瓦。
(5)进场原材料堆放区:进场原材料堆放区分为1个HPB300钢筋堆放区和3个HRB400钢筋堆放区。HPB300钢筋堆放区台座面宽4m,长12m,使用C20混凝土浇筑,两台座间距60cm,单条台座宽40cm,高40cm,长12m;HRB400钢筋堆放区台座面宽9m,长12m,使用C20混凝土浇筑,两台座间距4m,单条台座宽40cm,高40cm,长9m。
(6)钢筋加工区:钢筋加工区分“16筋”加工区、“25筋”加工区、“12筋”加工区,安装两台龙门吊供使用,钢筋加工区明显位置设标识牌,标明各材料名称、产地、规格型号、生产日期、出产批号、进场日期、检验状态、进场数量等,根据不同的检验状态和结果分区存放合格材料与不合格材料。
(7)进场大门:进场大门高5m,宽9m,采用轨道式双向移动铁门,下设
武汉城市圈环线高速公路洪湖段第二标段 2
武汉城市圈环线高速公路洪湖段第二标段 钢筋加工厂标准化建设方案
大门滑轮轨道。
(8)标示标牌
1)大门口处设置加工场铭牌,铭牌名称分别为:湖北交投武汉城市圈环线高速公路仙洪段第二合同段1号标准化钢筋加工场,尺寸为80cm×60cm。
2)在大门正对面醒目处设置八牌一图(工程概况牌、管理人员名单及监督电话牌、质量保证牌、安全生产牌、消防保卫牌、文明施工牌、风险告知牌、安全警示牌、施工现场布置图),采用铝合金制作,材质采用镀锌铁皮,铝合金框,尺寸2.5m×2m,标牌底距地面120cm。
3)钢筋场内部钢筋制作区布置各分项工程钢筋大样图,尺寸均为18m×2.6m。
4)钢筋场顶棚下挂钢筋区标识牌,尺寸为60cm×100cm。加工区设置警示、警告标志。成品半成品区设置检验标识牌,尺寸为60cm×90cm。
5)焊接、用电等场所设置禁止警示牌。
6)机械设备悬挂机械操作安全规定公示牌和设备标识牌。
7)各种原材料、半成品或成品按其检验状态与结果、使用部位等进行标识。 8)在加工制作区悬挂各号钢筋的大样设计图,标明尺寸、部位,确保下料及加工准确。
4.1.2 2#标准化钢筋加工场建设
2#标准化钢筋加工场设立于K195+000,与2#标准化梁场加工区及2#拌合站相邻,场区占地面积3600㎡,分HPB300钢筋堆放区、HPB300钢筋调直区、HPB300钢筋下料区、HPB300钢筋加工区、HRB400钢筋存放区、HRB400钢筋下料区、HRB400钢筋加工区、2个半成品区和两个成品区,场内设立2台5t龙门吊供钢筋堆放及加工使用。
(1)场区处理:钢筋加工场内采用20cm厚毛渣回填,碾压密实后采用20cm厚C20混凝土硬化,横向每隔12m进行切缝处理,场地纵向6m处切缝处理,防止不均匀沉降造成场地开裂。
(2)场区道路采用:原地面采用30cm毛碴回填,碾压密实后场地采用厚度25cmC30混凝土进行硬化,路面宽4.5m,路面坡度为双向1.5%,两边设置0.5m排水沟,道路边线距离钢筋功能区0.5m,道路每隔30m设置沉降缝,路面每隔6m进行切缝处理。
武汉城市圈环线高速公路洪湖段第二标段 3
武汉城市圈环线高速公路洪湖段第二标段 钢筋加工厂标准化建设方案
(3)场区做成中高边低的地面,水流向场区外侧设置的排水沟(50cm×50cm)。排水沟采用“24砖”砌筑后M7.5砂浆抹面。
(4)钢筋场顶棚使用彩钢瓦全部覆盖,钢筋棚起拱高度12m。
(5)进场原材堆放区:堆放区地面砌筑钢筋堆放台座,原材料堆放区分为2个区。分别为三级钢堆放区和一级钢堆放区,三级钢堆放区台座区宽9m,长12m,两台座间距4m,台座用C20混凝土浇筑,抹4cmM7.5水泥砂浆。单条台座高40cm,宽40cm,长9m。 一级钢堆放区宽5m,长12m,两台座间距60cm,单条台座高40cm,宽40cm。长12m。
(6)钢筋下料加工区、成品、半成品堆放区:使用混凝土浇筑台座,台座宽40cm,高40cm,HPB300钢筋下料加工区台座面宽9m,长33m,HRB400钢筋下料加工区台座面宽5m,长33m。HRB400台座间距宽4m,单条台座宽40cm,高40cm,长9m;HPB300台座间距宽60cm,单条台座宽40cm,高40cm,长12m。成品区分待检区和已检区,两区域在明显位置设标识牌,标明各材料名称、产地、规格型号、生产日期、出产批号、进场日期、检验状态、进场数量等,根据不同的检验状态和结果分区存放合格材料与不合格材料。
(7)废料区:设置在成品区旁,加工过程产生的废料集中堆放处理。 (8)围墙和大门:钢筋加工场围墙设置在已经硬化的场地边缘,绕钢筋加工场一周,围墙使用彩钢瓦。大门采用高5m,宽9m的轨道式双向移动铁门。
(9)标示标牌
1)大门口处设置加工场铭牌,铭牌名称分别为:湖北交投武汉城市圈环线高速公路仙洪段第二合同段2号标准化钢筋加工场,尺寸为80cm×60cm。
2)在大门正对面醒目处设置八牌一图(工程概况牌、管理人员名单及监督电话牌、质量保证牌、安全生产牌、消防保卫牌、文明施工牌、风险告知牌、安全警示牌、施工现场布置图),采用铝合金制作,材质采用镀锌铁皮,铝合金框,尺寸2.5m×2m,标牌底距地面120cm;
3)钢筋场内部钢筋制作区布置各分项工程钢筋大样图,尺寸均为18m×2.6m。
4)钢筋场顶棚下挂钢筋区标识牌,尺寸为60cm×100cm。加工区设置警示、警告标志。成品半成品区设置检验标识牌,尺寸为60cm×90cm。
5)焊接、用电等场所设置禁止警示牌;
武汉城市圈环线高速公路洪湖段第二标段 4
武汉城市圈环线高速公路洪湖段第二标段 钢筋加工厂标准化建设方案
6)机械设备悬挂机械操作安全规定公示牌和设备标识牌;
7)各种原材料、半成品或成品按其检验状态与结果、使用部位等进行标识。 8)在加工制作区悬挂各号钢筋的大样设计图,标明尺寸、部位,确保下料及加工准确。
4.2 下构钢筋加工场场地建设
本标段设下构钢筋加工场5个,1#、2#、5#下构钢筋加工场分别设在K185+801、K187+001、K189+671,供大沙湖特大桥及大沙湖服务区钢筋加工使用;3#、4#下构钢筋加工场设在K192+780~K195+080,分别供宋家沟特大桥、燕窝互通、团结大桥钢筋加工使用。 4.2.1 1#下构钢筋加工场建设
1#下构钢筋场设在K185+801,供大沙湖特大桥桩基、系梁、墩柱钢筋加工使用,占地面积2900㎡。
(1)场区处理:用装载机、挖掘机清除原地面表层的杂草、有机土、种植土等再整平原地面,整平后用20t振动压路机压实,最后采用15cm厚C20混凝土硬化。
(2)场区地面设双面1.5%坡度,场区水向场内道路两侧的排水沟(30cm×30cm)及场区外侧的排水沟(50cm×50cm)排放。场区道路路面坡度为双向1.5%,排水沟采用“24砖”砌筑后M7.5砂浆抹面。
(3)进场原材堆放区:采用轻型钢结构搭设移动式防雨棚,雨棚顶采用彩钢瓦搭建,顶棚起拱高度6m。地面砌筑钢筋堆放台座,台座用C20混凝土浇筑,抹4cmM7.5水泥砂浆。单条台座高40cm,宽40cm,长9m。台座区宽9m,长12m,两台座间距3m。
(4)成品、半成品堆放区:制作固定雨棚,顶棚起拱高度7m。成品、半成品堆放使用20cm×20cm的木方将钢筋垫起。成品区分待检区和已检区,两区域明显位置设标识牌,避免材料混淆。
(5)围墙和大门:钢筋加工场围墙设置在已经硬化的场地边缘,采用彩钢瓦围护,绕钢筋加工场一周。大门采用高4m,宽5m的轨道式双向移动铁门。
(6)标示标牌
1)大门口处设置加工场铭牌,铭牌名称分别为:湖北交投武汉城市圈环线高速公路仙洪段第二合同段1号下构钢筋加工场,尺寸为80cm×60cm。
武汉城市圈环线高速公路洪湖段第二标段 5
武汉城市圈环线高速公路洪湖段第二标段 钢筋加工厂标准化建设方案
2)钢筋场内墙两侧设质量保证牌、安全生产牌采用铝合金制作,材质采用镀锌铁皮,铝合金框,尺寸2.5m×2m,标牌底距地面120cm。
3)焊接、用电等场所设置禁止警示牌。
4)机械设备悬挂机械操作安全规定公示牌和设备标识牌。
5)各种原材料、半成品或成品按其检验状态与结果、使用部位等进行标识。 4.2.2 2#下构钢筋加工场建设
2#下构钢筋场设在K187+001,供大沙湖特大桥桩基、系梁、墩柱钢筋加工使用,占地面积2000㎡
(1)场区处理:用装载机、挖掘机清除原地面表层的杂草、有机土、种植土等再整平原地面,整平后用20t振动压路机压实,最后采用15cm厚C20混凝土硬化。
(2)场区地面设双面1.5%坡度,场区水向场内道路两侧的排水沟(30cm×30cm)及场区外侧的排水沟(50cm×50cm)排放。场区道路路面坡度为双向1.5%,排水沟采用“24砖”砌筑后M7.5砂浆抹面。
(3)进场原材堆放区:采用轻型钢结构搭设移动式防雨棚,雨棚顶采用彩钢瓦搭建,顶棚起拱高度6m。地面砌筑钢筋堆放台座,台座用C20混凝土浇筑,抹4cmM7.5水泥砂浆。单条台座高40cm,宽40cm,长9m。台座区宽9m,长12m,两台座间距3m。
(4)成品、半成品堆放区:制作固定雨棚,顶棚起拱高度7m。成品、半成品堆放使用20cm×20cm的木方将钢筋垫起。成品区分待检区和已检区,两区域明显位置设标识牌,避免材料混淆。
(5)围墙和大门:钢筋加工场围墙设置在已经硬化的场地边缘,采用彩钢瓦围护,绕钢筋加工场一周。大门采用高4m,宽5m的轨道式双向移动铁门。
(6)标示标牌
1)大门口处设置加工场铭牌,铭牌名称分别为:湖北交投武汉城市圈环线高速公路仙洪段第二合同段1号下构钢筋加工场,尺寸为80cm×60cm。
2)钢筋场内墙两侧设质量保证牌、安全生产牌采用铝合金制作,材质采用镀锌铁皮,铝合金框,尺寸2.5m×2m,标牌底距地面120cm。
3)焊接、用电等场所设置禁止警示牌。
4)机械设备悬挂机械操作安全规定公示牌和设备标识牌。
武汉城市圈环线高速公路洪湖段第二标段 6
武汉城市圈环线高速公路洪湖段第二标段 钢筋加工厂标准化建设方案
5)各种原材料、半成品或成品按其检验状态与结果、使用部位等进行标识。 4.2.3 3#下构钢筋加工场建设
3#下构钢筋场设在K192+780,供宋家沟特大桥桩基、系梁、墩柱钢筋加工使用,占地面积1350㎡
(1)场区处理:用装载机、挖掘机清除原地面表层的杂草、有机土、种植土等再整平原地面,整平后用20t振动压路机压实,最后采用15cm厚C20混凝土硬化。
(2)场区地面设双面1.5%坡度,场区水向场区外侧的排水沟(50cm×50cm)排放。场区地面坡度为双向1.5%,排水沟采用“24砖”砌筑后M7.5砂浆抹面。
(3)进场原材堆放区:采用轻型钢结构搭设移动式防雨棚,雨棚顶采用彩钢瓦搭建,顶棚起拱高度6m。地面砌筑钢筋堆放台座,台座用C20混凝土浇筑,抹4cmM7.5水泥砂浆。单条台座高40cm,宽40cm,长9m。台座区宽9m,长12m,两台座间距3m。
(4)成品、半成品堆放区:制作固定雨棚,顶棚起拱高度7m。成品、半成品堆放使用20cm×20cm的木方将钢筋垫起。成品区分待检区和已检区,两区域明显位置设标识牌,避免材料混淆。
(5)围墙和大门:钢筋加工场围墙设置在已经硬化的场地边缘,采用彩钢瓦围护,绕钢筋加工场一周。大门采用高4m,宽5m的轨道式双向移动铁门。
(6)标示标牌
1)大门口处设置加工场铭牌,铭牌名称分别为:湖北交投武汉城市圈环线高速公路仙洪段第二合同段1号下构钢筋加工场,尺寸为80cm×60cm。
2)钢筋场内墙两侧设质量保证牌、安全生产牌采用铝合金制作,材质采用镀锌铁皮,铝合金框,尺寸2.5m×2m,标牌底距地面120cm。
3)焊接、用电等场所设置禁止警示牌。
4)机械设备悬挂机械操作安全规定公示牌和设备标识牌。
5)各种原材料、半成品或成品按其检验状态与结果、使用部位等进行标识。 4.2.4 4#下构钢筋加工场建设
4#下构钢筋加工场设在K195+080,供燕窝互通、团结大桥桩基、系梁、墩柱钢筋加工使用,占地面积1600㎡
(1)场区处理:用装载机、挖掘机清除原地面表层的杂草、有机土、种植
武汉城市圈环线高速公路洪湖段第二标段 7
武汉城市圈环线高速公路洪湖段第二标段 钢筋加工厂标准化建设方案
土等再整平原地面,整平后用20t振动压路机压实,最后采用15cm厚C20混凝土硬化。
(2)场区地面设双面1.5%坡度,场区水向场区外侧的排水沟(50cm×50cm)排放。场区地面坡度为双向1.5%,排水沟采用“24砖”砌筑后M7.5砂浆抹面。
(3)进场原材堆放区:采用轻型钢结构搭设移动式防雨棚,雨棚顶采用彩钢瓦搭建,顶棚起拱高度6m。地面砌筑钢筋堆放台座,台座用C20混凝土浇筑,抹4cmM7.5水泥砂浆。单条台座高40cm,宽40cm,长9m。台座区宽9m,长12m,两台座间距3m。
(4)成品、半成品堆放区:制作固定雨棚,顶棚起拱高度7m。成品、半成品堆放使用20cm×20cm的木方将钢筋垫起。成品区分待检区和已检区,两区域明显位置设标识牌,避免材料混淆。
(5)围墙和大门:钢筋加工场围墙设置在已经硬化的场地边缘,采用彩钢瓦围护,绕钢筋加工场一周。大门采用高4m,宽5m的轨道式双向移动铁门。
(6)标示标牌
1)大门口处设置加工场铭牌,铭牌名称分别为:湖北交投武汉城市圈环线高速公路仙洪段第二合同段1号下构钢筋加工场,尺寸为80cm×60cm。
2)钢筋场内墙两侧设质量保证牌、安全生产牌采用铝合金制作,材质采用镀锌铁皮,铝合金框,尺寸2.5m×2m,标牌底距地面120cm。
3)焊接、用电等场所设置禁止警示牌。
4)机械设备悬挂机械操作安全规定公示牌和设备标识牌。
5)各种原材料、半成品或成品按其检验状态与结果、使用部位等进行标识。 4.2.5 5#下构钢筋加工场建设
5#下构钢筋加工场设在K187+001,供大沙湖特大桥桩基、系梁、墩柱钢筋加工使用,占地面积1600㎡。
(1)场区处理:用装载机、挖掘机清除原地面表层的杂草、有机土、种植土等再整平原地面,整平后用20t振动压路机压实,最后采用15cm厚C20混凝土硬化。
(2)场区地面设双面1.5%坡度,场区水向场区外侧的排水沟(50cm×50cm)排放。场区地面坡度为双向1.5%,排水沟采用“24砖”砌筑后M7.5砂浆抹面。
(3)进场原材堆放区:采用轻型钢结构搭设移动式防雨棚,雨棚顶采用彩
武汉城市圈环线高速公路洪湖段第二标段 8
武汉城市圈环线高速公路洪湖段第二标段 钢筋加工厂标准化建设方案
钢瓦搭建,顶棚起拱高度6m。地面砌筑钢筋堆放台座,台座用C20混凝土浇筑,抹4cmM7.5水泥砂浆。单条台座高40cm,宽40cm,长9m。台座区宽9m,长12m,两台座间距3m。
(4)成品、半成品堆放区:制作固定雨棚,顶棚起拱高度7m。成品、半成品堆放使用20cm×20cm的木方将钢筋垫起。成品区分待检区和已检区,两区域明显位置设标识牌,避免材料混淆。
(5)围墙和大门:钢筋加工场围墙设置在已经硬化的场地边缘,采用彩钢瓦围护,绕钢筋加工场一周。大门采用高4m,宽5m的轨道式双向移动铁门。
(6)标示标牌
1)大门口处设置加工场铭牌,铭牌名称分别为:湖北交投武汉城市圈环线高速公路仙洪段第二合同段1号下构钢筋加工场,尺寸为80cm×60cm。
2)钢筋场内墙两侧设质量保证牌、安全生产牌采用铝合金制作,材质采用镀锌铁皮,铝合金框,尺寸2.5m×2m,标牌底距地面120cm。
3)焊接、用电等场所设置禁止警示牌。
4)机械设备悬挂机械操作安全规定公示牌和设备标识牌。
5)各种原材料、半成品或成品按其检验状态与结果、使用部位等进行标识。
5.钢筋加工设备及成品钢筋运输车配置
1#标准化钢筋加工场配置10t龙门吊2台、2#标准化钢筋场配置5t龙门吊2台、数控弯曲中心机2台、滚焊机4台、钢筋调直切断机8台、钢筋成品运输车4台、25t汽车吊2台、250kW发电机2台。
1#、2#、3#、4#、5#下构钢筋加工场共配置钢筋加工设备4套,钢筋成品运输车4台,25t汽车吊2台,150kW发电机4台。
6.钢筋加工场人员配置
1#、2#标准化钢筋加工场各设:厂长1人,钢筋加工工长2人,生产工人45人。
1#、2#、3#、4#、5#下构钢筋加工场各设:厂长1人,钢筋加工工长1人,生产工人20人。
7.安全保障措施
(1)所有进入场内的作业人员统一劳保着装。
武汉城市圈环线高速公路洪湖段第二标段 9
武汉城市圈环线高速公路洪湖段第二标段 钢筋加工厂标准化建设方案
(2)电工、焊工持证上岗,对进场施工人员进行技术和安全交底,并定期进行安全教育。
(3)使用性能良好的机械和机具设备,定期检修,及时进行故障维修,杜绝带病作业。每月组织安全生产大检查,积极配合上级进行专项和重点检查。
(4)钢筋加工场现场严禁非工作人员进入,一切工作人员进入施工现场必须佩带安全帽。严禁酒后上岗。
(5)站内运行车辆和机械运行速度不超过15km/h。
(6)现场临时用电符合“三级配电两级保护”,达到“一机、一闸、一漏、一箱”要求。电箱设置、线路敷设、接零保护、接地装置、电气连接、漏电保护等配电装置符合规范要求。
(7)生活及照明用电与生产用电严格区分,分开安装,严禁混用。用电线路由有电工证的专业人员进行布线。沿场地周边布线,采用架空、过路保护等措施,保证施工和用电安全。严禁非专业人员对用电线路进行改造、移位、拆接等工作。
(8)电工定期检查各用电线路的漏电保护器、接地装置、保护装置是否处于完好状态、各用电线路是否异常,接头是否松动,检查确定电机、线路及配电柜中的各开关及保护装置是否有故障,发现问题及时处理,消除安全隐患,不得拖延。操作员及其他人员发现电路故障时,切断电源,等待电工处理。
(9)施工现场按规定布置防火设施,配置消防灭火工具,灭火器、消防砂、铁桶和铁锹手锤等,并落实相关责任人管理。
(10)禁止将电焊机零线搭在钢筋原材上。
8.文明施工措施
(1)施工现场场地围蔽,并在入口醒目位置设置施工标示牌、施工平面布置图等,钢管支架,电脑喷涂打印粘贴在镀锌铁皮面板。
(2)钢筋的原材料和半成品堆放在围蔽范围内,分类堆放整齐,并标识清楚。
(3)施工现场内道路平整畅通,排水系统功能良好,有人员经过的沟、井、坑均加盖设防和设置安全防护标志或回填整平。
(4)作业人员进入施工现场必须穿戴相应劳动保护用品。现场管理人员和
武汉城市圈环线高速公路洪湖段第二标段 10
武汉城市圈环线高速公路洪湖段第二标段 钢筋加工厂标准化建设方案
作业人员统一制服、挂牌上岗,安全监察人员应佩戴安全袖标(牌),各种特种设备操作人员必须持证上岗。
(5)各类标识标牌整齐划一,材料堆放整齐有序。加工剩余材料或废料要合理回收利用。
(6)建立门禁制度,严禁与工程无关人员入内。
9.环境保护
(1)定期检修搅拌机各部件,保持机械良好作业;减少场内行驶车辆通行次数,禁止车辆随便鸣笛。施工过程中尽量避免夜间施工。加工场四周设置围挡,降低噪音对周围的影响。
(2)车辆通行道路,安排专人进行清扫,地面无严重积灰,车辆行走无明显扬尘。
(3)排水沟出水口处设置三级沉淀池,经沉淀后排入附近水渠。 (4)废弃的钢筋、包装材料、生活垃圾必须及时清理出现场,防止引起扬尘和影响环境卫生。
(5)在施工场地禁止焚烧废弃物品,防止产生有毒、有害烟尘和气体。 (6)原材料堆放场地及道路在晴天干燥时应经常洒水予以养护和保护,防止道路灰尘弥漫。
(7)在施工中尽量使用低噪声设备,对各种高噪声设备安装消声设备,避开夜间使用,对施工过程中产生振动的噪声进行隔振,隔噪处理或采取其它措施。对无法控制的施工噪声应合理安排施工时间。定期发放个人卫生防护用品,现场检测人员负责检查噪声控制落实情况。
(8)各机具产生的废液废油统一定时收集处理,严禁乱倒乱弃。
10.附件:
附件1:《钢筋场分布图》
附件2:《1#标准化钢筋加工场平面布置示意图》 附件3:《2#标准化钢筋加工场平面布置示意图》 附件4:《1#下构钢筋场平面布置示意图》 附件5:《2#下构钢筋场平面布置示意图》 附件6:《3#下构钢筋场平面布置示意图》
武汉城市圈环线高速公路洪湖段第二标段 11
武汉城市圈环线高速公路洪湖段第二标段 钢筋加工厂标准化建设方案
附件7:《4#下构钢筋场平面布置示意图》 附件8:《5#下构钢筋场平面布置示意图》
武汉城市圈环线高速公路洪湖段第二标段 12
正在阅读:
标准化钢筋加工场方案02-01
宁波市家具店名录2018版302家05-21
钓鱼的启示阅读07-08
理论中心组党课讲稿_“不忘初心 牢记使命”主题教育02-23
七年级语文现代文阅读题解答技巧和答题模式11-24
窗外的世界作文600字07-12
吸烟者与癌症:你的吸烟史有多久?07-01
捏橡皮泥作文400字06-25
第24章 圆 归纳总结12-05
- exercise2
- 铅锌矿详查地质设计 - 图文
- 厨余垃圾、餐厨垃圾堆肥系统设计方案
- 陈明珠开题报告
- 化工原理精选例题
- 政府形象宣传册营销案例
- 小学一至三年级语文阅读专项练习题
- 2014.民诉 期末考试 复习题
- 巅峰智业 - 做好顶层设计对建设城市的重要意义
- (三起)冀教版三年级英语上册Unit4 Lesson24练习题及答案
- 2017年实心轮胎现状及发展趋势分析(目录)
- 基于GIS的农用地定级技术研究定稿
- 2017-2022年中国医疗保健市场调查与市场前景预测报告(目录) - 图文
- 作业
- OFDM技术仿真(MATLAB代码) - 图文
- Android工程师笔试题及答案
- 生命密码联合密码
- 空间地上权若干法律问题探究
- 江苏学业水平测试《机械基础》模拟试题
- 选课走班实施方案
- 加工场
- 钢筋
- 标准化
- 方案
- SAP - BADI屏幕增强实例MB - MIGO - BADI
- 优秀中班教案数学:开宝箱—认识数字9
- 费尔巴哈
- 针对吉林省经济社会发展现实问题的对策研究
- 大数据平台-kerberos安装部署文档
- 新中国成立以来的经济发展历程
- 施工组织设计、安全专项方案培训
- 小学二年级音乐教案下册
- 小箱梁预制施工方案
- 部编新教材2019秋季学期统编版语文五年级(上)7 什么比猎豹的速度更快 教学反思3-公开课配套资料
- 浅谈施工项目部HSE管理
- 电大古代小说戏曲专题小抄(直接打印)
- 胸膜外血肿的X线平片与CT扫描诊断对比
- 人教版五年级数学上册《小数乘整数》说课稿
- 2014-2018年中国粮食加工市场运营态势及投资方向研究报告
- 最新初三化学方程式总结及现象(精品) - 图文
- hfss论文
- 装饰装修服务方案
- 新四级英语考试必记核心词汇
- 建筑工程技术基础知识要点