目 录

第八章 编制本施工组织计划的依据 ····························································· 2-1

8.1 总则······································································································ 2-1 8.2 工程概况······························································································ 2-1 8.3 合同项目和工作范围·········································································· 2-1 8.4 施工条件······························································································ 2-2 8.5 控制性进度要求·················································································· 2-6 第九章 施工管理工作目标及组织机构框图 ················································· 2-7

9.1 施工管理工作目标·············································································· 2-7 9.2 施工组织机构框图·············································································· 2-7 第十章 主要施工方案及技术要点 ································································· 2-9

10.1 施工总方案························································································ 2-9 10.2 临建工程及其平面布置···································································· 2-22 10.3 施工测量作业···················································································· 2-25 10.4 土方开挖···························································································· 2-27 10.5 土石方填筑························································································ 2-29 10.6 砌体工程···························································································· 2-32 10.7 混凝土工程························································································ 2-33 10.8 堤身灌浆···························································································· 2-43 10.9 土工防渗膜························································································ 2-47 10.10 堤顶防汛路面·················································································· 2-49 10.11草皮护坡 ··························································································· 2-52 10.12 杂项金工·························································································· 2-53 10.13混凝土及砌体拆除··········································································· 2-53 第十一章 施工进度计划及其保证措施 ························································· 2-54

11.1 业主设计控制性工期要求 ································································ 2-54 11.2 施工工期总计划 ················································································ 2-54 11.3 控制性施工进度计划 ········································································ 2-54 11.4 扫尾工程及退场 ················································································ 2-55

11.5 施工进度横道图 ················································································ 2-55 11.6 施工进度网络计划图 ········································································ 2-55 11.7 完成主要工程量进度计划 ································································ 2-55 11.8 工期保证措施 ···················································································· 2-55

第十二章 资源计划 ························································································· 2-60

12.1 施工机械设备计划············································································ 2-60 12.2 施工劳力计划···················································································· 2-60 12.3 施工用建筑材料计划········································································ 2-60 12.4 资金流动计划···················································································· 2-60 第十三章 质量保证措施 ················································································· 2-62

13.1 质量保证体系框图············································································ 2-62 13.2 质量保证措施···················································································· 2-63 13.3思想保证措施····················································································· 2-64 13.4技术保证措施····················································································· 2-64 13.5资源保证措施····················································································· 2-66 13.6经济保证····························································································· 2-66 第十四章 安全保证措施 ················································································· 2-68 14.1 安全组织机构框图············································································ 2-68 14.2 安全保证措施···················································································· 2-70 14.3加强劳动保护····················································································· 2-70 14.4保障照明安全····················································································· 2-70 14.5积极预防事故····················································································· 2-70 14.6安装避雷及接地保护装置································································· 2-71 14.7切实管理好炸药、雷管和油料························································· 2-71 14.8认真做好消防工作············································································· 2-71 14.9防护洪水和气象灾害········································································· 2-71 14.10设置一切必要的信号······································································· 2-71 14.11编制《安全防护手册》 ··································································· 2-71 14.12疾病防治··························································································· 2-71 14.13加强工地保卫··················································································· 2-71 第十五章 环境保护措施 ················································································· 2-73

15.1 环保机构及主要措施········································································ 2-73 15.2 环保法规的实施················································································ 2-73 15.3 环保计划···························································································· 2-73 第十六章 降低施工成本措施 ········································································· 2-75 16.1 提高施工组织水平············································································ 2-75 16.2 提高施工技术水平············································································ 2-75 16.3 提高劳动生产率················································································ 2-75 16.4 提高机械使用率················································································ 2-75 16.5 提高管理水平···················································································· 2-75 第十七章 合理化建议 ····················································································· 2-76

第八章 编制本施工组织计划的依据

8.1总则

中技国际招标公司于二○○三年八月编写的《中华人民共和国**城市防洪土建工程项目招标文件(标号ITC-**)第**合同段(**)》(简称《招标文件(**)》)是编制本施工组织计划的依据。其工程概况、施工条件等内容摘抄如后:

8.2工程概况

**城市防洪工程位于**县城及其周围,县城位于**处,自南向北流经县城将县城分为东西两部分。**城市防洪土建工程主要由城东、城西二区防洪保护圈组成。

本次招标的主要工程项目包括:

a.东区加高加固现有防洪土堤5.25km,新建防洪土堤3.25km; b.西区加高加固现有防洪土堤7.662km;

c.新建及重建电排站5处(城东区3处,城西区2处),扩建电排1处(城西区); d.新建及重建涵闸5处(城东区2处,城西区3处),新建交通闸1处(城东区)。

8.3合同项目和工作范围

8.3.1本合同承包人的工程项目及范围

a. 主体工程项目及范围

本合同主体工程项目及范围如下表8.3-1详细工程量见工程量清单。按合同规定完成该表所述主体工程的施工以及竣工后验收移交前的运行和维护。

表8.3-1 主体工程项目及范围表 工程项目 城西区大堤 城西区大堤 城西区大堤 城东区大堤 城东区大堤 城东区大堤 城东区大堤 城东区大堤 城东区大堤 城东区大堤 **电排站 **电排站 **电排站 **电排站 **电排站 **电排站 位置 桩号X0-200~X1+840段 桩号X1+840~X3+600段 桩号X3+600~X7+462段 桩号D0+000~D2+664段 桩号D2+664~D3+270段 桩号D3+270~D4+000段 桩号D4+000~D4+400段 桩号D4+400~D4+850段 桩号D4+850~D5+250段 桩号D5+250~D8+500段 桩号X1+020处 桩号X3+100处 桩号X4+330处 桩号D4+150处 桩号D5+400处 桩号D0+070处 备注 土堤加高加固 土堤加高加固 土堤加高加固 土堤加高加固 土堤加高加固 土堤加高加固 土堤加高加固 土堤加高加固 土堤加高加固 新建土堤 新建 扩建 重建 重建 新建 重建

**自排涵闸 **自排涵闸 **灌溉涵闸 **自排涵闸 **自排涵闸 交通涵闸 桩号X1+035处 桩号X4+315处 桩号X6+950处 桩号D4+170处 桩号D5+415处 桩号D3+070处 新建 重建 新建 重建 新建 新建 b. 临时工程项目

负责完成本合同主体工程施工所需的所有临时工程的设计、施工和维护等,这些临时工程包括但不限于:

1) 进场与出场:

2) 施工导流与水流控制。

8.3.2 其他承包人承担的工程项目

本工程由其他承包人承担的工程项目如下:

a.涵闸金属结构及启闭设备(包括闸门、启闭机及其附属设备)的制作和安装工程; b.电排站金属结构及启闭设备(包括闸门、拦污栅、启闭机及其附属设备)、机电设备(包括水泵、电机及其配套电气设备)的制作和安装工程。

8.4 施工条件 8.4.1 水文条件

资水**段处于**~**段暴雨中心附近,全年发生暴雨最多的是5~6月,大暴雨主要发生在7月15日以后,**水文站暴雨持续时间一般为1~3天,最长达5天。根据多年水文资料统计,工程区内一般每年5~8月为汛期,9月~次年4月为枯水期。工程区内各控制点施工洪水水位见下表8.4-1

施工期9月~次年4月设计洪水位

表8.4-1 单位m(85黄海高程)

地点 时段和频率 9月~次年4月 P=10% 38.62 38.26 38.54 38.93 38.95 39.02 39.03 39.41 P=20% 37.62 37.26 37.54 37.93 37.95 38.02 38.03 38.41 8.4.2 气象条件

根据**县气象局多年统计资料分析:多年平均降水量1524.8mm,历年最大降水量2255.7mm,历年最小降水量1041.9mm;多年平均气温13.2℃,历年最高气温40.0℃,历年最低气温-15.5℃;多年平均蒸发量1206.3mm,历年最大蒸发量1486.9mm;历年最

小蒸发量767.1mm;多年平均风速1.8m/s,历年最大风速20.0m/s。

8.4.3 工程地质条件

**县城位于雪峰山弧形构造的北缘,浮邱山倒转背斜的东北及龙潭桥背斜的东部,三面环山,一面环水,近似盆地状地貌,地面标高35~40m,台地标高45~80m,远山标高80~335.4m,现有堤防堤顶标高39~41m。

堤线段地表上部6~8m多为人工填土,中部2~5m多为粉质粘土,下部1~2m多为粉土及少量淤泥质粉质粘土,深层不均匀分布有3~8m厚的砂卵石,深层基础多为板岩或花岗岩。

8.4.4 对外交通条件

本合同工程对外交通较为方便。公路通过省道1837线、1824线和**高等级公路可与207国道、319国道和**高速公路相接,经国道、长益高速公路可与益**等城市沟通。水路沿资水航道可达**等城市,**至**33km,工程区内现有防洪堤均有简易道路与城区道路相通。

8.4.5 天然建材条件

本合同工程天然建筑材料主要特性见下表8.4-2。

天然建筑材料主要特性表

表8.4.2 建材类别 料场名称 土料 砂石料 块石料 材料性质 粉质粘土 粉质粘土 粉质粘土 粉质粘土 砂卵石 砂卵石 花岗岩 花岗岩 花岗岩 花岗岩 有用层厚(m) 4 4 5 5 5.5 4 无用层厚(m) 0.5 0.5 0.5 0.5 0 0 无用层体积(万m3) 9 7 15 10 0 0 有用层储量(万m3) 75 56 120 90 90 65 120 90 75 100 8.4.6 建筑材料

所需建筑材料均由承包人负责采购、验收、运输和保管。所有建筑材料均应符合设计要求,而且应具有材质证明或出厂合格证书,并符合相关技术规范标准和要求。

由于某种原因无法提供规定的材料时,则须于事前28天申请报告后采用经工程师批准的替代材料。报送采用替代材料报告时,必须附有其技术标准和检测、试验资料,

并以不降低工程质量为前提。

材料的搬运和储存方式都应保证其质量、性能和适应工程需要。

整个施工过程中采用的混凝土及砼骨料、块石料、土料、填筑料、水泥、粉煤灰、外加剂、钢筋、钢材等都得进行取样试验,并将试验报告报送工程师批准后方可使用。

劣质材料必须清理运出施工现场。

8.4.7 协作条件

应根据业主及工程师指令,为其他承包人提供必要的施工条件。

在场地布置,施工道路及码头使用和施工进度要求等各方面服从工程师协调。

8.4.8 技术条件

1. 施工图纸:免费提供8份设计图纸和设计文件。图纸均须盖有现场工程师的公章,否则视为无效图纸。

2. 引用技术标准和规范。

《**省城市防洪土建工程招标文件(标号ITC--**)第**合同 段(**),第五章 技 术条款》(2003年8 月)

《铁道部铁路货物运输规程》 《交通部汽车货物运输规程》 《中国水路运输管理条例》

《中国民航货物国内运输规程》 《生活饮用水卫生标准》(GB5749-85)

《污水综合排放标准》(GB8978-88) 《小型石油库及汽车加油站设计规范》(GB50156-92) 《建筑内部装修设计防火规范》(GB50222-95) 《汽车库、修车库、停车场设计防火规范》(GB50067-97) 《通用用电设备配电设计规范》(GB50055-93) 《供配电系统设计规范》(GB50052-95) 《防洪标准》(GB50201-94) 《堤防工程设计规范》(GB50286-98)

《标准水泥(一)普通水泥(二)特种水泥》(国家标准局) 《硅酸盐水泥、普通硅酸盐水泥》(GB175-1999) 《砌体工程施工及验收规范》(GB50203-98) 《混凝土结构工程施工及验收规范》(GB50204-92) 《混凝土质量控制标准》(GB50164-92) 《钢筋混凝土用热轧带肋钢筋》(GB1499-1998) 《钢筋混凝土用热轧光圆钢筋》(GB13013-1991) 《中热硅酸盐水泥、低热矿渣硅酸盐水泥》(GB200) 《低热微膨胀水泥》(GB2938-97)

《用于水泥和混凝土中的粉煤灰》(GB1596-91)

《钢焊缝手工超声波探伤方法的探伤结果分级》(GB11345-89)

《钢熔化焊对接接头射线照相和质量分级》(GB3323-87) 《埋弧焊焊缝坡口的基本型式与尺寸》(GB986-88)

《气焊、手工电弧焊及气体保护焊焊缝坡口的基本型式与尺寸》(GB985-88) 《普通碳素结构钢技术条件》(GB700-88) 《低合金高强度结构钢》(GB1591-94) 《土工合成材料应用技术规范》(GB50290-98) 《建筑工程质量检验评定标准》(GBJ301-88) 《地基与基础工程施工及验收规范》(GBJ202-83) 《土方与爆破工程施工及验收规范》(GBJ201-83) 《施工现场临时用电安全技术规范》(GBJ232-82) 《粉煤灰混凝土应用技术标准》(GBJ146-90) 《内河通航标准》(GBJ139-90) 《建筑给排水设计规范》(GBJ15-88,1997年修订版) 《室外排水设计规范》(GBJ14-87,1997年修订版) 《建筑设计防火规范》(GBJ16-87,1997年修订版) 《民用爆破器材工厂设计规范》(GBJ189-85) 《厂矿道路设计规范》(GBJ22-87) 《砌体结构设计规范》(GBJ3-88) 《木结构设计规范》(GBJ5-88)

《堤防工程施工质量评定与验收规程(试行)》(SL239-1999) 《堤防工程施工规范》(SL260-98)

《水利水电建设工程验收规程》(SL223-1999) 《水利水电工程施工测量规范》(SL52-93)

《水利水电工程钻孔压水试验规程》(SL25-92) 《水利水电工程施工质量评定规程》(试行)》(SL176-96) 《疏竣工程施工技术规范》(SL17-90)

《水工建筑物水泥灌浆施工技术规范》(SL62-94) 《土石坝安全监测技术规范》(SL60-94) 《土工试验规程》(SL237-1999)

《泵站施工规范》(SL234-1999) 《水工混凝土滑动模板施工技术规范》(SL32-92)

《水利水电工程土工合成材料应用技术规范》(SL/T225-98) 《土工合成材料测试规程》(SL/T235-1999) 《水工混凝土掺粉煤灰技术规范》(DL/T5055-96)

《水利水电工程模板施工规范》(DL/T5110-2000) 《碾压式土石坝施工技术规范》(DL/T5129-2001) 《水工混凝土外加剂技术规程》(DL/T5100-1999) 《混凝土拌和楼(站)用搅拌机》(DLJT456-91) 《水利水电工程天然建筑材料勘察规程(试行)》(SDJ17-78)

《水利水电基本建设工程单元质量等级评定标准》(SDJ249-88)(SDJ249-91)(SL38-92)

《水工混凝土施工规范》(SDJ207-82) 《土工试验方法标准》(SDJ123-88) 《水利水电工程施工组织设计规范》(SDJ338-89) 《水工建筑物测压管水位观测试行规范》(SDJ/51-65) 《水工混凝土试验规程》(SD105-82) 《浆砌石坝施工技术规定(试行)》(SD120-84) 《公路水泥混凝土路面设计规范》(JTJ012-94) 《公路路基设计规范》(JTJ013-95) 《公路沥青路面设计规范》(JTJ014-97) 《公路排水设计规范》(JTJ018-97) 《公路路面基层施工技术规范》(JTJ034-2000) 《公路工程无机结合料稳定材料试验规程》(JTJ057-94) 《公路路基路面现场测试规程》(JTJ059-95) 《公路工程质量检验评定标准》(JTJ071-98) 《公路路基施工技术规范》(JTJ033-95) 《公路工程技术标准》(JTJ001-97) 《公路桥涵施工技术规范》(JTJ041-2000) 《混凝土拌和用水标准》(JTJ63-89) 《建筑地基处理技术规范》(JGJ79-91) 《钢筋焊接及验收规范》(JGJ18-96) 《高压旋喷灌注浆技术规范》(YSJ210 YBJ43-92) 《钻井液用膨润土》(SY5060-85)

8.5 业主控制性进度要求

根据《招标文件》规定,本合同工程设计于2003年12月1日开工,2005年12月31日全部完工,总工期25个月。

第九章 施工管理工作目标及组织机构框图

9.1 施工管理目标

根据招标文件的有关要求,结合我公司多年从事各类工程施工积累的管理经验,认真贯彻执行我公司的质量方针和TQC质量保证体系。为将本工程建成优质工程,特制定如下施工管理目标:

(1) 质量目标

单元工程合格率100%,力争优良率达90%以上,整体工程质量达到优良工程。无施工责任质量事故,无保修期责任影响工程正常使用事故。

(2) 工期目标

严格按照工程师批准的施工进度网络计划进行施工进度控制,确保按设计工期25个月如期完工。

(3) 安全目标

制定切实可行的工程施工安全措施,加强工程施工过程中的安全管理,杜绝人身死亡事故和重大机械设备事故。

(4) 环保目标

严格遵守国家有关环境保护的法律、法规和规章,搞好施工区的环境保护工作,确保环境保护各项指标均达到国家标准。 (5) 文明施工目标

加强施工现场管理和施工区域的综合治理,创建文明施工工地。

9.2 施工组织机构

为实现上述施工管理目标,选派专业知识基础扎实、技术熟练、经验丰富、身体强壮的技术骨干组成项目部,其组织机构框图如图9.2.1。

项目部下设生产技术部、安全管理部、材料供应部、环境管理部、质量监测部、计划财务部、设备管理部、办公室、调度室,由项目副经理、项目总工和首席经济师主管,并下设测量队、工地实验室、进行施工现场控制;下设供应科、材料仓库、机修厂,做好后勤服务工作。

工程施工设立堤防工程第一、二、三工段,每工段配备1m3挖掘机3~4台及相应的运输和碾压设备,第四工段为涵闸施工工段,第五工段为电排施工工段。各工段明确项目主管,组建土石方队,现浇砼队,砌筑队、技术队和灌浆队(堤防)。土石方队负责土方开挖、填筑、草皮护坡和路面硬化;现浇砼队负责现浇砼的钢筋制安、止水带和伸缩缝制安、模板制安、砼的拌制、运输、浇筑、养护和缺陷修补;砌筑队负责砼和砌体拆除,砌石、砌砖、砼护坡块预制及其砌筑养护;灌浆队负责相应堤段的堤身充填灌浆;同时各工段组建技术队,负责各施工段的施工测量、质量检测 、环境保护以及安全、消防、保卫等工作。

图9.2.1 施工组织机构框图

打 孔组 公司总部 项目主管 项目经理部 公司总工 项目经理 项目总工 首席经济师 项目副经理 质量监测部 计划财务部 生产技术部 环境管理 部 调 度 室 办 公 室 安全管理部 材料供应部 设备管理部 测量 队 实验室 供应科 仓 库 设备调度科 机修厂 第一、二、三、 (堤防)、四(涵闸)、五(电排站)工段 灌浆队 土石 方队 现浇 砼队 砌筑队 技术队 制浆组 灌注组 挖掘组 运输组 填筑组 钢筋组 模板组 砼 组 砼 砂块 筑预制组 组 运输组 砌筑组 测量科 安全科 环保科 质检科

第十章 主要施工方案及技术要点

10.1施工总方案 10.1.1 工程特点

首先是本合同工程属于防洪工程,防洪工程施工的特点:主要是受雨水、洪水制约,特别是汛期洪水暴涨,施工中需要同时兼顾防洪保安;而且建筑物的基础大多泡在水下,必须抢在冬枯水位季节施工。第二个特点是:战线长,包含城东城西两大防洪圈,堤长16162m,其中东区加高加固防洪土堤5.25km,新建防洪土堤3.25km,西区加高加固现有防洪堤7.662km。第三个特点是东区新建防洪堤段交通道路差,连畅通的人行道也不具备,第四个特点是各单位工程的工作内容混杂,涉及土方开挖、土方回填、大堤灌浆、砌石、砌砖、砌砼块、现浇砼、草皮护坡、砂石路面硬化等多项工作内容,而且工程量较大,需投入大量施工机械设备。

10.1.2 施工工段划分

按照施工专业和地段划分施工工段,其优点较多,专业性强,有利于保证施工质量和安全,同时可相对减少投入本合同工程施工的各种机械设备,有利于施工管理。因此,采取按地域划分施工段和按专业组建施工专业队相结合的组建形式,具体划分为:堤防一、二、三工段,涵闸工段和电排站工段。各工段按施工专业要求下设土方队、砌筑队、砼队:各施工队分成多个专业施工组、班,形成严密的组织结构,明确各自的施工任务以及质量、安全、环保和控制性进度计划实施等重大责任,以确保将本合同工程如期建成安全、优质的精品工程。

10.1.3 堤防工程施工措施

① 工作内容

堤防工程共长16162m,其中城西保护区7662m,城东保护区堤长8500m,其主要工程量为:土方开挖295250m3、土方回填2300393m3、堤身充填灌浆进尺21630m、现浇砼护坡11751.9m3、C20现浇砼挡墙29791.83 m3、预制C15砼块及安装12697.02m3、砂砾石垫层12697.02m3、草皮护坡272610m2、M7.5浆砌块石98489.99m3, 钢筋制安417T、泥结石路面硬化75770m2.

② 施工方法

a. 料场规划。业主提供的土料场为**粘土料场120万m3,**粘土料场90万m3,**粘土料场75万m3,**粘土料场56万m3。按照就近取土、减短运距的原则和汛期不宜施工的实际情况,城西区堤防桩号X0-200~X1+840堤段的培修加固土方从**粘土料场取土,城西区X1+840~X5+480的填筑土方通过**一桥、二桥,从**粘土场取土;城东区D0+000~D5+400堤段从**土料场取土,城西区X5+480~X7+462的填筑土方在**处填筑一砂砾石坝,过**,从**粘土料场取土,城东区D5+400~D8+500堤段的新修及培修加固土方从**粘土料场和**粘土料场取土。开工前,对料场进行复查。

b. 经测量放样后,对取土区和填土区均设置截水和排水系统,同时清理植被和表土,修筑临时车道。

c. 各堤段施工时,清基分段开槽后,X0-200~X3+360堤段砌筑浆砌块石挡土墙,然后填土筑堤;X3+233~X3+600堤段修筑临水面C20挡土墙,同时背水面填土培修至高程39.00米(黄海),砌筑内浆砌石挡墙后,填土筑堤;X3+600~X7+462堤段,修筑临水面C20砼挡墙后,填土筑堤;D0+280~D1+100堤段修筑堤外基堤身内外肩挡土墙后,填土筑堤;D3+000~D3+270堤段完成防洪墙和浆砌石挡墙后,筑堤成形;其余东区堤段均砌筑挡土墙后填土筑堤。

d. 土方回填时,层厚不大于0.3m,逐层摊平,夯压密实,土方施工采用1m3挖掘机挖土5T~8T自卸汽车运土,59kw推土机摊平,74kw履带拖拉机带羊足碾碾压密实。大堤填筑达到设计标准后,根据完工顺序对相应堤段X1+840~X2+300、X3+800~X4+200、X4+500~X5+400、X5+700~6+000进行堤身充填灌浆;X0-200~X7+462堤段、D0+000~D2+664堤段、D3+270~D8+500堤段做好防汛泥结石路面,同时,砼护坡工程和草皮护坡工程按堤防填筑工程完工顺序连接施工,以保护坡面,避免水土流失。

e. 堤防工程中的砼工程中,设拌和站2处,城东城西区各1处,配0.8 m3拌和机4台,砼熟料采用1T自卸车配以适当的双胶轮车运送。振动器捣实,薄膜覆盖保水湿润养护,模板采用木模板和组合钢模,钢筋采用机械制作,焊机焊接,结合人工绑扎。

f. 堤身灌浆施工采用二台灌浆机组按三序法进行充填灌浆。 g. 土工膜铺设采用波浪形松驰铺设方式,随堤身填筑时协调施工。

堤防工程施工自2003年12 月1日进场,2004年1 月 1日开始进行西区X0-200~X5+580堤段的土方开挖,接着砌筑浆砌石挡墙和砼挡墙,2月1日开始进行填筑,于2004年9月30日前完成浆砌石和土方填筑施工,然后利用已成形的堤面于2004年9月1日开始砼预制块制作,并对城西区X5+480~X7+462堤段进行土方开挖和堤身填筑,对城西区相应堤段进行堤身充填灌浆,并对城西区堤段全面进行砼和草皮护坡、路面硬化等进行施工,工程于2004年12月31日完成;同时于2004年9月1日开始按照施工程序对城东区D0+000~D5+250堤段进行土方开挖、堤身填筑,浆砌石挡墙护坡,砼挡墙护坡,草皮护坡,泥结石路面和相应堤段的土工防渗膜制安等工程的施工,于2005年4月30日完工;2005年1月1日开始进行城东区D5+250~D8+500堤段的土方开挖、浆砌石挡墙、预制砼块、现浇砼护坡和土方填筑施工,于2005年4月30日完工;2005年9月1月开始进行D5+250~D8+500堤段的预制砼制作、安装,草皮护坡,路面硬化等工作,于2005年12月底全部完工。

详见堤防工程施工总程序图,如图10.1.1 各堤段工程施工程序框图,如图10.1.2 ③ 堤防工程施工机械设备调配计划

堤防工程施工主要机械设备包括:土方开挖、运输、碾压、灌浆等主要机械,砼及砂浆拌制、运输、振捣、养护机械,泥结石路面摊铺、碾压机械,起重机械、提水、排水机械,备用发电机组及施工测量仪器,工地实验室、检测仪器等。

详见堤防工程施工机械设备配置计划表,如表10.1-1。 ④ 堤防工程施工劳力调配计划,详见表10.1-2。 ⑤ 堤防工程施工主要材料供应计划详见表10.1-3。

西区X0-200~X4+480堤段土方开挖 C20砼挡墙 浆砌石挡墙 C15砼垫层 CC15砼预制块制 15 砼预制块制作 砂砾石 路面 施工准备 土方填筑 堤身充填灌浆 西区X5+580X4+480~X7+462X7+460堤段 东区D0+000~D5+250堤段 土方开挖 CC20砼挡墙 20砼挡墙C15C15砼垫层砼垫层 砼块护坡砼护坡 砂砾石垫层 草皮护坡 浆砌石挡墙 D4+000~D5+250 土工防渗膜 土方填筑 C20砼现浇排水渠 C15预制块制作 堤身充填灌浆 砼护坡 砂砾石垫层 草皮护坡 砂砾石路面

东区D5+250~D8+500堤段土方开挖 浆砌石挡墙 D5+250~D7+800 土工防渗膜 C15预制砼制砼块护坡 砂砾石垫层 泥结石路面 草皮护坡 土方填筑 清理场地 完工验收 图10.1.1 堤防工程施工总程序框图

错误! 测量放样 取土区 土料复查 截水植被 修筑和排和表 临时水系土清 车道 理 统 土方挖运 X1+840~X2+123,X3+800~X4+200 X4+500~X5+400,X5+700~X6+000 堤身充填灌浆 堤顶砂砾石路面

施工准备 材料检测 钢筋、水泥、水、 模板填土区 及止水截水和排水系统 砂浆拌运 砼拌运 清理植被和表土 带配比试验 制安 钢筋制安 砼及砂浆外加剂、掺合料 基槽土方开挖 砼浆砌石挡墙 砼挡墙 C15砼垫层 预制块制作土方逐层回填夯实 ‘养护大堤整理成形 D4+000~D4+400 土工防渗膜 及运输 草皮护坡 砼护坡 砂砾石垫层

图10.1.2 各堤段工程施工程序框图

检查与完工验收

堤防工程施工主要机械设备配置计划表

表10.1-1 序号 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 设备名称 (种类、型号、产地) 推土机59kw 挖掘机1m3 推土机74kw 自卸汽车5t 自卸汽车8t 74kw拖拉机带羊足碾8-12t 数量 (台或艘) 7+4 7+4 4+3 60+52 40+30 5+7 6+3 5 各1 台 4 2套 2系统 3 16 10 10 12 2 200 16 3 3 6 12 4 4 6 4 2 1 3 6 1 3 3 进场时间 (年.月) 2004.1, 2004.9 2004.1, 2004.9 2004.1, 2004.9 2004.1, 2004.9 2004.1, 2004.9 2004.1, 2004.9 2004.1, 2004.9 2004.1 2004.1 2004.1 2004.9 2004.1 2004.1 2004.1 2004.1 2004.1 2004.1 2004.1 2004.1 2004.1 2004.1 2004.1 2004.1 2004.1 2004.1 2004.1 2004.1 2004.1 2004.1 2004.1 2004.1 2004.1 2004.1 2004.1 2004.1 出场时间 (年.月) 2005.4, 2005.11 2005.4, 2005.11 2005.4, 2005.11 2005.4, 2005.11 2005.4, 2005.11 2005.4, 2005.11 2005.4, 2005.11 2005.4, 2005.11 2005.4, 2005.11 2005. 11 2004.12 2005.4, 2005.11 2005.4, 2005.10 2005.4, 2005.11 2005.4, 2005.11 2005.4, 2005.11 2005.4, 2005.11 2005.4, 2005.11 2005.4, 2005.11 2005.4, 2005.11 2005.4, 2005.11 2005.4, 2005.11 2005.4, 2005.11 2005.4, 2005.11 2005.4, 2005.11 2005.4, 2005.11 2005.4, 2005.11 2005.4, 2005.11 2005.11 2005.11 2005.11 2005.11 2005.11 2005.11 2005.11 蛙式打夯机2.8kw 刨毛机 压路机8t、10t、12t 洒水车 灌浆设备 砼拌和机2台*0.8m3 砼搅拌机0.4m3 插入式振捣器2.2kw 插入式振捣器1.1kw 平板式振捣器2.2kw 砂浆搅拌机0.25kw 砼泵30m3/h 胶轮车 机动翻斗车1T 钢筋调直机14kw 钢筋切断机20kw 钢筋弯曲机 电焊机25KVA 木工锯床 木工刨床 载重汽车8t 风砂枪 汽吊5t 平板拖车 发电机组40kw 水泵75kw 全站仪 水准仪 经纬仪

堤防工程劳动力调配计划表

表10.1-2 序号 1 2 3 4 5 6 7 8 9 10 11 工种名称 管理人员 测量工 电焊工 钢筋工 模板工 砼工 砌筑工 机电维修工 司机 普工 合计 单位 人 人 人 人 人 人 人 人 人 人 人 数量 18 8 22 42 30 180 240 26 250 120 936 附注

堤防工程主要材料供应计划表

表10.1-3 序号 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 材料名称 汽油 柴油 电 水 块石 砂子 水泥 石子 草皮 碎石 石屑 水玻璃 专用钢模 型钢 卡扣件 铁件 电焊条 钢筋 紫铜片 止水橡皮 土工膜 单位 T T 度 T m3 m3 T m3 m2 m3 m3 T Kg Kg Kg Kg Kg T Kg m m2 数量 444.6 1151.86 5989744 158372.7 83789.7 73696.4 20309.45 58795.8 100865.7 17730.2 834.9 611.89 20160.1 10887 6417.7 31209.3 3639.1 425.3 507.7 186.4 6678 附注

10.1.4 涵闸工程施工措施

① 工作内容

涵闸工程施工共6处,其中城西保护区过水涵闸3处,城东区过水涵闸2处,交通闸1处。主要工程量为:土方开挖4499m3、土方回填3545m3、砼及钢筋砼1774.04m3、钢筋制安88.9T、M7.5浆砌石2116.6m3。

② 施工方法

设立涵闸工程施工工段,由项目经理部委派工段主管进行全面施工管理。由于涵闸工程全部位于堤身底部,5处过水闸嵌入堤基,1处交通涵闸嵌入堤身,都必须现浇好涵闸砼,养护到强度达到设计强度70%时,方可进行填土施工。因此,涵闸工程完工14-21天后,才能进行同桩号大堤土方填筑施工。

涵闸工程施工于2004年1月1日开始进行城西区**涵闸的施工,于2004年3月31日完工,2004年9月1日开始进行城西区**涵闸和城东区**涵闸的施工,于2005年3月30日全部完工。

涵闸工程施工中,对需要拆除的浆砌石和砼先进行拆除,再进行基槽开挖。基槽土方工程采用机械开挖结合人工开挖;填土时,采用机械夯实,与蛙夯机夯实相结合,与混凝土表面结合部位要结合人工夯压密实。砼浇筑工程采用0.4m3搅拌机拌制砼,双胶轮车运送砼,插入式振捣器振捣密实,塑料薄膜覆盖保水湿润养护;浇筑砼模板采用组合钢模,局部异形部位结合使用少量木模板,但务必使砼表面平整光洁,无明显搭接痕迹;二期砼与老砼的结合面先凿毛洗刷干净,然后再浇筑二期砼;钢筋采用机械制作、人工绑扎和焊接相结合;涵闸工程施工中,预埋金工铁件和预留洞的做法,与其承包施工单位配合,保证精确可靠。

涵闸工程施工程序框图,如图10.1.3

③ 涵闸工程施工主要施工机械设备配置计划 详见表10.1-4

④ 涵闸工程施工劳力调配计划 详见表10.1-5

⑤ 涵闸工程施工主要材料供应计划 详见表10.1-6

沥青杉板、模板制安止水铜片、排水管制安施工导流 板梁柱砼C20 施工准备 测量放样 原材料检测 钢筋、水泥、骨料、块石、水、掺合 料、外加剂 截水清理浆 和排植被砌 砼配比试验 钢水系和表石 筋统 土 拆 制除 砼拌制 安 砼运输 基槽土方开挖 砂浆配比试验 垫层C15砼 C20闸墩、闸底板砼 管身C20砼 砂浆拌制及运输 M7.5浆砌石挡墙 土方回填 检查及完工验收

图10.1.3涵闸工程施工程序框图

PVC

涵闸工程主要施工机械配置计划表

表10.1-4 序号 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 设备名称 (种类、型号、产地) 推土机74kw 挖掘机1m3 拌和机0.4m3 振动棒2.2kw 振动棒1.1kw 离心水泵 电焊机25kw 蛙式打夯机2.8kw 钢筋制作机械(套) 载重汽车 潜水泵 胶轮车 水准仪 经纬仪 对焊机 塔式起重机 1t机动翻斗车 数量 (台或艘) 2 2 1+2 1+2 1+3 1+2 1+4 2 3 3 2 20 3 2 1 1 3 进场时间 (年.月) 2004.1.1 2004.1.1 2004.1, 2004.9 2004.1, 2004.9 2004.1, 2004.9 2004.1, 2004.9 2004.1, 2004.9 2004.1 2004.1 2004.1 2004.1 2004.1 2004.1 2004.1 2004.1 2004.1 2004.1 出场时间 (年.月) 2005.3 2005.3 2005.3 2005.3 2005.3 2005.3 2005.3 2005.3 2005.3 2005.3 2005.3 2005.3 2005.3 2005.3 2005.3 2005.3 2005.3

涵闸工程施工劳动力调配计划表

表10.1-5 序号 1 2 3 4 5 6 7 8 9 10 11 工种名称 管理人员 测量工 电焊工 钢筋工 模板工 砼工 机电维修工 司机 砌筑工 普工 合计 单位 人 人 人 人 人 人 人 人 人 人 人 数量 6 3 12 32 40 80 10 11 30 80 301 附注

涵闸工程施工主要材料供应计划表

表10.1-6 序号 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 材料名称 汽油 柴油 电 水 块石 砂 水泥 砾石 φ50PVC管 紫铜片 钢材 专用钢模 型钢 卡扣件 铁件 电焊条 铜焊条 止水橡皮 单位 T T 度 T m3 m3 T m3 M Kg T Kg Kg Kg Kg Kg Kg M 数量 29.16 2.02 29094.3 3710.6 2285.9 1740.1 640.35 1480.1 131.5 736.9 90.7 2981.6 1610.2 949.2 4615.7 919.1 8.2 250.3 附注 10.1.5 电排站工程施工措施

① 工作内容

**重建和扩建工程6处,总容量3250kw.,其中,城西保护区**电排站2台*180kw, **电排站4台*155kw,**电排站2台*155kw,城东保护区**电排站4台*155kw,**电排站5台*155kw,**电排站3台*155kw。其主要工程量为:土方开挖40814m3、土方回填197893m3、砼及钢筋砼5938.3m3、钢筋制安410.9T、砖砌体289.8m3。

② 施工方法

电排站施工成立专业施工工段,分2个时段相继施工。首先施工**电排站,2003年12月下旬作好施工准备,2004年1月1日开工,至2004年4月底完工;**电排站于2004年9月1日开工,**电排站于2004年10月1日开工,**电排站于2004年11月1日开工,金华桥电排站于2005年1月1日开工, 2005年4月底前全部完成电排站施工任务。

电排站施工中,土方采用机械开挖结合人工开挖,运50-100m,回填土方时一部分用开挖土进行回填,另一部分用挖掘机挖土,自卸汽车运土填筑。采用74kw拖拉机带羊足碾碾压密实与蛙夯机夯实相结合,务令夯压密实,特别是与砼接触部位,还须使用蛙夯机结合人工夯实;电排站砼和钢筋砼工程施工采用0.4m3砼搅拌机拌制砼;1m3机动翻斗车和胶轮车运输,插入式振捣器振捣密实,塑料薄膜覆盖保水湿润养护;浇筑砼的模板采用组合钢模,局部异形部位结合使用少量木制模板;钢筋采用机械制作,交流

电焊机焊接结合人工绑扎。

电排站工程施工中,所有预埋金工铁件和预留孔洞,以及设备安装工程施工一定与另承包单位密切配合,务令其满足精度要求。电排站工程施工程序框图,如图10.1.4。

③ 电排站工程施工主要机械调配计划 详见表10.1-7

④ 电排站工程施工劳力调配计划 详见表10.1-8

⑤ 电排站工程施工主要材料供应计划 详见表10.1-9

电排站工程主要施工机械配置表

表10.1-7 序号 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 设备名称 (种类、型号、产地) 搅拌机0.4m3 胶轮车 平板振动器2.2kw 插入式振动器2.2kw 挖掘机1m3 推土机74kw 蛙式打夯机2.8kw 拖拉机74kw带羊足碾 水泵15kw 钢筋制作机械(套) 电焊机 水准仪 经纬仪 全站仪 自卸汽车 推土机59kw 载重汽车 刨毛机 汽车起重机 手持式风钻 修钎设备 塔式起重机 1t机动翻斗车 数量 (台或艘) 2+1 40 4 4 2 2 2 1 4 4 6 2 2 1 15 2 1 2 1 2 1 1 3 进场时间 (年.月) 2004.1,2004.9 2004.1 2004.1 2004.1 2004.1 2004.1 2004.1 2004.1 2004.1 2004.1 2004.1 2004.1 2004.1 2004.1 2004.2 2004.2 2004.2 2004.2 2004.1 2004.1 2004.1 2004.1 2004.1 出场时间 (年.月) 2005.4 2005.4 2005.4 2005.4 2005.2 2005.4 2005.4 2005.4 2005.3 2005.3 2005.3 2005.4 2005.4 2005.4 2005.4 2005.4 2005.3 2005.4 2005.4 2005.3 2005.3 2005.3 2005.3 错误!电排站工程施工劳动力调配计划表

表10.1-8 序号 1 2 3 4 5 6 7 8 9 10 11

工种名称 管理人员 测量工 电焊工 钢筋工 模板工 砼工 机电维修工 司机 砌筑工 普工 合计 单位 人 人 人 人 人 人 人 人 人 人 人 数量 6 3 12 40 32 100 28 40 40 80 353 附注 电排站工程施工主要材料供应计划表

表10.1-9 序号 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

材料名称 汽油 柴油 电 水 块石 砂子 水泥 砾石 Φ50PVC管 专用钢模 型钢 卡扣件 铁件 电焊条 钢筋 止水橡皮 紫铜片 钢板 单位 T T 度 T m3 m3 T m3 m Kg kg Kg Kg Kg T m Kg T 数量 552.69 84.92 120016 5687.1 12257.9 7121.2 2280.6 4312.6 3811.9 4100.1 2192.9 1305.2 347.3 4767.2 68.15 292.2 741.1 15.89 附注

施工准备

测量放样 原材料检测 钢筋、水泥、骨料、块石、水、掺合模板沥青杉板制安 止水橡皮紫铜片施工导流 截水和排水系统 清理植被和表土 料、外加剂 砌体拆除砼拆除 钢筋制 安 砼配比试验 砼拌制 制安 砼运输 基槽土方开挖 砂浆配合比试验 垫层C15砼 水下大体积砼 闸 墩 管 身 闸底板C20砼 板柱梁、板C20砼 砂浆拌制及运输 浆砌石 砖砌体 土方回填 检查与完工验收 图10.1.4电排站施工程序框图

10.2 临建工程及其平面总布置

10.2.1临时设施布置

临时设施包括所有施工人员、设备及其临建工程所需的材料和提供其进出场运送的施工道路及办公和生活营地建造、材料堆放、仓库、加工厂及设备维修站建造,砼生产系统图及砼构件预制场建造,供排水、供(变)电系统、照明系统、通讯系统建造,施工道路、码头、围堰排水设施建造,以及消防、环保、安全、保卫、医疗等设施的建造等。所有上述设备的布置详见施工总平面布置图,如图10.2.1。

临时设施用地约45200m2,详见表10.2-1 临时设施用地计划表

10.2.2进场及出场

进出场施工设备总量约1100T,其中800T在10公里范围内调集,约300T在500公里内调集;各类施工人员进出场约1590人,其中1400人在50公里内调集,其余在300公里内调集。发布开工令之日,土方开挖工程开工,所需设备提前10天进场。

各项工程施工完成后,人员及机械设备分次退场,退场时,人员及设备均不另计费用。主要施工机械设备进、出场计划详见表10.1-1、表10.1-4和表10.1-7。

10.2.3办公室及生活营地 项目部办公营地设在**分公司内,并先后建立生活营地5处,面积2500 m2,各生活营地平面布置见图10.2.2。

10.2.4施工道路及码头

本合同工程应修建临时车道长2km,路面宽5m;维修现有车行道14km。 在填筑城西区X4+600~X7+462堤段,从**土场取土时在**处填筑砂砾石坝一座,顶宽8米,采用砂砾石填筑。

10.2.5施工用电及照明

全线施工用电和照明采用当地电网,就近接入,现有**电排站以及城区生活用电变压器供施工用电。本工程施工最大电力负荷约1500kw,全线施工用电和照明用电需架设临时0.4kv电力线14km,采用三相五线制架设;全部使用防尘防爆电气设备,其金属外壳均埋设安全接地线;施工照明采用高压汞灯为主,局部辅以1000W碘钨灯和普通白炽灯。为防止意外停电影响正常生产,自备柴油发电机组5台套,其中40kw4台套,120kw1台套。

10.2.6砼生产系统

于**电排站附近布置砼生产系统,设2台0.8m3砼搅拌楼2系统(详见图10.2.3),集中生产后,自卸车运送至浇筑现场;进行城东、城西大堤现浇砼护坡及钢筋砼挡土墙浇筑;待城西区X1+840~X4+600大堤土方填筑完成后,利用填筑好的堤顶开辟砼构件预制场2处;

砼生产系统棚库建筑面积600m2,砂石料堆场占地1400m2,填筑完工后的大堤堤面

开辟预制场砼块生产场地3.2万m2。

临时设施用地计划表

表10.2-1 序号 1 2 3 4 5 土地的计划 用途及类别 项目部办公室 项目部 一工段(堤防) 五工段(电排) 二工段(堤防) 三工段(堤防) 四工段(涵闸) 生活营地 一工段(堤防) 五工段(电排) 二工段(堤防) 三工段(堤防) 四工段(涵闸) 砼搅拌站 0.8m3砼搅拌站 0.4m3砼搅拌站 砼块预制场 仓库 所需面积(m3) 250 150 150 150 150 150 1200 1200 1200 1000 1000 1100*2 300*6 24000 8000 200 200 200 200 200 200 大致位置或起止桩号 D4+850 X2+800 D5+200 X6+000 D2+600 D5+300 X9+780 D4+000 X6+480 D2+000 X4+400 X1+200~X2+400 X3+000 X4+200 X6+000 D0+600 D4+000 D5+200 2004.1~2005.11 2004.1~2005.11 2004.9~2005.10 2004.9~2005.10 2004.1~2005.10 2004.1~2005.10 2004.9~2005.10 2004.9~2005.11 2004.9~2005.11 2004.9~2005.11 20010.12~2004.12 20010.12~2005.4 2004.9~2005.12 2004.9~2005.4 2004.1~2005.3 所需时间 自__至__ 20010.12~2005.11 20010.12~2004.12 20010.12~2005.4 2004.9~2005.12 2004.9~2005.4 2004.1~2005.3 其中利用业主已征用土地 5600 1200 1200 1200 1000 1000 4000 2200 1800 32000 24000 8000 1200 200 200 200 200 200 200 待租用 (m2) 1000 250 150 150 150 150 150 临时设施用地计划表

表10.2-1 序号 6 7 8 9 土地的计划 用途及类别 加工棚 机修车间 防守棚 临时施工路面 合 计 20m2*20个 所需面积(m3) 2000 300 150 150 200 200 150 200 150 150 150 大致位置或起止桩号 X3+100 X4+100 X6+120 D0+800 D4+420 D5+300 X9+780 X4+000 X6+480 D2+000 X4+400 所需时间 自__至__ 2004.1~2005.10 2004.1~2005.10 2004.9~2005.10 2004.9~2005.11 2004.9~2005.11 2004.9~2005.11 20010.12~2004.12 20010.12~2005.4 2004.9~2005.12 2004.9~2005.4 2004.1~2005.3 2004.1~2005.12 2004.1~2005.12 45200 其中利用业主已征用土地(m2) 1200 200 300 150 150 200 200 800 150 200 150 150 400 400 1000 待租用 (m2) 14km 10.2.7施工用水

施工用水设立10m3水池4处,从附近**取水进入储水池。

供水管采用PVC钙塑管道,供水管道共长15000m。

10.2.8通信系统

项目部及各施工工段架设固定电话,项目部组成人员及各施工队、班、负责人全部配置小灵通手机约100台,建立通信网络,随时反馈各类信息,以便及时有效地指导各项具体工作。

10.2.9临时房屋建筑 生活营地建筑5处3000m2 ,钢筋加工厂800m2,木工厂400m2,维修站800m2,合计5000m2。全部采用钢质管架组合、拼装墙体和屋面,只需计算折旧费,故费用极低。临时建筑占地45200m2。详见表10.2-1。

10.2.10环保设施

⑴ 由于该工程施工的主要运输道路大部分经过城区,施工散落的土屑易产生扬尘,为确保施工期间运输道路全线环境卫生,所有运输车辆车箱均须加盖化纤布,或用全封闭渣土运输车运输,并对施工运输道路定时洒水,适时清洗。

⑵ 沿线布置临时水冲厕所10处,水冲入化粪池,营地全部使用喷淋浴室,全线污水接入就近的下水道;营地布置垃圾池,能焚烧的垃圾送入专门的焚烧炉内焚烧,不能焚烧的垃圾按工程师指定位置深埋。

10.2.11消防及保卫

配备必要的消防设施,明确专职和兼职消防队员,以防万一。 设立安全保卫岗点20处,配备专职人员坚守岗位,日夜巡逻,确保安全保卫万无一失。

10.2.12施工导流与排水控制

⑴ 5处过水涵闸和6处电排站施工,必须进行有效的施工导流和水流控制,临时围堰工程量大,围堰总长度约660m。为确保施工期安全,采用袋装土筑坝围堰,堰顶面宽1m,高2~4m,双向坡比1:1,工程量约3700m3。围堰内排水采用75kw水泵提排。

⑵ 取土区和填土区与建筑物基础一样,都要做到旱地施工,同样需要采取截水和排水措施。

10.3施工测量作业 10.3.1技术标准

《水利水电工程施工测量规范》SL52-93。

10.3.2测量准备

(1) 开工前,选用训练有素、经验丰富、技能娴熟、资格老练的测量人员,配备足够数量的精密测量设备,并且对投入本合同工程施工测量的仪器设备送国家技术监督部门进行检定,确定所用测量仪器设备的精度满足规范要求后再投入使用。

(2) 根据工程师提供的测量基准点,基准线和水准点及基本资料和数据,对其进行校测,复核其资料和数据的准确性,并以书面形式报告业主和工程师。

(3) 平面控制点加密

在监理人提供的高程控制网点的基础上,为方便施工,适当增设水准点。根据现场具体情况,采用全站仪进行三角站测量和几何水准测量法进行高程控制网加密。

(4) 增设网点用不锈钢或铸钢埋设。在软弱土中将钢螺栓埋设在适当大小的混凝土块中,并保证其绝对稳固、耐久、明显、易读。

(5) 为防止差错,对施工质量控制网,先由测量员勘测,再由项目经理部技术负责人进行复测,经相互检查校核,并做好检查校核的记录,以备核查。

(6) 根据工程师批准的测量原始记录本的格式,认真做好各种施工测量原始记录和施工放样记录,并妥善保管,以备核查。

(7) 施工过程中,加强对测量控制点的保护,定期进行检查校核,测量仪器设备由专人进行保管及维护。

10.3.3施工测量

(1) 轴线放样测量

根据设计图纸和施工控制网点,采用极坐标法测放设计桩号,进行轴线测量定线。 (2) 轴断面测量

轴线测量定线后,以全站仪极坐标法或经纬仪辅以皮尺量测出横断面,并测放开挖边线或回填边线。开挖或回填施工初步完成后,测量、检查开挖或回填断面所有高程,每隔15m设样架,指导坡面整平及护坡的施工。

10.3.4测量审查

所有测量和放样的有关参数全部报工程师审查。在某一特定区或开始工作足够长时间之前向工程师申请审查。并在任何时候协助工程师进行控制测量作业。为此,必须保持所有标志干净,观测视线清晰。校核工作一般应在施工作业停歇时刻进行,遇紧急情况,则限制或暂停其工作。

10.3.5测量辅助工作

本节的辅助工作一般包括但不限于下列内容:

(1)进行所有的必要的计算,要求计算及其成果清楚,以便于校核; (2) 揭开测量水准点的保护盖;

(3) 根据观测视线的需要,移出阻挡视线的机械及各种障碍物;

(4) 暂停所有引起地震动的工作,并防止有碍观测或会造成折射的烟雾及尘埃气体; (5) 限制或止住车辆及人员在仪器附近及仪器视野范围内通行;

(6) 配备有数量的具备辅助测量工作经验的非熟练劳力,以及工程师认为适于控制和辅助测量的材料;

(7) 做好一切必要的安全预防措施;

(8) 为了便于工程量决算及绘制竣工图,在基础开挖经验槽后,每15米长测横断面

一个;

(9) 提供并标明工程师需要的与控制测量有关的材料;

(10) 根据工程师的指令设置测量水准点代替或补充测量水准点;

(11) 若既有地形资料不能满足工程计量所要求的精度时,进行地形补测; (12) 观测施工期建筑物状况所必须的所有地形测量。

10.4土方开挖 10.4.1工作内容

本合同土方开挖施工包括堤身植被和表土清基、堤身及堤基土方开挖、岸坡削坡开挖、护坡脚槽土方开挖、涵闸及电排基础土方开挖、回填土取料开挖,以及图纸所示和工程师指示的其他项目的土方开挖施工。

本合同工程开挖土方量340563m3,其中:堤防工程土方开挖295250m3、建筑物工程土方开挖45313m3。堤防填筑工程回填土料开挖2300393m3,建筑物回填工程土料开挖201438m3。

10.4.2施工方法 本合同工程土方开挖采用1m3挖掘机,土方运输采用5吨~8吨自卸车。按照自上而下、梯段分层的开挖方式进行,每梯段高度控制在5m以内。开挖前,首先进行测放、开挖边线;接着沿开挖边线外侧2m以外开挖截水沟;同时进行植被清理,按工程师指示,清理开挖区域内的树木、树桩、树根、杂草、垃圾、废渣及其它有碍物;还要清除含有细根须、草本植被、腐殖质或有机质的表层土壤;同时,还要准备好排水设备,布置开挖区内的排水沟和集水池;然后才能进入土方开挖施工。土方开挖工程完工后,立即进行整体平整,整理开挖边坡和弃土边坡,使其保持稳定,不致坍塌。最后进行完工验收。土方开挖施工工艺流程如图10.4.1

10.4.3技术要点

⑴ 于任一单项工程开工前14天,提交详细的施工计划一式四份,报送工程师批准。 ⑵ 植被清理中凡属没有使用价值的可燃物,尽快烧毁;无法烧焚的清除料按工程师指定位置掩埋,其覆盖土厚不小于0.6m。

⑶ 表土清除按工程指定厚度和堆放地点堆放,堆土宜矮并防止冲刷流蚀。

⑷ 按设计图纸和设计文件要求进行开挖。开挖均为旱地施工,开挖中的地下水和地表水,都须采取有效的截、排措施。

⑸ 基础清基范围,包括堤身、堤基、铺盖、压载的建基面及其他建筑物基础,都必须清理至设计基面线外0.3~0.5m。

⑹ 机械开挖时,建基面以上留足土层厚度0.1~0.2m,采用人工开挖以保护地基原状土不受扰动。

⑺ 建基面表层不合格土、杂物必须清除;堤基范围内的坑、槽、沟等,按堤身填筑要求进行回填处理。

施工准备 测量放样 开挖外围截水沟 清理植被 清理表土 布置场内排水沟、集水池和排水设备 梯段开挖 运送至工程师指定位置 平整场地 整理边坡 清理场地 完工 图10.4.1土方开挖施工工艺流程图

⑻ 土方清基实际开挖轮廓必须符合设计图纸所示开口线、水平尺寸和高程的要求,不得欠挖。

⑼ 开挖前、开挖中和开挖后,随时按图纸要求或工程师指示进行测量、放样,防止超挖。

⑽ 土方开挖边坡及时修整,使其处于稳定状态,以防止坍塌。 ⑾ 开挖渣料的堆存、利用和处理均按业主和工程师指示施工。

⑿ 料场开采完毕,按业主和工程师指示进行场地平整、边坡稳定处理、环境保护或土地还耕等。

10.4.4 检查与验收

⑴ 基础开挖后的基面尺寸和土体质量进行检查、整修和处理。 ⑵ 基础检查分为自检、复检和工程师组织的终检。 ⑶ 基础处理合格后,请工程师组织验收。

10.5 土石方填筑 10.5.1 工作内容

本合同工程土石方填筑工程量为2514528.02m3,其中:大堤土方填筑2300393m3,涵闸工程回填土石方3545m3,电排站工程回填土方197893m3和砂卵石垫层填筑12697.02m3。

⑴ 合同工程土石方填筑施工主要工作内容包括:

⑵ 为填筑所需的土料场的复查及料场规划; ⑶ 土料的制备及现场生产性试验;

⑷ 土料的开采和运输;土料的填筑及压实; ⑸ 垫层料、反滤料的购买和运输;

⑹ 垫层料的铺筑和碾压,反滤料的铺筑; ⑺ 接缝处理;

⑻ 监督、质量控制、试验与检测;

⑼ 工程师指示的与本合同工程有关的填筑工作; ⑽ 其它回填与场地填筑。

10.5.2施工方法

首先对料场进行复查,以落实土料数量、质量及其开采条件,复核土料物理力学特性,其重点是比重、天然容量、天然含水量、颗粒级配、最优含水量、最大干容重、压缩系数、渗透系数等。在此基础上规划好料场、运输线路、水电系统、排水系统和弃渣场等。同时对采料区和填筑区进行植被和表土清理。上述工作经业主和工程师检查验收合格后,开始挖、运、填筑土方。本合同工程计划使用1m3挖机取土,5吨~8吨自卸车运输土料,59KW推土机推平,层厚不大于0.3m,74kw拖拉机带8t~12t羊足碾逐层碾压密实。每个作业段控制长度100~500m以上,垂直堤轴线方向的搭接斜坡1:3~1:5,跨缝搭接碾压,搭接宽度不小于3.0m。由工程师逐层检查验收,只有当下层填土经验收合格后,才进行其上一层土料填筑。其施工工艺流程如图10.5.1。

本土方填筑工程施工,首先填筑城西区X0-200~X5+480段大堤,采用7台1m3挖掘机配5台74kw推土机挖土,5~8t自卸汽车110辆运土,3台74kw拖拉机带8~12t羊足碾碾压密实。该段大堤填筑完工后,接着于 2004年9月上旬,增加1m3挖掘机4台,相应增加运土和夯压机械,按上述方法进行城西X5+480~X7+462堤段和城东区D0+100~D5+250段大堤的土方填筑,于2005年1月上旬开始按上述方法填筑城东D5+250~D8+500段大堤,于2005年12月31日之前完成全部土方填筑工程施工。

施工准备 料场复查 填土区测量放样 测量放样 布置截、排水系统 清理植被和表土 基础面验收 土方挖运 土方填筑夯实 不合格

逐层检查验收

完工验收 图10.5.1土方填筑施工工艺流程图

10.5.3技术要点

⑴ 土石方填筑任一单项工程开工前14天提交详细的措施计划一式四份,同时提交现场生产性土料试验方案和计划一份,一并报送工程师批准。

⑵ 现场土料试验包括铺料方式、铺料厚度、碾压机械类型及重量、碾压遍数、行进速度、填料最优含水量、压实后的干容重及渗透系数等提出试验成果,并整理编写成正式报告,经工程师批准后正式开工。

⑶ 按照批准的措施计划和设计图纸及相关技术规范规定的尺寸、高程及质量标准、实施各部位的填筑和碾压。

⑷ 经复查合格的填筑料按照施工规划进行开采,直接上堤填筑或依据填筑参数进行加工,不得混入任何有害物质,如淤沙、风化软弱的岩块、树枝树根、杂草及垃圾等。

⑸ 填筑基面或接触面须进行植被和表土清理,基面平整,并按工程师指示进行洒水或干燥和刨毛处理,将表皮以下0.1m之浅层先耙松并与第一层填料一道进行压实。

⑹ 土料铺筑至设计连续边线外侧超填0.1m(人铺料时)或0.3m(机械铺料时),新老结合层间的结合坡度不陡于1:3。填筑高程预留沉降超高按填筑相对高度的5%预留。

⑺ 用于填筑的土料不得含有杂草、树根等有机物及块石,不得含有腐殖土,并控制其含水量接近最优含水量,含水量允许偏差为+2%,渗透系数须满足设计要求。用于垫层、反滤层填筑的砂、砂卵石、碎(砾)石,其性能须满足设计图纸和有关规范要求,否则严禁使用。

⑻ 送不同填料的车辆相对固定,不同材料的运送车辆分别标记,运输车辆保持轮胎、车箱清洁,并保持车辆挡板严密,防止物料洒落污染环境。

⑼ 填筑作业时,分层平行堤轴线摊铺,厚薄一致、无结块,碾压机具平行堤轴线方向行驶;与老土结合的坡面上,配合填土上升将表面松土铲除,刨毛坡面;垂直堤轴线接缝坡度不陡于1:3,搭接碾压宽度不小3.0m,平行于堤轴方向搭接碾压宽度不小于0.5m。

⑽ 设有压浸平台的堤段,堤身与压浸平台同步填筑,严禁先筑堤身后压浸,并严格控制填筑速度。

⑾ 填土与刚性建筑物结合时,须于建筑物强度达到设计强度标准值的50%~70%方可填土;填土前,先清除建筑物表面的乳皮、粉尘及油污等;其外露铁件全部割除,并用水泥砂浆覆盖残余露头;建筑物表面先涂泥浆、边铺土、边夯实;两侧填土,均衡上升;贴边填筑采用人工夯实。

⑿ 垫层料、反滤料铺筑前,先将基础整平,放好样桩,做好场地排水后,由坡底开始自下而上逐层铺筑、压实;陡于1:1.5的垫层铺筑采用挡板支护施工;铺筑好的垫层料应及时进行上层护坡铺筑施工,严禁人、车通行。

⒀ 填筑料的含水量控制:填筑料按最优含水量进行控制,若需洒水则由碾压试验确定洒水量;若遇雨季,则按相关规范规定停工或施工,并且将填筑面向外侧倾斜,以利排水;下雨前采取覆盖和压光面层等措施,以防雨水下渗;雨后禁止践踏,直至调整到最优含水量再复工。

10.5.4检查和验收

⑴ 填筑前、填筑中、填筑后,都须按设计要求和工程师指示进行测量、放样、布设控制网,保证符合设计填筑轮廓的准确性。

⑵ 填筑前需检查填筑料质量是否符合要求;填筑中重点检查碾压参数、碾压情况判断含水量是否适当,随时检查有无层间光面、弹簧土地、漏压或欠压、裂缝等;检查填筑体与基础、岸坡、刚性建筑物的结合、纵向和横向接缝的处理与结合部位的压实质量,还须检查填筑后的压实度和干容量是否满足设计要求。

⑶ 填筑后质量检测依据《堤防工程施工规范》SL260-98《碾压式土石坝施工规范》DL/T5219-2001和《土工试验规程》SL237-1999、《土工试验方法标准》GBJ123-88进行。采用环刀法取样,主要检测干容重和含水量。大型碾压机械筑堤时约600m2取样一个,人工或小型机具筑堤时约300m2一个;自检时每层取样数量按填筑量每100~150m3取样一个,抽检量为自检量的1/3,但至少3个;特别狭长堤段的作业面,堤长每20~30m取样一个。根据填筑区域的实际条件,选择若干断面,每填高5m,取样做颗粒分析、相对密度、含水量、容重、比重、е值、中值、压缩系数、变形模量等物理力学试验,提供工程师审核和供工程验收备查。

⑷ 填筑前进行地形图、平面图、剖面图复核检查,基础面质量检查与验收,填筑料物理力学性质抽样验收和现场生产性试验成果的检查与验收。施工过程中对土料含水量、粘粒含量和垫层料颗粒级配、含泥量、软弱颗粒含量和形状等检查,以及对填筑体每一填筑层面质量进行工程隐蔽部位的验收。

分部填筑工程完工后,经自检合格,然后报请工程师进行检查、验收和工程质量等级评定。

10.6砌体工程 10.6.1工作内容 本合同砌体工程124943.31m3,其中浆砌体块石111956.49m3,浆砌砼预制块护坡12697.02m3,砌砖289.8m3。其施工内容包括砌体材料的提供、运输、浇捣、砌筑、勾凸缝、伸缩缝、排水管的设置及工程师指示的其他砌筑工作。

10.6.2施工方法

⑴ 首先清除砌体基面的腐殖土、草皮、树枝、杂物、垃圾等杂物,并且夯实、平整基面,经工程师检查验收合格后再进行垫层或砌体施工。

⑵ 垫层料一般选用粒径5~20mm的粗砂和碎石(或砾石)按厚度15cm均匀铺设并压实。当设计或工程师有明确要求时,则按其要求施工。

⑶ 浆砌块石砌筑时,选用合格石料,采用铺浆法分层卧砌。上、下错缝,内外搭砌、砌立稳定。石料先洒水湿润,使其表面充分吸水但不留残水。砌筑后12~18h之内对其外露面及时养护,保持湿润。持续养护时间至少14天。

⑷ 砖砌体施工采用M7.5水泥砂浆砌75#普通标准砖,于砌前1~2天浇水湿润使其含水10~15%,然后按坐浆法满浆平砌,做到上下错缝、内外搭砌,采用一顺一丁、梅花丁或三顺一丁的砌筑形式。每层承重墙的最上一皮砖、梁或梁垫的下面、砌体台阶水平面上以及砌体的挑出层(挑檐、腰线等),都须采用整砖丁砌层砌筑。砌砖体完工后至少洒水养护三天。

⑸ 护坡选用符合设计要求和相关技术要求的砼预制块,采用M7.5水泥砂浆砌筑。铺设的砂砾石垫层经工程师验收合格后,按设计规定分段分缝铺砌从坡脚开始,依次向上铺砌,并按设计要求布排丁、顺砌块,做到砌缝横平竖直,上下层竖缝错开距离大于10cm.。砼预制块砌筑后12~18h内开始养护,经常保持其外露面湿润,持续养护至少14天。

⑹ 砌筑砂浆采用M7.5水泥砂浆,采用砂浆搅拌机拌制,人力斗车运送。砌筑砂浆使用的水泥、中粗砂、掺合料和水等材料品质要求与砼的要求相同。

10.6.3技术要点

⑴ 砌筑砂浆强度须符合设计要求,配合比须经试验确定,并报工程师同意。砂浆稠度为70~90mm,必须搅拌均匀并于初凝前用完。

⑵ 浆砌块石所用面料必须选择质地坚硬、不易风化,没有裂缝且大致方正的块石,上下两面应大致平整、无尖角、块厚应大于20cm,不允许用片状石料。石料的抗水性、

抗冻性、抗压强度及块料尺寸等应符合设计及相关规范要求。用于表面的石料应有一个比较平整的表面。

⑶ 砌体的第一层石块都应大面朝下,第一层及其转角处、交叉处、洞穴孔口等,均应选用较大的平凿毛石。所有石块都应砌在新铺砂浆上,接缝必须填满,石缝不得直接紧靠,不允许采用外面侧立石、中间填心的方法砌石。砌缝要求饱满,勾缝平顺自然、匀称美观。

⑷ 砖砌体水平灰缝的砂浆饱满度不低于80%,竖向灰缝宜采用挤浆或加浆方法,使其砂浆饱满,严禁用水冲浆灌缝。埋入砖砌体中的拉结筋必须位置正确、平直,其外露部分在施工过程上不得任意弯插;框架结构中的填充墙应与框架中预埋的拉结筋连接。外墙转弯处严禁留直槎,普通粘土砖斜槎长度不小于高度的2/3。墙角预留洞口时两侧墙面不小于500mm,洞口顶部设置钢筋砼过梁。 ⑸ 预制砼护坡砌筑时水平缝宽不大于15mm,竖缝宽不大于20mm。铺砌完工后表面整洁、缝路清晰,无砂浆、沥青等污染,表面必须平整美观。

⑹ 冬季室外月平均气温连续5天低于5℃且最低气温低于-3℃时,应保温防冻。

10.6.4质量检查与验收

⑴ 用于砌体工程的石料、砖和砼预制块都应进行物理性质和外形尺寸检查。砌筑砂浆所用原材料即水泥、水、外加剂及砂和砾石等都应按规范规定进行质量检测。定期检查砂浆的配合比和均匀性,拌和机出料口出料时间的始末所取试样测定的湿容重,前后差值每立方米不大于35kg;砂浆28天龄前强度检测取样每200m3一组试件3个。同品种、同标号砂浆组试块的平均强度不小于砂浆强度的标准值;任意一个试块的强度不小于0.75砂浆强度标准值。砌体中砂浆的饱满度必须符合规范规定。

⑵ 浆砌石外观检测,其表面平整度用2m尺检测表面偏差不大于30mm,平缝宽15~20mm,竖缝宽20~30mm。并且须检查排水管的坡度及畅通情况。

⑶ 砖砌体做到砖柱、砖垛无包心砌法,窗间墙及清水墙面无通缝;混水墙每间(处)的4~6皮砖通缝不超过3处。砖墙体接槎处缝、砖平直,水平缝厚度不小于5mm,灰浆密实透亮缺陷不超过10个。预埋拉结筋间距偏差不超过3皮砖。构造柱位置须正确。清水墙尺寸允许偏差须符合《砌体工程施工及验收规范》GB50203-98表4.1.8的规定。

⑷ 砼预制块砌体须进行外观检查,即平整度、勾缝质量,缝隙砂浆饱满度、伸缩缝贯通情况等,同时检查排水管坡度及畅通情况。

⑸ 砌体工程砌筑前进行的测量放样成果的检查和基础面开挖清理质量的检查和验收,砌筑过程中对各项材料检测、以及完工、自检后,报请工程师检查、验收,并进行质量等级评定。

10.7 混凝土工程 10.7.1工作内容

本合同混凝土工程砼及钢筋砼工程62199.96m3。其中:大堤C15砼垫层2699.01m3、C20砼挡墙29791.83m3,C15砼预制块共12697.02m3,C20现浇砼护坡11751.90m3,涵闸C15砼垫层213.2m3,闸墩砼C20、闸底板砼C20、管身砼C20、梁板柱砼C20及二期

砼共1560m;电排站C15砼垫层797.20m、C20砼泵房、C20水下砼、闸墩C20砼、闸底板、管身C20砼及梁、板、柱共2689.8m3,钢筋砼中含钢筋916.8吨。

10.7.2 施工方法

本合同砼工程相对分散,很不集中。主要分布于城西城东区堤段的砼护坡、C20砼挡墙,6处电排站和6处涵闸工程。

⑴ 砼拌制和运输

根据其特点,采用现场拌制和工厂化生产相结合的生产方法拌制砼。6处涵闸和6处电排站的现浇砼6305.54m3,分别于X0+920,X3+000、X4+230、X6+800、D5+300、D4+050等桩号处建立砼搅拌站6处现场拌制砼,该6处涵闸或电排站现拌现浇,另1处交通涵闸杨家坝涵闸则由就近的砼搅拌站拌制砼后,1T翻斗车运送到施工现场进行浇筑;城西区7662m堤防和城东区8500m堤防上的挡墙砼,护坡砼于鲇鱼港电排和团山电排站处设置2台*0.8m3拌和楼2处集中生产,拌制好的砼,由5T自卸车运送,皮带机转运入仓浇筑;城西和城东堤防上的C15砼预制块12697.02m3,采用工厂化生产,于大堤填筑完工后,利用堤顶开辟生产场地,集中生产保养,达到设计强度后进行护砌。

⑵ 模板工程:

砼工程使用的模板绝大部分使用大模板、组合钢模板与异形木模板相结合的方法,预制砼块使用定型钢模,现浇砼的异型模板使用木模板以便与所需形状相吻合。 ⑶ 砼捣实采用插入式震捣器和平板震捣器捣实。

⑷ 砼养护:钢筋砼防洪墙、4处涵闸、30处电排站和砼护坡等水工建筑物分别建造储水池储备养护用水,并使用薄膜和草袋覆盖,保持砼表面湿润,养护28天。 ⑸ 钢筋工程:钢筋制作采用切割机、调直机、弯曲机制作成型,人工绑扎、焊接按设计要求制作骨架。

⑹ 现浇砼工程施工工艺流程见图10.7.1

10.7.3技术要点

1. 模板制安

(1) 为了得到要求的结构物形状,或需限制砼流动,都需设置模板。模板要有足够的强度和刚度,以承受荷载、满足稳定性和不变形走样等要求;还要有足够的密封性,以保证不漏浆。模板的设计、选型、材料、制作、安装、拆除及维修等均遵照《水利水电工程模板施工规范》DL/T5110-2000中的有关规定,并报工程师批准。

(2) 材料:优先使用组合钢模和大模板;为保证表面平整,曲面光滑,少量配用木模板。模板内侧使用的模板油和脱模剂先报工程师批准,并且不应导致砼表面受化学损坏和褪色。

(3) 制作:按设计建筑物结构外形制作模板,其允许偏差不超过DL/T5110-2000中第7.0.1条的规定。木模板采用10×12cm背方和撑方。

安装:先准确测量放样,多设控制点,以利检查校正。模板安装过程中,设置足够的临时固定设施以防倾复。支架必须设在坚实地基或老混凝土上,斜撑须防止滑动。

33

施工准备 模板制作 测量放样 钢筋检测砼原材料检测:水泥、砂子、粗骨料、水、掺合料、外加剂 基槽清理或基层面清理 钢筋制作 砼配比设计 模板安装 钢筋安装 砼拌制 砼运输 砼浇捣 砼养护 拆除模板 检查与完工验收

图10.7.1现浇砼生产工艺流程图

(4) 采用Φ12~Φ14的拉条锚固,使模板之间接缝严密、平整、而易于拆除。砼分层施工时接缝处使用薄海绵带垫帖,防模板下端出现错面。模板不能固定在结构钢筋或埋件上、岩石支护加固的张拉锚杆、非张拉锚杆或锚固体都不能用作模板的支撑物。

(5) 模板安装后,在混凝土浇筑前、浇筑中及浇筑后都按规范要求进行严格检测,其允许偏差应符合DL/T5110-2000中表8.0.9-2的规定。

(6) 看护: ① 侧模:不承重侧面模板的拆除,应在混凝土强度达到其表面及棱角不因拆模而损伤时,方可拆除:在墩、墙和柱部位在其强度不低于10.5Mpa时,方可拆除:

② 底模:底模在混凝土强度达到表10.7-1的规定后,方可拆除:

③ 模板拆除时需小心谨慎,分批拆除锚固连接中,防止大片模板堕落,避免砼表面损坏。

④ 在梁、墩、板砼未到100%设计强度时其上不能承受施工荷载。

⑤ 拆下的模板、支架及配件等,及时清理维修、分类堆放,妥善保管。

底 模 拆 模 标 准

表10.7-1 结构类型 板 结构跨度(m) ≤2 >2,≤8 >8 梁、拱、壳 悬臂构件

≤8 >8 ≤2 >2 按设计的混凝土强度标准值的百分率计(%) 50 75 100 75 100 75 100 2. 钢筋制安

(1) 钢筋材料与制作

① 在配筋前不少于14天,提交根据钢筋布置图作出的钢筋加工详图一式四份,供工程师批准。

② 钢筋混凝土结构用的钢筋,其种类、钢号、直径等均按设计图纸规定,并经过材质试验。如因某种原因,要求以另一种钢号或直径的钢筋代替设计图纸规定的钢筋时,必须征得工程师的同意。热轧钢筋的性能必须符合规范《钢筋混凝土用热轧带肋钢筋》GB1499-1998、《钢筋混凝土用热轧光圆钢筋》GB13013-1991的要求。

③ 钢筋的切割、弯曲遵照《水工混凝土施工规范》SDJ207-82的规定执行。 ④ 钢筋的表面应洁净,使用前将表面油渍、漆污、锈皮、鳞等清除干净。钢筋须平直,无局部弯折,钢筋中心同直线的偏差不超过其长度的1%。成盘的钢筋或弯曲的钢筋均应矫直后,才允许使用。

⑤ 加工后钢筋的允许偏差应符合表10.7-2的规定。

加工后钢筋的允许偏差

表10.7-2 项次 1 2 3 4 偏差名称 受力钢筋全长净尺寸的偏差 箍筋各部分长度的偏差 钢筋弯起点位置的偏差 钢筋转角的偏差 机房构件 大体积混凝土 允许偏差值(mm或度) ±10 ±5 ±20 ±30 3

(2) 钢筋架设

① 钢筋安装的位置、间距、保护层及各部分钢筋大小的尺寸均按设计图纸的规定。其偏差应符合下表10.7-3的规定。

② 在已架设好的钢筋工作中,不应再沾上泥土、有害的铁锈、松散的铁屑、油漆、油脂或其他外来的物质。当钢筋配置绑扎以后,一定要使其钢筋或钢筋网保持清洁状态直到完全埋入混凝土为止。

钢筋安装允许偏差

表10.7-3 项次 1 2 3 4 5 6 偏差名称 钢筋长度方向的偏差 同一排受力钢筋间距的局部偏差 1)柱及梁中 2)板、墙中 同一排中分布钢筋间距的误差 双排钢筋,其排与排间距的局部误差 梁与柱中箍筋间距的误差 保护层厚度的局部误差 允许偏差 ±1/2净保护层厚 ±0.5d ±0.1间距 ±0.1间距 ±0.1间距 0.1箍筋间距 ±1/4净保护层厚 ③ 现场焊接或绑扎的钢筋网,其钢筋的连接按设计图纸规定执行。如图中未作规定,且钢筋直径在25mm以下时,则除楼板和墙内靠近外围两行钢筋之相交点应逐点绑扎除外,其余按50%的交叉点绑扎。

④ 为了保证混凝土保护层的必要厚度,在钢筋与模板之间设置强度不低于结构物件设计强度的混凝土垫块。垫块应埋设铁丝并与钢筋扎紧。垫块互相错开,分散布置。在各排钢筋之间,用短钢筋支撑以保证位置准确。

⑤ 钢筋混凝土结构中受力钢筋的混凝土保护层厚度按工程师指示和规范的要求执行。

⑥ 钢筋或钢筋网一定要精确就位并牢牢加以固定,钢筋或钢筋网与任何相邻金属埋件之间的距离至少为25mm,以便在混凝土浇筑期间不使钢筋或钢筋发生位移。确保在已浇筑的混凝土内的钢筋或钢筋网没有扰动。支撑钢筋用的托架、吊架垫块以及其它允许的金属混凝土支座,不使用容易生锈斑的垫块。

⑦ 钢筋架设完毕须经检查,并符合设计图纸要求后,方能浇筑混凝土。 (3)钢筋接头

① 如有必要拼接钢筋可根据图纸的规定,采用焊接接头或机械接头。钢筋的接头应遵照SDJ207-82的规定执行。

② 钢筋或钢筋网的接头位置按设计图纸确定,相邻钢筋的接头错开。

③ 如果拟使用机械的套管接头,则在使用前至少14天,提交这种管套的样品,以供工程师批准。凡是直径等于或大于32mm的钢筋都使用经过批准的机械接头,如果采用焊接能保证在接头处保持最小钢筋间距,也可使用焊接接头。对于直径小于32mm的钢筋都采用焊接接头或机械套管接头。

④ 如拟使用焊接接头则在安装钢筋前至少14天提交按有关规范规定进行焊接试验成果和采用的焊接程序、电焊条和电焊设备的详细资料,以供工程师批准。

⑤ 钢筋的焊接接头采用闪光对头焊接,当不能进行闪光对焊时,宜采用电弧焊(搭接焊、帮条焊、熔槽焊等)。钢筋接头焊接前,将施焊范围内的浮锈、漆污、油渍等清除干净。直径小于25mm钢筋也可采用绑扎接头,但轴心受拉、小偏心受拉构件和承受振动荷载的构件,其钢筋接头不得采用绑扎接头。

⑥ 直径为10mm以上的热轧钢筋,其接头采用搭接焊、帮条电弧焊时,应符合下列要求:

a. 搭接焊、帮条焊的接头做成双面焊缝。对I级钢筋搭接的帮条的焊接长度不小于钢筋直径的4倍,对于II、III级钢筋和5号钢筋,其搭接和帮条的焊接长度不小于钢筋直径的5倍。

b. 帮条的总截面应符合下列要求:当主筋为I级钢筋时,不小于主筋截面面积的1.2倍,当主筋为II、III级钢筋和5号钢筋时,不小于主筋截面面积的1.5倍。帮条宜采用与主筋同钢号、同直径的钢筋制成。

c. 搭接焊接的两根搭接钢筋的轴线,应位于同一直线上。

3. 砼的原材料

对砼原材料即水泥、骨料、水、掺合料和外加剂的要求列入表10.7-4 4. 砼配比设计

(1) 不同部位、不同强度、等级的砼,分别满足抗压、抗渗、抗裂、抗风化和抗侵蚀等要求,并同时满足和易性等要求。合理降低水泥用量均由试验确定优化的砼配合比。

(2) 水灰比、粗骨料级配及砂率选用,经试验确定后,报工程师指认,方可投入使用。 (3) 混凝土的坍落度,应根据建筑物的性质、钢筋含量、混凝土运输、浇筑方法和气象条件决定,尽量采用小的坍落度,混凝土在浇筑地点的坍落度可按下表10.7-5

混凝土在浇筑地点的坍落度(使用振捣器)

表10.7-5 建筑物的性质 水工素混凝土或少筋混凝土 配筋率不超过1%的钢筋混凝土 配筋率超过1%的钢筋混凝土 标准圆锥坍落度(cm) 3~5 5~7 7~9

5. 砼拌和与运输 (1) 砼拌和

① 砼配合比经工程师批准后,称量入机拌和,其称量误差:水泥和混合材<±1%,骨料<±2%,水、外加剂溶液<±1%。

② 采用0.4m3拌和机搅拌霎时间≦2.5min。 (2) 砼运输

① 选用机动翻斗车和自卸车运输,经皮带机转运的运输方式。

② 凝土运输时间控制见表表10.7-6

砼运输时间控制表

表10.7-6

气温(℃) 20-30 10-20 5-10 不含运输时间(min) 30 45 60