梁板模板专项施工方案(毕业设计也可用)
更新时间:2024-05-24 23:08:01 阅读量: 综合文库 文档下载
- 梁板吊装专项施工方案推荐度:
- 相关推荐
梁模板专项施工方案
XXXX学院
毕业设计说明书
院 系:_ 土木工程系 专 业:_ 建筑工程技术 班 级:_XXXXXXXXXXXX 学 号:__XXXXXXXXXX 学生姓名: XX 指导教师:_ XXXXXX _
20XX年 XX 月 XX 日
1
梁模板专项施工方案
目 录
一 工程概况 ························································································· 1 二 编制依据 ························································································· 1 三 模板方案选择 ··················································································· 1 四 材料选择 ························································································· 1 五 模板安装 ························································································· 4 六 模板拆除 ························································································· 5 七 安全、环保文明施工措施 ································································· 6 八 模板技术措施和验收 ································································ 7 九 框架梁模板计算书 ·········································································· 12
2
梁模板专项施工方案
梁模板专项施工方案
一 工程概况
本工程建筑物面积为11073.9m2,结构类型为框架结构建筑设计使用年限50年,耐火等级为二级,本工程火灾危险类别属丙类,屋面防水等级为二级,使用年限为15年,抗震设防烈度为6度 二 编制依据
《建筑结构荷载规范》GB50009-2001中国建筑工业出版社; 《混凝土结构设计规范》GB50010-2002中国建筑工业出版社;
《建筑施工扣件式钢管脚手架安全技术规范》JGJ130-2001 中国建筑工业出版社;
《钢结构设计规范》GB 50017-2003中国建筑工业出版社; 三 模板方案选择
本工程考虑到施工工期、质量和安全要求,故在选择方案时,应充分考虑以下几点:
1、模板及其支架的结构设计,力求做到结构要安全可靠,造价经济合理。 2、在规定的条件下和规定的使用期限内,能够充分满足预期的安全性和耐久性。
3、选用材料时,力求做到常见通用、可周转利用,便于保养维修。 4、结构选型时,力求做到受力明确,构造措施到位,升降搭拆方便,便于检查验收;
5、综合以上几点,模板及模板支架的搭设,还必须符合JCJ59-99检查标准要求,要符合省文明标化工地的有关标准。 四 材料选择
按清水混凝土的要求进行模板设计,在模板满足强度、刚度和稳定性要求的前提下,尽可能提高表面光洁度,阴阳角模板统一整齐。 梁模板(扣件钢管架)
面板采用18mm 胶合面板50×100木方(内楞)现场拼制,圆钢管48×3.5(外楞)支撑,采用可回收M12对拉螺栓进行加固。梁底采用50×100木方支撑。承重架采用扣件式钢管脚手架,由扣件、立杆、横杆、支座组成,采用υ48×3.5钢管。
3
梁模板专项施工方案
五 模板安装
1、模板安装的一般要求
竖向结构钢筋等隐蔽工程验收完毕、施工缝处理完毕后准备模板安装。安装柱模前,要清除杂物,焊接或修整模板的定位预埋件,做好测量放线工作,抹好模板下的找平砂浆。 (2)主体结构模板工程 1、模板体系的选用
为保证主体结构的质量目标的实现,使主体结构砼达到清水砼效果,根据结构布置情况,本工程将采用如下模板体系:结构框架柱、墙体与楼面梁板砼分开浇筑,墙体模板采用20厚胶竹模板体系;框架柱、梁板采用胶合大模板,模板支撑采用快拆支撑体系。
2、模板安装: 框架梁板模板
1.模板安装顺序:搭设和调平模板支架(包括安装水平拉杆和剪力撑)→按标高铺梁底模板→拉线找直→绑扎梁钢筋→安装垫块→梁两侧模板→调整模板 2.技术要点:按设计要求起拱(跨度大于4m日寸,起拱0.2%)梁的侧模包住底模,下面龙骨包底侧模。
梁模板施工要点:当梁高超过60cm时,需加50cm×10cm腰楞。 2、模板组拼
模板组装要严格按照模板配板图尺寸拼装成整体,模板在现场拼装时,要控制好相邻板面之间拼缝,两板接头处要加设卡子,以防漏浆,拼装完成后用钢丝把模板和竖向钢管绑扎牢固,以保持模板的整体性。拼装的精度要求如下: 1、两块模板之间拼缝 ≤1 2、相邻模板之间高低差 ≤1 3、模板平整度 ≤2 4、模板平面尺寸偏差 ±3 3、模板定位
当底板或顶板混凝土浇筑完毕并具有一定强度(≥1.2MPa),即用手按不松软、无痕迹,方可上人开始进行轴线投测。根据轴线位置放出墙柱截面位置尺寸
4
梁模板专项施工方案
线、模板500 控制线,以便于梁模板的安装和校正。当混凝土浇筑完毕,模板拆除以后,开始引测楼层500mm 标高控制线,并根据该500mm 线将板底的控制线直接引测到上。
首先引测建筑物的主轴线的控制线,并以该控制线为起点,引出每道轴线,根据轴线与施工图用墨线弹出模板的内线、边线以及外侧控制线,施工前三线必须到位,以便于模板的安装和校正。 4、模板的支设
模板支设前用空压机将楼面清理干净。不得有积水、杂物,并将施工缝表面浮浆剔除,用水冲净。所有内侧模板必须刷油性脱模剂。 5、梁模板支撑
梁模板(扣件钢管架)
1、梁侧模板采用木方作为内楞间距400mm,钢管作为外楞间距600mm,采用可回收的M12普通穿墙螺栓加固水平间距600mm,竖向间距同外楞。梁模板采用18mm胶合面板作为面板,梁底采用小头直径为50mm 圆木横向布置,间距300mm。纵向支承为υ48×3.5钢管。扣件式钢管脚手架作为撑系统,脚手架梁跨方向1.5m,梁两侧立杆间0.8m,步距1m。 2、梁模板施工时注意以下几点:
(1)横板支撑钢管必须在楼面弹线上垫木方;
(2)钢管排架搭设横平竖直,纵横连通,上下层支顶位置一致,连接件需连接牢固,水平拉撑连通;
(3)根据梁跨度,决定顶板模板起拱大小:<4不考虑起拱,4≤L<6起拱10mm,≥6 的起拱15mm; 六 模板拆除
1、模板拆除根据现场同条件的试块指导强度,符合设计要求的百分率后,由技术人员发放拆模通知书后,方可拆模。
2、模板及其支架在拆除时混凝土强度要达到如下要求。在拆除侧模时,混凝土强度要达到1.2MPa(依据拆模试块强度而定),保证其表面及棱角不因拆除模板而受损后方可拆除。混凝土的底模,其混凝土强度必须符合下表规定后方可拆除。
5
梁模板专项施工方案
3、拆除模板的顺序与安装模板顺序相反,先支的模板后拆,后支的先拆。 4、模板拆除吊至存放地点时,模板保持平放,然后用铲刀、湿布进行清理。支模前刷脱模剂。模板有损坏的地方及时进行修理,以保证使用质量。 5、模板拆除后,及时进行板面清理,涂刷隔离剂,防止粘结灰浆。 七 安全、环保文明施工措施
(1)拆模时操作人员必须挂好、系好安全带。 (2)支模前必须搭好相关脚手架。
(3)在拆墙模前不准将脚手架拆除,用塔吊拆时与起重工配合;拆除顶板模板前划定安全区域和安全通道,将非安全通道用钢管、安全网封闭,挂\禁止通行\安全标志,操作人员不得在此区域,必须在铺好跳板的操作架上操作。 (4)浇筑混凝土前必须检查支撑是否可靠、扣件是否松动。浇筑混凝土时必须由模板支设班组设专人看模,随时检查支撑是否变形、松动,并组织及时恢复。经常检查支设模板吊钩、斜支撑及平台连接处螺栓是否松动,发现问题及时组织处理。
(5)木工机械必须严格使用倒顺开关和专用开关箱,一次线不得超过3m,外壳接保护零线,且绝缘良好。电锯和电刨必须接用漏电保护器,锯片不得有裂纹(使用前检查,使用中随时检查);且电锯必须具备皮带防护罩、锯片防护罩、分料器和护手装置。使用木工多用机械时严禁电锯和电刨同时使用;使用木工机械严禁戴手套;长度小于50cm 或厚度大于锯片半径的木料严禁使用电锯;两人操作时相互配合,不得硬拉硬拽;机械停用时断电加锁。
(6)用塔吊吊运模板时,必须由起重工指挥,严格遵守相关安全操作规程。模板安装就位前需有缆绳牵拉,防止模板旋转不善撞伤人;垂直吊运必须采取两个以上的吊点,且必须使用卡环吊运。不允许一次吊运二块模板
(7)钢模板堆放时,使模板向下倾斜30°,不得将模板堆放在施工层上,防止模板在风荷载下倾覆。
(8)大模板堆放场地要求硬化、平整、有围护,阴阳角模架设小围护架放置。安装就位后,要采取防止触电保护措施,将大模板加以串联,并同避雷网接通,防止漏电伤人。
(9)在电梯间进行模板施工作业时,必须层层搭设安全防护平台。因混凝
6
梁模板专项施工方案
土侧力既受温度影响,又受浇筑速度影响,因此当夏季施工温度较高时,可适当增大混凝土浇筑速度,秋冬季施工温度降低混凝土浇筑速度也要适当降低。当T=15℃时,混凝土浇筑速度不大于2m3/h。 (10)环保与文明施工
夜间22:00~6:00 之间现场停止模板加工和其他模板作业。现场模板加工垃圾及时清理,并存放进指定垃圾站。做到工完场清。整个模板堆放场地与施工现场要达到整齐有序、干净无污染、低噪声、低扬尘、低能耗的整体效果。
八 模板技术措施和验收
1、进场模板质量标准
模板要求:
(1)技术性能必须符合相关质量标准(通过收存、检查进场木胶合板出厂合格证和检测报告来检验)。
(2)外观质量检查标准(通过观察检验)
任意部位不得有腐朽、霉斑、鼓泡。不得有板边缺损、起毛。每平方米单板脱胶不大于0.001m2 。每平方米污染面积不大于0.005m2 (3)规格尺寸标准
厚度检测方法:用钢卷尺在距板边20mm 处,长短边分别测3 点、1 点,取8 点平均值;各测点与平均值差为偏差。长、宽检测方法:用钢卷尺在距板边100mm 处分别测量每张板长、宽各2点,取平均值。对角线差检测方法:用钢卷尺测量两对角线之差。翘曲度检测方法:用钢直尺量对角线长度,并用楔形塞尺(或钢卷尺)量钢直尺与板面间最大弦高,后者与前者的比值为翘曲度。
2、模板安装质量要求
必须符合《混凝土结构工程施工及验收规范》(GB 50204-2002)及相关规范要求。即\模板及其支架应具有足够的承载能力、刚度和稳定性,能可靠地承受浇筑混凝土的重量、侧压力以及施工荷载\。 (1)主控项目
1)安装现浇结构的上层模板及其支架时,下层楼板应具有承受上层荷载的承载能力,或加设支架;上下层支架的立柱应对准,并铺设垫板。
7
梁模板专项施工方案
检查数量:全数检查。
检验方法:对照模板设计文件和施工技术方案观察。 2)在涂刷模板隔离剂时,不得沾污钢筋和混凝土接槎处。 检查数量:全数检查。 检验方法:观察。 (2) 一般项目
1)模板安装应满足下列要求:
模板的接缝不应漏浆;在浇筑混凝土前,木模板应浇水湿润,但模板内不应有积水;模板与混凝土的接触面应清理干净并涂刷隔离剂;浇筑混凝土前,模板内的杂物应清理干净; 检查数量:全数检查。 检验方法:观察。
2)对跨度不小于4m 的现浇钢筋混凝土梁、板,其模板应按要求起拱。 检查数量:按规范要求的检验批(在同一检验批内,对梁,应抽查构件数量的10%,且不应少于3 件;对板,应按有代表性的自然间抽查10%,且不得小于3 间。)检验方法:水准仪或拉线、钢尺检查。
3)固定在模板上的预埋件、预留孔洞均不得遗漏,且应安装牢固其偏差应符合附表1的规定;
模板安装允许偏差和检查方法 附表1 项次 1 2 3 轴线位移 项目 柱、墙、梁 国家规范标准允许偏差(mm) 5 ±5 ±10 +4,-5 6 8 2 5 方正 阴阳角 8 垂直度 5 5 5 经纬仪或拉线、尺量 尺量 靠尺,塞尺 方尺,塞尺 线尺 拉线,尺量 尺量 检查方法 尺量 水准仪或拉线、尺量 底模上表面标高 截面模内尺寸 基础 柱、墙、梁 层高不大于5m 层高垂直度 层高大于5m 4 5 6 7 相邻两板表面高低差 表面平整度 预埋铁件中心线位移 8
梁模板专项施工方案
9 中心线位移 预埋管、螺栓 螺栓外露长度 3 +10,-0 +10 +10,-0 +10,-0 +10,-0 +10,-0 5 +10,-0 拉线,尺量 拉线,尺量 拉线,尺量 拉线,尺量 10 预留孔洞 11 门窗洞 12 插筋 中心线位移 尺寸 中心线位移 宽、高 对角线 中心线位移 外露长度 检查数量:按规范要求的检验批(对梁、柱,应抽查构件数量的10%,且不应少于3 件;对墙和板,应按有代表性的自然间抽查10%,且不得小于3间)。 检验方法:钢尺检查。
(3)现浇结构模板安装的偏差应符合表1 的规定。
检查数量:按规范要求的检验批(对梁、柱,应抽查构件数量的10%,且不应少于3 件;对墙和板,应按有代表性的自然间抽查10%,且不得小于3间)。现浇结构模板安装允许偏差和检验方法见表1:(检验方法:检查同条件养护试块强度试验值。检查轴线位置时,应沿纵、横两个方向量测,并取其中的较大值。) (4)模板垂直度控制
1)对模板垂直度严格控制,在模板安装就位前,必须对每一块模板线进行复测,无误后,方可模板安装。
2)模板拼装配合,工长及质检员逐一检查模板垂直度,确保垂直度不超过3mm,平整度不超过2mm;
3)模板就位前,检查顶模棍位置、间距是否满足要求。 (5)顶板模板标高控制
每层顶板抄测标高控制点,测量抄出混凝土墙上的500线,根据层高4500mm及板厚,沿墙周边弹出顶板模板的底标高线。 (6)模板的变形控制
1)墙模支设前,竖向梯子筋上,焊接顶模棍(墙厚每边减少1mm)。 2)浇筑混凝土时,做分层尺竿,并配好照明,分层浇筑,层高控制在500以内,严防振捣不实或过振,使模板变形。 3)门窗洞口处对称下混凝土;
9
梁模板专项施工方案
4)模板支立后,拉水平、竖向通线,保证混凝土浇筑时易观察模板变形,跑位;
5)浇筑前认真检查螺栓、顶撑及斜撑是否松动; 6)模板支立完毕后,禁止模板与脚手架拉结。 (7)模板的拼缝、接头
模板拼缝、接头不密实时,用塑料密封条堵塞。 (8)清扫口的留置
楼梯模板清扫口留在平台梁下口,清扫口50×100 洞,以便用空压机清扫模内的杂物,清理干净后,用木胶合板背订木方固定。
(9)跨度小于4m 不考虑,4~6m 的板起拱10mm;跨度大于6m 的板起拱15mm。 (10)与安装配合
合模前与钢筋、水、电安装等工种协调配合,合模通知书发放后方可合模。 (11)混凝土浇筑时,所有墙板全长、全高拉通线,边浇筑边校正墙板垂直度,每次浇筑时,均派专人专职检查模板,发现问题及时解决。
(12)为提高模板周转、安装效率,事先按工程轴线位置、尺寸将模板编号,以便定位使用。拆除后的模板按编号整理、堆放。安装操作人员应采取定段、定编号负责制。
3、其他注意事项
在模板工程施工过程上中,严格按照模板工程质量控制程序施工,另外对于一些质量通病制定预防措施,防患于未然,以保证模板工程的施工质量。严格执行交底制度,操作前必须有单项的施工方案和给施工队伍的书面形式的技术交底。
(1)胶合板选统一规格,面板平整光洁、防水性能好的。
(2)进场木方先压刨平直统一尺寸,并码放整齐,木方下口要垫平。 (3)模板配板后四边弹线刨平,以保证墙体、柱子、楼板阳角顺直。 (4)墙模板安装基层找平,并粘贴海绵条,模板下端与事先做好的定位基准靠紧,以保证模板位置正确和防止模板底部漏浆,在外墙继续安装模板前,要设置模板支撑垫带,并校正其平直。
(5)墙模板的对拉螺栓孔平直相对,穿插螺栓不得斜拉硬顶。内墙穿墙螺
10
梁模板专项施工方案
栓套硬塑料管,塑料管长度比墙厚少2~3mm。
(6)门窗洞口模板制作尺寸要求准确,校正阳角方正后加固,固定,对角用木条拉上以防止变形。
(7)支柱所设的水平撑与剪刀撑,按构造与整体稳定性布置。
4、脱模剂及模板堆放、维修
(1)木胶合板选择水性脱模剂,在安装前将脱膜剂刷上,防止过早刷上后被雨水冲洗掉。
(2)模板贮存时,其上要有遮蔽,其下垫有垫木。垫木间距要适当,避免模板变形或损伤。
(3)装卸模板时轻装轻卸,严禁抛掷,并防止碰撞,损坏模板。周转模板分类清理、堆放。
(4)拆下的模板,如发现翘曲,变形,及时进行修理。破损的板面及时进行修补。
九 框架梁模板计算书
11
梁模板专项施工方案
梁模板(扣件钢管架)
一、参数信息
1.模板支撑及构造参数 梁截面宽度 B(m):0.30; 梁截面高度 D(m):0.90 混凝土板厚度(mm):120.00;
立杆纵距(沿梁跨度方向间距)La(m):1.00; 立杆上端伸出至模板支撑点长度a(m):0.10; 脚手架步距(m):1.50;
梁支撑架搭设高度H(m):3.60; 梁两侧立柱间距(m):0.80;
承重架支设:1根承重立杆,木方支撑垂直梁截面; 立杆横向间距或排距Lb(m):1.00; 采用的钢管类型为Φ48×3.50;
扣件连接方式:双扣件,考虑扣件质量及保养情况,取扣件抗滑承载力折减
12
梁模板专项施工方案
系数:0.80;
2.荷载参数
模板自重(kN/m2):0.35; 钢筋自重(kN/m3):1.50;
施工均布荷载标准值(kN/m2):2.5; 新浇混凝土侧压力标准值(kN/m2):18.0; 倾倒混凝土侧压力(kN/m2):2.0; 振捣混凝土荷载标准值(kN/m2):2.0 3.材料参数
木材品种:粗皮落叶松;
木材弹性模量E(N/mm2):10000.0; 木材抗弯强度设计值fm(N/mm2):17.0; 木材抗剪强度设计值fv(N/mm2):1.7; 面板类型:胶合面板;
钢材弹性模量E(N/mm2):210000.0; 钢材抗弯强度设计值fm(N/mm2):205.0; 面板弹性模量E(N/mm2):9500.0; 面板抗弯强度设计值fm(N/mm2):13.0; 4.梁底模板参数 梁底纵向支撑根数:2; 面板厚度(mm):18.0; 5.梁侧模板参数 主楞间距(mm):600; 次楞间距(mm):400;
穿梁螺栓水平间距(mm):600; 穿梁螺栓竖向间距(mm):400; 穿梁螺栓直径(mm):M12; 主楞龙骨材料:钢楞; 截面类型为圆钢管48×3.5;
13
梁模板专项施工方案
主楞合并根数:2;
次楞龙骨材料:木楞,,宽度50mm,高度100mm; 次楞合并根数:2; 二、梁模板荷载标准值计算 1.梁侧模板荷载
强度验算要考虑新浇混凝土侧压力和倾倒混凝土时产生的荷载;挠度验算只考虑新浇混凝土侧压力。
按《施工手册》,新浇混凝土作用于模板的最大侧压力,按下列公式计算,并取其中的较小值:
其中 γ -- 混凝土的重力密度,取24.000kN/m3;
t -- 新浇混凝土的初凝时间,可按现场实际值取,输入0时系统按200/(T+15)计算,得5.714h;
T -- 混凝土的入模温度,取20.000℃; V -- 混凝土的浇筑速度,取1.500m/h;
H -- 混凝土侧压力计算位置处至新浇混凝土顶面总高度,取0.750m; β1-- 外加剂影响修正系数,取1.200; β2-- 混凝土坍落度影响修正系数,取1.000。
根据以上两个公式计算的新浇筑混凝土对模板的最大侧压力F; 分别为 44.343 kN/m2、18.000 kN/m2,取较小值18.000 kN/m2作为本工程计算荷载。
三、梁侧模板面板的计算
面板为受弯结构,需要验算其抗弯强度和刚度。强度验算要考虑新浇混凝土侧压力和倾
倒混凝土时产生的荷载;挠度验算只考虑新浇混凝土侧压力。计算的原则是按照龙骨的间
距和模板面的大小,按支撑在内楞上的三跨连续梁计算。
14
梁模板专项施工方案
面板计算简图 1.抗弯验算
其中, σ -- 面板的弯曲应力计算值(N/mm2); M -- 面板的最大弯距(N.mm);
W -- 面板的净截面抵抗矩,W = 60.00×1.8×1.8/6=32.40cm3; [f] -- 面板的抗弯强度设计值(N/mm2); 按以下公式计算面板跨中弯矩:
其中 ,q -- 作用在模板上的侧压力,包括:
新浇混凝土侧压力设计值: q1= 1.2×0.60×18.00×0.90=11.66kN/m;
倾倒混凝土侧压力设计值: q2= 1.4×0.60×2.00×0.90=1.51kN/m;
q = q1+q2 = 11.664+1.512 = 13.176 kN/m; 计算跨度(内楞间距): l = 400.00mm;
面板的最大弯距 M= 0.1×13.18×400.002 = 2.11×105N.mm; 经计算得到,面板的受弯应力计算值: σ = 2.11×105 / 3.24×104=6.507N/mm2;
面板的抗弯强度设计值: [f] = 13.000N/mm2;
面板的受弯应力计算值 σ =6.507N/mm2 小于 面板的抗弯强度设计值 [f]=13.000N/mm2,满足要求!
15
梁模板专项施工方案
2.挠度验算
q--作用在模板上的侧压力线荷载标准值: q = 18.00×0.60 = 10.80N/mm;
l--计算跨度(内楞间距): l = 400.00mm; E--面板材质的弹性模量: E = 9500.00N/mm2; I--面板的截面惯性矩: I = 60.00×1.80×1.80×1.80/12=29.16cm4;
面板的最大挠度计算值: ω =
0.677×10.80×400.004/(100×9500.00×2.92×105) = 0.676 mm;
面板的最大容许挠度值:[ω] = l/250 =400.000/250 = 1.600mm; 面板的最大挠度计算值 ω =0.676mm 小于 面板的最大容许挠度值 [ω]=1.600mm,满足要求!
四、梁侧模板内外楞的计算 1.内楞计算
内楞(木或钢)直接承受模板传递的荷载,按照均布荷载作用下的三跨连续梁计算。
本工程中,龙骨采用木楞,截面宽度50mm,截面高度100mm,截面惯性矩I和截面抵抗矩W分别为:
W = 50×100×100/6 = 83.33cm3; I = 50×100×100×100/12 = 416.67cm4;
内楞计算简图 (1).内楞强度验算
16
梁模板专项施工方案
强度验算计算公式如下:
其中, σ -- 内楞弯曲应力计算值(N/mm2); M -- 内楞的最大弯距(N.mm); W -- 内楞的净截面抵抗矩; [f] -- 内楞的强度设计值(N/mm2)。 按以下公式计算内楞跨中弯矩:
其中,作用在内楞的荷载,q = (1.2×18.000×0.90+1.4×2.000×0.90)×0.400/2=4.39kN/m;
内楞计算跨度(外楞间距): l = 600mm;
内楞的最大弯距: M=0.1×4.39×600.002= 1.58×105N.mm; 经计算得到,内楞的最大受弯应力计算值 σ = 1.58×105/8.33×104 = 1.897 N/mm2;
内楞的抗弯强度设计值: [f] = 17.000N/mm;
内楞最大受弯应力计算值 σ = 1.897 N/mm2 内楞的抗弯强度设计值 小于 [f]=17.000N/mm2,满足要求!
(2).内楞的挠度验算
2
其中 E -- 面板材质的弹性模量: 10000.00N/mm2;
q--作用在模板上的侧压力线荷载标准值: q =18.00×0.40/2= 3.60 N/mm;
l--计算跨度(外楞间距):l = 600.00mm; I--面板的截面惯性矩:E = 4.17×106N/mm2; 内楞的最大挠度计算值: ω =
0.677×3.60×600.004/(100×10000.00×4.17×106) = 0.076 mm;
内楞的最大容许挠度值: [ω] = 2.400mm;
17
梁模板专项施工方案
内楞的最大挠度计算值 ω=0.076mm 小于 内楞的最大容许挠度值 [ω]=2.400mm,满足要求!
2.外楞计算
外楞(木或钢)承受内楞传递的荷载,按照集中荷载作用下的三跨连续梁计算。
本工程中,外龙骨采用钢楞,截面惯性矩I和截面抵抗矩W分别为: 截面类型为圆钢管48×3.5; 外钢楞截面抵抗矩 W = 5.08cm3; 外钢楞截面惯性矩 I = 12.19cm4;
外楞计算简图
(1).外楞抗弯强度验算
其中 σ -- 外楞受弯应力计算值(N/mm2) M -- 外楞的最大弯距(N.mm); W -- 外楞的净截面抵抗矩; [f] --外楞的强度设计值(N/mm2)。 最大弯矩M按下式计算:
其中,作用在外楞的荷载: P = (1.2×18.00×0.90+1.4×2.00×0.90)×0.60×0.40/2=2.64kN;
外楞计算跨度(对拉螺栓竖向间距): l = 400mm;
外楞的最大弯距:M = 0.175×2635.200×400.000 = 1.84×105N.mm
18
梁模板专项施工方案
经计算得到,外楞的受弯应力计算值: σ = 1.84×105/5.08×103 = 36.312 N/mm2;
外楞的抗弯强度设计值: [f] = 205.000N/mm2;
外楞的受弯应力计算值 σ =36.312N/mm2 小于 外楞的抗弯强度设计值 [f]=205.000N/mm2,满足要求!
(2).外楞的挠度验算
其中 E -- 外楞的弹性模量,其值为 210000.00N/mm2;
p--作用在模板上的侧压力线荷载标准值: p =18.00×0.60×0.40/2= 2.16 KN;
l--计算跨度(拉螺栓间距):l = 400.00mm; I--面板的截面惯性矩:I = 1.22×105mm4; 外楞的最大挠度计算值: ω =
1.146×2.16×103×400.003/(100×210000.00×1.22×105) = 0.062mm;
外楞的最大容许挠度值: [ω] = 1.000mm;
外楞的最大挠度计算值 ω =0.062mm 小于 外楞的最大容许挠度值[ω]=1.000mm,满足要求!
五、穿梁螺栓的计算 验算公式如下:
其中 N -- 穿梁螺栓所受的拉力; A -- 穿梁螺栓有效面积 (mm2);
f -- 穿梁螺栓的抗拉强度设计值,取170.000 N/mm2; 查表得:
穿梁螺栓的直径: 12 mm; 穿梁螺栓有效直径: 9.85 mm; 穿梁螺栓有效面积: A= 76 mm2;
19
梁模板专项施工方案
穿梁螺栓所受的最大拉力: N =18.000×0.600×0.400×2 =8.640 kN。 穿梁螺栓最大容许拉力值: [N] = 170.000×76/1000 = 12.920 kN;
穿梁螺栓所受的最大拉力 N=8.640kN 小于 穿梁螺栓最大容许拉力值 [N]=12.920kN,满足要求!
六、梁底模板计算
面板为受弯结构,需要验算其抗弯强度和挠度。计算的原则是按照模板底支撑的间距和模板面的大小,按支撑在底撑上的简支梁计算。
强度验算要考虑模板结构自重荷载、新浇混凝土自重荷载、钢筋自重荷载和振捣混凝土时产生的荷载;挠度验算只考虑模板结构自重、新浇混凝土自重、钢筋自重荷载。
本算例中,面板的截面惯性矩I和截面抵抗矩W分别为: W = 1000.00×18.00×18.00/6 = 5.40×104mm3;
I = 1000.00×18.00×18.00×18.00/12 = 4.86×105mm4;
1.抗弯强度验算
按以下公式进行面板抗弯强度验算:
其中, σ -- 梁底模板的弯曲应力计算值(N/mm2); M -- 计算的最大弯矩 (kN.m);
l--计算跨度(梁底支撑间距): l =300.00mm; q -- 作用在梁底模板的均布荷载设计值(kN/m); 新浇混凝土及钢筋荷载设计值:
20
梁模板专项施工方案
q1: 1.2×(24.00+1.50)×1.00×0.90×0.90=24.79kN/m; 模板结构自重荷载:
q2:1.2×0.35×1.00×0.90=0.38kN/m; 振捣混凝土时产生的荷载设计值: q3: 1.4×2.00×1.00×0.90=2.52kN/m;
q = q1 + q2 + q3=24.79+0.38+2.52=27.68kN/m; 跨中弯矩计算公式如下:
Mmax = 1/8×27.684×0.3002=0.311kN.m; σ =0.311×106/5.40×104=5.768N/mm2;
梁底模面板计算应力 σ =5.768 N/mm2 小于 梁底模面板的抗压强度设计值 [f]=13.000N/mm2,满足要求!
2.挠度验算
根据《建筑施工计算手册》刚度验算采用标准荷载,同时不考虑振动荷载作用。
最大挠度计算公式如下:
其中,q--作用在模板上的压力线荷载:
q =((24.0+1.50)×0.900+0.35)×1.00= 23.30KN/m; l--计算跨度(梁底支撑间距): l =300.00mm; E--面板的弹性模量: E = 9500.0N/mm; 面板的最大允许挠度值:[ω] =300.00/250 = 1.200mm; 面板的最大挠度计算值: ω =
5×23.300×300.04/(384×9500.0×4.86×105)=0.532mm;
面板的最大挠度计算值: ω =0.532mm 小于 面板的最大允许挠度值:[ω] = 300.0 / 250 = 1.200mm,满足要求!
2
21
梁模板专项施工方案
七、梁底支撑的计算
本工程梁底支撑采用方木。
强度及抗剪验算要考虑模板结构自重荷载、新浇混凝土自重荷载、钢筋自重荷载和振捣混凝土时产生的荷载;挠度验算只考虑模板结构自重、新浇混凝土自重、钢筋自重荷载。
1.荷载的计算:
(1)钢筋混凝土梁自重(kN/m):
q1 = (24.000+1.500)×0.900×0.300=6.885 kN/m; (2)模板的自重线荷载(kN/m):
q2 = 0.350×0.300×(2×0.900+0.300)/ 0.300=0.735 kN/m; (3)活荷载为施工荷载标准值与振倒混凝土时产生的荷载(kN/m): 经计算得到,活荷载标准值 P1= (2.500+2.000)×0.300=1.350 kN/m; 2.方木的支撑力验算
静荷载设计值 q = 1.2×6.885+1.2×0.735=9.144 kN/m; 活荷载设计值 P = 1.4×1.350=1.890 kN/m;
方木计算简图 方木按照三跨连续梁计算。
本算例中,方木的截面惯性矩I和截面抵抗矩W分别为: W=5.000×10.000×10.000/6 = 83.33 cm3;
I=5.000×10.000×10.000×10.000/12 = 416.67 cm4; 方木强度验算:
最大弯矩考虑为静荷载与活荷载的设计值最不利分配的弯矩和,计算公式如下:
22
梁模板专项施工方案
线荷载设计值 q = 9.144+1.890=11.034 kN/m;
最大弯距 M =0.1ql2= 0.1×9.144×1.000×1.000= 0.914 kN.m; 最大应力 σ= M / W = 0.914×106/83333.3 = 10.973 N/mm2; 抗弯强度设计值 [f]=13.000 N/mm2;
方木的最大应力计算值 10.973 N/mm2 小于 方木抗弯强度设计值 13.000 N/mm2,满足要求!
方木抗剪验算:
最大剪力的计算公式如下: 截面抗剪强度必须满足:
其中最大剪力: V = 0.6×9.144×1.000 = 5.486 kN;
方木受剪应力计算值 τ = 3×5486.400/(2×50.000×100.000) = 1.646 N/mm2;
方木抗剪强度设计值 [τ] = 1.700 N/mm2;
方木的受剪应力计算值 1.646 N/mm2 小于 方木抗剪强度设计值 1.700 N/mm2,满足要求!
方木挠度验算:
最大挠度考虑为静荷载与活荷载的计算值最不利分配的挠度和,计算公式如下:
q = 6.885 + 0.735 = 7.620 kN/m;
方木最大挠度计算值 ω= 0.677×7.620×1000.0004
23
梁模板专项施工方案
/(100×10000.000×416.667×104)=1.238mm;
方木的最大允许挠度 [ω]=1.000×1000/250=4.000 mm;
方木的最大挠度计算值 ω= 1.238 mm 小于 方木的最大允许挠度 [ω]=4.000 mm,满足要求!
3.支撑钢管的强度验算 支撑钢管按照简支梁的计算如下 荷载计算公式如下:
(1)钢筋混凝土梁自重(kN/m2):
q1 = (24.000+1.500)×0.900= 22.950 kN/m2; (2)模板的自重(kN/m2): q2 = 0.350 kN/m2;
(3)活荷载为施工荷载标准值与振倒混凝土时产生的荷载(kN/m2): q3= (2.500+2.000)=4.500 kN/m2;
q = 1.2×(22.950 + 0.350 )+ 1.4×4.500 = 34.260 kN/m2; 梁底支撑根数为 n,立杆梁跨度方向间距为a, 梁宽为b,梁高为h,梁底支撑传递给钢管的集中力为P,梁侧模板传给钢管的集中力为N 。
当n=2时:
当n>2时:
24
梁模板专项施工方案
计算简图(kN)
支撑钢管变形图(m.m)
支撑钢管弯矩图(kN.m)
经过连续梁的计算得到:
支座反力 RA = RB=1.018 kN,中间支座最大反力Rmax=8.997;最大弯矩 Mmax=0.420 kN.m; 最大挠度计算值 Vmax=0.100 mm;
支撑钢管的最大应力 σ=0.420×106/5080.0=82.724 N/mm2;支撑钢管的抗压设计强度 [f]=205.0 N/mm2;
25
梁模板专项施工方案
支撑钢管的最大应力计算值 82.724 N/mm2 小于 支撑钢管的抗压设计强度 205.0 N/mm2,满足要求!
八、梁底纵向钢管计算
纵向钢管只起构造作用,通过扣件连接到立杆。
九、扣件抗滑移的计算:
按照《建筑施工扣件式钢管脚手架安全技术规范培训讲座》刘群主编,P96页,双扣件承载力设计值取16.00kN,按照扣件抗滑承载力系数0.80,该工程实际的旋转双扣件承载力取值为12.80kN 。
纵向或横向水平杆与立杆连接时,扣件的抗滑承载力按照下式计算(规范5.2.5):
R ≤ Rc
其中 Rc -- 扣件抗滑承载力设计值,取12.80 kN;
R -- 纵向或横向水平杆传给立杆的竖向作用力设计值; 计算中R取最大支座反力,根据前面计算结果得到 R=8.997 kN;
R < 12.80 kN,所以双扣件抗滑承载力的设计计算满足要求!
十、立杆的稳定性计算:
立杆的稳定性计算公式
26
梁模板专项施工方案
1.梁两侧立杆稳定性验算:
其中 N -- 立杆的轴心压力设计值,它包括: 横杆的最大支座反力: N1 =1.018 kN ;
脚手架钢管的自重: N2 = 1.2×0.129×3.600=0.558 kN; 楼板的混凝土模板的自重: N3=1.2×(1.00/2+(0.80-0.30)/2)×1.00×0.35=0.315 kN;
楼板钢筋混凝土自重荷载:
N4=1.2×(1.00/2+(0.80-0.30)/2)×1.00×0.120×(1.50+24.00)=2.754 kN;
N =1.018+0.558+0.315+2.754=4.645 kN;
υ-- 轴心受压立杆的稳定系数,由长细比 lo/i 查表得到; i -- 计算立杆的截面回转半径 (cm):i = 1.58; A -- 立杆净截面面积 (cm2): A = 4.89; W -- 立杆净截面抵抗矩(cm3):W = 5.08; σ -- 钢管立杆轴心受压应力计算值 ( N/mm2);
[f] -- 钢管立杆抗压强度设计值:[f] =205.00 N/mm2; lo -- 计算长度 (m);
如果完全参照《扣件式规范》不考虑高支撑架,按下式计算
lo = k1uh (1)
k1 -- 计算长度附加系数,取值为:1.155 ;
u -- 计算长度系数,参照《扣件式规范》表5.3.3,u =1.700;上式的计算结果:
立杆计算长度 Lo = k1uh = 1.155×1.700×1.500 = 2.945 m; Lo/i = 2945.250 / 15.800 = 186.000 ;
由长细比 lo/i 的结果查表得到轴心受压立杆的稳定系数υ= 0.207 ;钢管立杆受压应力计算值 ;σ=4644.986/(0.207×489.000) = 45.889
27
梁模板专项施工方案
N/mm2;
钢管立杆稳定性计算 σ = 45.889 N/mm2 小于 钢管立杆抗压强度的设计值 [f] = 205.00 N/mm2,满足要求!
2.梁底受力最大的支撑立杆稳定性验算: 其中 N -- 立杆的轴心压力设计值,它包括: 梁底支撑最大支座反力: N1 =8.997 kN ;
脚手架钢管的自重: N2 = 1.2×0.129×(3.600-0.900)=0.558 kN; N =8.997+0.558=9.416 kN;
υ-- 轴心受压立杆的稳定系数,由长细比 lo/i 查表得到; i -- 计算立杆的截面回转半径 (cm):i = 1.58; A -- 立杆净截面面积 (cm2): A = 4.89; W -- 立杆净截面抵抗矩(cm3):W = 5.08; σ -- 钢管立杆轴心受压应力计算值 ( N/mm2);
[f] -- 钢管立杆抗压强度设计值:[f] =205.00 N/mm2; lo -- 计算长度 (m);
如果完全参照《扣件式规范》不考虑高支撑架,按下式计算 lo = k1uh (1) k1 -- 计算长度附加系数,取值为:1.155 ;
u -- 计算长度系数,参照《扣件式规范》表5.3.3,u =1.700; 上式的计算结果:
立杆计算长度 Lo = k1uh = 1.155×1.700×1.500 = 2.945 m; Lo/i = 2945.250 / 15.800 = 186.000 ;
由长细比 lo/i 的结果查表得到轴心受压立杆的稳定系数υ= 0.207 ; 钢管立杆受压应力计算值 ;σ=9415.735/(0.207×489.000) = 93.020 N/mm2;
钢管立杆稳定性计算 σ = 93.020 N/mm2 小于 钢管立杆抗压强度的设计值 [f] = 205.00 N/mm2,满足要求!
28
正在阅读:
梁板模板专项施工方案(毕业设计也可用)05-24
5古诗三首03-15
金相检验二级人员考核复习题一.是非题1明场照明时应用环形光栏06-05
4S店管理制度09-12
优秀少先队活动课案例02-20
2012计算机试卷及答案03-15
陈春花管理论述读后感04-19
2022党员个人工作总结【优秀5篇】03-22
- 多层物业服务方案
- (审判实务)习惯法与少数民族地区民间纠纷解决问题(孙 潋)
- 人教版新课标六年级下册语文全册教案
- 词语打卡
- photoshop实习报告
- 钢结构设计原理综合测试2
- 2014年期末练习题
- 高中数学中的逆向思维解题方法探讨
- 名师原创 全国通用2014-2015学年高二寒假作业 政治(一)Word版
- 北航《建筑结构检测鉴定与加固》在线作业三
- XX县卫生监督所工程建设项目可行性研究报告
- 小学四年级观察作文经典评语
- 浅谈110KV变电站电气一次设计-程泉焱(1)
- 安全员考试题库
- 国家电网公司变电运维管理规定(试行)
- 义务教育课程标准稿征求意见提纲
- 教学秘书面试技巧
- 钢结构工程施工组织设计
- 水利工程概论论文
- 09届九年级数学第四次模拟试卷
- 毕业设计
- 专项
- 可用
- 模板
- 施工
- 方案
- 梁板
- 浅谈工程造价管理-题目:我国工程造价管理现存的问题 - 图文
- 2010年专转本英语试卷
- 施工组织设计
- 计算机组成习题5,6,8,9章答案
- 路面结构设计示例
- 毕业设计文本格式 - 图文
- 音乐美术室等功能管理员岗位职责、制度
- 监理规划
- C语言学习教程
- 2015年全国注册监理工程师延续注册-系统考试试题2
- 央企班组长岗位管理能力资格认证六期在线测试
- 09行政管理1班团支部“活力在基层,成才在莞工”主题团日活动
- 航海英语考试大纲
- 水性油墨及相关专利最新2013
- Res - 2009春学期C语言上机练习参考答案汇总
- 单元评价检测(二)(第二单元 生物体的结构层次)
- 动态跌落补偿的三相静态串联电压稳压器控制算法
- 砌筑工试卷正文
- 乡卫生院党务政务公开内容目录
- 嘉兴南湖导游词