石材幕墙工程监理实施细则

更新时间:2024-07-11 14:30:01 阅读量: 综合文库 文档下载

说明:文章内容仅供预览,部分内容可能不全。下载后的文档,内容与下面显示的完全一致。下载之前请确认下面内容是否您想要的,是否完整无缺。

监理实施细则

(石材幕墙工程)

编制人: 审核人:

编制单位:奉化市凯远工程咨询有限公司 编制时间:2010年5月20日

目 录

一、工程概况 ················································································································ 2 二、监理细则依据 ········································································································ 2 三、幕墙工程施工质量保证条件 ················································································ 2 四、幕墙工程监理程序 ································································································ 3 五、幕墙材料 ················································································································ 4

1. 2. 3. 4.

钢材 ·············································································································· 4 石材 ·············································································································· 4 建筑密封材料 ······························································································ 5 其他材料 ······································································································ 7

六、幕墙设计和施工阶段监理要点 ············································································ 7 七、幕墙工程的制作与安装 ························································································ 8

1. 2. 3. 4. 5.

“施工组织设计”的审查要点 ·································································· 8 审查、确认进场材料 ·················································································· 8 幕墙材料制作加工 ······················································································ 9 幕墙工程的安装施工 ················································································ 11 幕墙的性能试验 ························································································ 12

八、幕墙工程验收 ······································································································ 13

1. 2.

工程现场验收 ···························································································· 13 工程提交资料验收 ···················································································· 15

一、工程概况

本工程位于 。总建筑面积172324.64m2,由 组成。其中 。均为钢筋混凝土剪力墙结构。外墙装饰大部分采用外挂石材幕墙。根据本工程特点外立面设计装饰效果要求较复杂,施工有一定难度,所以幕墙子分部工程由 幕墙有限公司分包。计划工期 天。

二、监理细则依据

本细则根据以下有关规范、标准制定:

1、 建筑装饰装修工程质量验收规范 (GB50210—2001) 2、 金属与石材幕墙工程技术规范 (JGJ133—2001) 3、 建筑用硅酮结构密封胶 (GB16776) 4、 建筑幕墙物理性能分级 (GB/T15225) 5、 建筑幕墙风压变形检测方法 (GB/T15227) 6、 建筑幕墙雨水渗漏性能检测方法 (GB/T15228) 7、 建筑幕墙空气渗透性能检测方法 (GB/T15226) 8、 铝合金建筑型钢 (GB/T 5237.2—5237.5) 9、 天然石材产品放射性防护分类标准 10、 其他有关国家标准。

三、幕墙工程施工质量保证条件

1、幕墙设计必须由相应资质的设计单位承担。设计应严格执行国家相关规范。 2、幕墙工程所用材料:钢材及不锈钢、石材、粘结密封胶等均须有出厂合格证,并符合国家和行业标准。

3、加工制作所使用的材料和配件、加工质量等均应符合国家和行业标准、技术规程。

4、幕墙施工必须由相应资质的施工单位进行施工安装,安装工艺及质量应符合国家现行标准。幕墙工程的设计、材料、制作和安装施工及验收应符合《金属与石材幕墙工程技术规范》合同签订;图纸会审;质量保证体系和控制体系落实;审阅施工进度计划和施工方案;新工艺、新材料、新技术进行格;第一次工地会议召开 试验合格;工地环境、开工条件检查合JGJ133—2001、《建筑装饰装修工程质量验收规范》GB50210—2001的要求。四、幕墙 工程监理程序

开工前准备工作 施工单位填报 《开工报告》 整改 监理处审核 不同意 工序返工整改处、理原材料限期退场前期开工条件 同意 材料报验、 下道工序 工序施工、工序报验 施工单位填报《材料报验单》《工 不合格 序报验单》附,材料出厂合格证、铝型材、石材、金属材料试验报告、结构胶与接触材料相容性、粘结力试验报告、夹胶玻璃的试验报告等,工序自检记录,检查 合格 试验结果等 监理工程师签认 《材料报验单》 《工序报验单》 施工单位提交 《竣工报告》 竣工图、 技术管理等资料

工程质量初验

工程交工验收 五、幕墙材料

1. 钢材

①幕墙工程所使用的不锈钢宜采用奥氏体不锈钢材,型材材质应符合相应的现行国家标准:不锈钢棒(GB1200)、不锈钢冷轧钢板(GB3280)、不锈钢热轧钢板(GB4237)。

②普通钢筋HPB235是应用最多的钢材,使用时应对其试验报告中的化学成份, 力学性能等重点审查。

③幕墙工程中使用的钢材、五金件应有出厂合格证、试验报告,热镀锌涂层必须合格。

④钢结构幕墙高度超过40M时,钢构件宜采用高耐候结构钢,并应在其表面涂刷防腐涂料。

⑤钢构件采用冷弯薄壁型钢时,其壁厚不得小于3.5mm,强度应符合设计计算要求,表面应进行处理。 2. 石材

① 幕墙石材宜选用火成岩。

② 石材的弯曲强度不应小于8.0MPa,吸水率应小于0.8%。

③ 石材幕墙的铝合金挂件厚度不应小于4.0mm,不锈钢挂件厚度不应小于3.0mm。

④ 火烧石板与抛光石板若要求同强度时,火烧石板的厚度应比抛光石板厚3mm。

⑤ 石材的强度,弯曲强度、耐磨性、耐酸性、体积密度、吸水率等主要性能试

2石板的长度、宽度、厚度、直角、异型角、半圆弧形状、异型材及花纹图案造型、石的外形尺寸均应符合设计要求;

2石板外表面的色泽应符合设计要求,花纹图案应按样板检查。石板四周围不得有明显的色差;

2火烧石应按样板检查火烧后的均匀程序,火烧石不得有暗 裂、崩裂情况; 2石板的编号应同设计一致,不得因加工造成混乱;

2石板应结合其组合形式,并应确定工程中使用的基本形式后进行加工; 2石板加工尺寸允许偏差应符合现行行业标准《天然花岗石建筑板材》(JC205)的有关规定中一等品要求。

钢销式安装的石板加工应符合下列规定:

2钢销的孔位应根据石板的大小而定。孔位距离边端不得小于石板厚度的3倍,也不得大于180㎜;钢销间距不宜大于600㎜;边长不大于1.0m时每边应设两个钢销,边长大于1.0m时应采用复合连接;

2石板的钢销孔深度宜为22~33㎜,孔的直径宜为7~8㎜,钢销直径宜为5~6㎜,钢销长度宜为20~30㎜。

2石板的钢销孔处不得有损坏或崩裂现象,孔径内应光滑、洁净。 通槽式安装的石板加工应符合下列规定:

2石板的通槽宽度宜为6㎜或7㎜,不锈钢支撑板厚度不宜小于3.0㎜,铝合金支撑板厚度不宜小于4.0㎜;

2石板开槽后不得有损坏或崩裂现象,槽口应打磨成45°倒角;槽内应光滑、洁净。

短槽式安装的石板加工应符合下列规定:

2每块石板上下边应各开两个短平槽,短平槽长度不应小于100㎜,在有效长度内槽深度不宜小于15㎜;开槽宽度宜为6㎜或7㎜;不锈钢支撑板厚度不宜小于3.0㎜,铝合金支撑板厚度不宜小于4.0㎜。弧形槽的有效长度不应小于80㎜。

2 两短槽边距离石板两端部的距离不应小于石板厚度的3倍且不应小于85㎜,也不应大于180㎜。

2石板开槽后不得有损坏或崩裂现象,槽口应打磨成45°倒角,槽内应光滑、

洁净。

2当石板的转角支撑采用不锈钢支撑件组装时,不锈钢支撑件的厚度不应小于3㎜;

2当石板的转角支撑采用铝合金型材专用件组装时,铝合金型材壁厚不应小于4.5㎜,连接部位的壁厚不应小于5㎜。 ⑶石材构件检验

2石材幕墙构件应按同一种类构件的5%进行抽样检查,且每种构件不得少于5件。当有一个构件抽检不符合上述规定时,应加倍抽样复验,全部合格后方可出厂。

2构件出厂时,应附有构件合格证书。

2幕墙构件若在厂内加工,且监理合同有要求时,专业监理工程师应驻厂监理或专人不定期进厂监理。

4. 幕墙工程的安装施工 ①可进行幕墙施工的先决条件: ? 主体结构已达到验收规范的要求。

? 现场已清理,土建脚手架已拆除。污染幕墙施工的工序已完,若未完也已采取保护措施,达到幕墙施工要求。 ? 有加工、堆放场地。

? 1∶1实际采用的幕墙样板已认可。 ? 构件、材料、零附件已认可验收。

? 主体上的予埋件应在主体施工时按设计要求埋设。预埋件应牢固,位置准确,预埋件的位置误差应按设计要求进行复查。若标高偏差>10㎜,位置差>20㎜,则应采取补救措施。

·若有变更,是否已经设计院、业主、监理认可,并有相应的技术文件。 ? 幕墙安装的基准线已设定,认可。

? 关键工序的技术人员及技工的岗位合格证书已具备。

②石材幕墙安装质量见下表 项目 幕墙高度(H)(m) H≤30 竖缝及墙面垂直度 60≤H>30 90≤H>60 H>90 幕墙平面度 竖缝直线度 横缝直线度 缝宽度 两相邻面板之间接缝高低差 允许偏差 ≤10 ≤15 ≤20 ≤25 ≤2.5 ≤2.5 ≤2.5 ±2 ≤1.0 激光经纬仪或经纬仪 检查方法 2m靠尺、钢板尺 2m靠尺、钢板尺 2m靠尺、钢板尺 卡尺 深度尺 ③监理着重检查项目

作 业 检 查 项 目 说 明 目测、尺量 依设计检查 依设计检查 按图纸、样板现场实物构件检查 按图纸、样板 按图纸、样板 目测 设定检查项目 ?检查工具精度 ?基准线位置 ?吊锺 予埋件、锚固件 ?位置 ?施工精度 ?固定状态 ?变形 ?防锈 牛腿、连接件 ?安装部位 ?加工精度 ?固定状态 ?防锈处理 构件安装 五金件安装 密封胶嵌缝 清洁 ?安装部位 ?加工精度 ?螺栓、铆钉安装 ?外观?功能:雨水泄水通路,密封状态 ?防锈处理 ?安装部位 ?加工精度 ?固定状态 ?外观 ?注胶有无遗漏 ?施工状态 ?外观、色泽 ?胶缝品质、形状、气泡 ?污染 ?应清洗部分有无遗漏 ?有无残留物 ④幕墙隐蔽项目验收应包括: 2预埋件(或后置埋件)

? 幕墙构件与主体结构的连接节点安装 ? 幕墙与建筑四周间隙处理 ? 幕墙防火构造

? 伸缩缝、沉降缝及墙面转角处的构造节点 ? 防雷装置

5. 幕墙的性能试验

? 一般幕墙面积超过10000m2均应进行物理性能试验。性能试验包括七项内容:

雨水渗漏试验(GB/T15228—94)、空气渗透试验(GB/T15226—94)、风压变形试验(GB/T15227—94)、平面内变形性能试验,这四项内容为基本实验项目,必须进行。保温性能试验(GB8484—87)、隔音性能试验(GB8485—87)、耐撞击性能试验这三项内容是在必要时或应业主要求时进行的试验。 ? 试验试件由承包商制作,监理按规定监督实施。 ? 性能试验应在具备资格的试验单位进行。

? 承包商在委托试验之前,应编制“试验计划”,计划中应明确规定试验内容、方法、程序、进度、合格标准等,并应得到业主、监理的认可。

? 进行试验时,三方应在场,若不能在场,试验方应保证出具具有法律效力的报告,报告必须公正、客观、真实。

? 物理性能试验报告是竣工资料的重要组成部分。

八、幕墙工程验收

幕墙工程涉及安全的项目,必须单独进行专项检查验收。 1、 现场验收

① 达到验收条件后,监理应组织设计、业主、施工等单位进行初验,列出整改清单,监督施工单位逐条消项。 ② 参与幕墙工程的竣工验收。

③ 验收应在施工完毕、脚手架拆除、剥去全部保护材料、进行清洗整体、幕墙外露后进行。

④ 幕墙的所有立面均应进行验收,可依一个大面作为基本单元进行验收。 ⑤抽查频率:每500-1000平方米为一个检验批,每个检验批每100平方米至少抽查一处,每处不少于10平方米。 石材幕墙工程验收应按如下项目进行验收: 主控项目:

(1)石材幕墙工程所用材料的品种、规格、性能和等级,应符合设计要求及国家现行产品标准和工程技术规范的规定。石材弯曲强度不应小于8.0MPa;吸水

率应小于0.8%。石材幕墙的铝合金挂件厚度不应小于4.0mm,不锈钢挂件厚度不应小于3.0mm。检查产品合格证书、性能检测报告、材料进场验收记录和复验报告。

(2)石材幕墙的造型、立面分格、颜色、光泽、花纹和图案应符合设计要求。 (3)石材孔、槽的数量、深度、位置、尺寸应符合设计要求。

(4)石材幕墙主体结构上的预埋件和后置埋件的位置、数量及后置埋件的拉拔力必须符合设计要求,检查拉拔力检测报告和隐蔽工程验收记录。

(5)石材幕墙的金属框架立柱与主体结构预埋件的连接、立柱与横梁的连接、连接件与金属框架的连接、连接件与石材面板的连接必须符合设计要求,安装必须牢固。

(6)金属框架和连接件的防腐处理应符合设计要求。

(7)石材幕墙的防雷装置必须与主体结构防雷装置可靠连接。

(8)石材幕墙的防火、保温、防潮材料的设置应符合设计要求,填充应密实、均匀、厚度一致。

(9)各种结构变形缝、墙角的连接节点应符合设计要求和技术标准的规定。 (10)石材表面和板缝的处理应符合设计要求。

(11)石材幕墙的板缝注胶应饱满、密实、连续、均匀、无气泡,板缝宽度和厚度应符合设计要求和技术标准的规定。

(12)石材幕墙应无渗漏。查验在易渗漏部位的淋水试验。 一般项目:

(1)石材幕墙表面应平整、洁净,无污染、缺损和裂痕。颜色和花纹应协调一致,无明显色差, 无明显修痕。

(2)石材幕墙的压条应平直、洁净、接口严密、安装牢固。

(3)石材接缝应横平竖直、宽窄均匀;阴阳角石板压向应正确,板边合缝应顺直;凸凹线出墙厚度应一致,上下口应平直;石材面板上洞口、槽边应套割吻合,边缘应整齐。

(4)石材幕墙的密封胶缝应横平竖直、深浅一致、宽窄均匀、光滑顺直。 (5)石材幕墙上的滴水线、流水坡向应正确、顺直。

(6)每平方米石材的表面质量和检验方法应符合下表的规定。

项次 1 2 3 项目 裂痕、明显划伤和长度>100㎜的轻微划伤 长度≤100㎜的轻微划伤 擦伤总面积 质量要求 不允许 ≤8条 2≤500㎜ 检验方法 观 察 用钢尺检查 用钢尺检查

(7)石材幕墙安装的允许偏差和检验方法应符合下表的规定。

允许偏差 (㎜) 项次 项 目 检验方法 光面 麻面 幕墙高度≤30m 10 30m<幕墙高度≤60m 15 1 幕墙垂直度 用经纬仪检查 60m<幕墙高度≤90m 20 幕墙高度>90m 25 2 幕墙水平度 用水平仪检查 3 3 板材立面垂直度 3 用水平仪检查 用1m水平尺 4 板材上沿水平度 2 和钢直尺检查 5 相邻板材板角错位 1 用钢直尺检查 用垂直检测尺6 幕墙表面平整度 2 3 检查 用直角检测尺7 阳角方正 2 4 检查 拉5m线,不足5m8 接缝直线度 3 4 拉通线,用钢直尺检查 用钢直尺和塞尺检9 接缝高低差 1 — 查 10 接缝高度 1 2 用钢直尺检查 2、工程提交资料验收

1、项目监理处应对以下资料进行审查: ① 设计竣工图。

② 结构计算书、设计文件、设计修改、材料代用文件。 ③ 各种材料、构件出厂合格证及各种试验报告(如前述) ④ 施工自检记录。 ⑤ 隐蔽验收记录。

⑥ 各种进口材料的商检报告。

⑦ 正常情况下物理耐用年限质量保证书。

⑧ 各种施工安装质量监测文件:照片、录像带、洽商记录、 施工安装测评记录。 ⑨ 幕墙物理性能试验报告。

2、幕墙使用期间每年应进行维护清洗,5年进行全面检查一次。

3、幕墙工程竣工资料单独整理,最终并入单位工程“建筑装饰装修工程分部”之中。