基础人防工程施工方案
更新时间:2023-11-14 08:31:01 阅读量: 教育文库 文档下载
江苏省建工集团有限公司 地下人防工程施工方案
目 录
1.编制依据 ··············································································································· 2 2.工程概况 ··············································································································· 2 3.施工准备 ··············································································································· 2 3.1施工现场准备 ···································································································· 3 3.2施工流水段划分原则 ··························································································· 4 3.3施工流程 ·········································································································· 4 4.技术准备 ··············································································································· 4 5.材料准备 ··············································································································· 4 5.1钢筋原材 ·········································································································· 4 5.2模板架料 ·········································································································· 6 5.3混凝土 ············································································································· 6 6.机具准备和劳动力安排 ····························································································· 7 6.1机具准备(人防部分) ························································································ 7 6.2劳动力安排(人防部分) ····················································································· 8 7.主要的施工方法和技术措施 ······················································································· 8 7.1钢筋工程 ·········································································································· 8 7.2模板工程 ········································································································· 25 7.3混凝土工程 ······································································································ 36 8.质量保证措施 ········································································································ 44 8.1钢筋工程质量控制 ····························································································· 44 8.2模板工程质量控制 ····························································································· 45 8.3混凝土施工质量控制措施 ···················································································· 46 9.成品保护措施 ········································································································ 47 10.安全生产与文明施工措施 ························································································ 48
- 1 -
1.编制依据
施工合同文本
《混凝土结构施工图平面整体表示方法制图规则和构造详图筏形基础》11G101-3
《混凝土结构施工图平面整体表示方法制图规则和构造详图》11G101-1 《建筑设计防火规范》 GB50016-2006 《高层民用建筑设计防火规范》 GB50016-2014 《汽车库、修车库、停车场设计防火规范》 GB50067-97 《建筑内部装修设计防火规范》 GB50222-2015 《建筑灭火器配置设计规范》 GB50140-2005 《人民防空地下室设计规范》 GB50038-2005 《人民防空工程设计防火规范》 GB50098-2009 《建筑地基基础工程施工质量验收规范》 GB50202-2011 《混凝土结构工程施工及验收规范》 GB50204-2011 《建筑工程抗震设防分类标准》 GB50223-2008 《普通混凝土配合比设计规程》 JGJ55-2000 《钢筋机械连接通用技术规程》 JGJ107-2011 《地下工程防水设计规范》 GB50108-2008 《防空地下室结构设计》 GB50038-2005 《防空地下室建筑设计》 FJ01~03 《人民防空地下室设计规范》 GB50038-2005 《德尔丝绸广场三期工程设计图纸》
2.工程概况
工程名称:德尔国际丝绸广场三期工程 工程地点:苏州市盛泽镇西环路与市场路交接 建设单位:德尔集团苏州博士国际地产有限公司 主体设计单位:苏州土木文化中城建筑设计有限公司 勘察单位:苏州市市政工程设计院有限责任公司 监理单位:苏州市长诚工程监理咨询有限公司 施工单位:江苏省建工集团有限公司
- 2 -
2.1、德尔国际丝绸广场三期工程,位于苏州市盛泽镇,西环路与市场路交接。场地平整,地理环境优越,德尔丝绸广场三期工程总建筑面积36274.63㎡,地下建筑面积为6924.98m2,18#楼底下2层,地上18层,建筑总高度为106米,14#楼地下一层,地上14层,建筑总高度为84米,15#、16#、17#楼为地下一层,地上2层,建筑总高度为12米,±0.00以下局部人防地下室约4000m2,室内地坪±0.00相当于黄海高程0.075m。。框剪结构形式,竹节桩+整体筏板基础,主楼与地下车库底板交接处留800mm宽后浇带。
2.2、本工程基础普通部位掺量为砼材料6—8%的SY-K膨胀纤维防水剂(p6),加强带部位掺量为砼材料10-12%的SY-K膨胀纤维防水剂(p6)。
基础底板砼标号为15#,16#,17#为C30P6自防水砼、14#为C35P6自防水砼、18#为C35P6自防水砼,侧墙砼标号为15#,16#,17#为C30P6自防水砼、14#为C40P6自防水砼、18#为C45P6自防水砼、顶板砼标号为15#,16#,17#为C30P6自防水砼、14#为C35P6自防水砼、18#为C35P6自防水砼,侧墙砼标号为15#,16#,17#为C30P6自防水砼、14#为C40P6自防水砼、18#为C45P6自防水砼。
2.3、地下室防水等级为二级,地下室顶板防水等级为一级,室外顶板防水等级一级,变配电所防水等级一级。
2.4、根据地质勘查报告得德尔三期工程地下水位情况如下表
初见水位 表2.3.2.1 数据个数 13 初见水位埋深(m) 最小值 0.10 最大值 0.60 稳定水位埋深(m) 最小值 0.20 最大值 1.10 平均值 0.48 最小值 -1.08 平均值 0.28 最小值 -0.88 初见水位标高(m) 最大值 -0.25 稳定水位标高(m) 最大值 -0.61 平均值 -0.89 平均值 -0.70 稳定水位 表2.3.2.2 数据个数 13 3.施工准备
3.1施工现场准备
根据现场的实际情况,便于材料的加工和运输,在施工现场内部建钢筋加工区和钢筋堆放场地及模板加工场。
- 3 -
3.2施工流水段划分原则
地库底板及筏板流水段划分时根据图纸后浇带进行划分,以减少板施工缝隙,规避防水风险为原则。
以工程量大致相同、平衡人、机、料的投入量和配置,合理安排施工场地为原则。 3.3施工流程
基坑降排水→ 土方开挖、支撑施工→ 截桩、凿桩→垫层砼浇注→桩头防水处理、底板防水卷材施工→底板钢筋放线→底板钢筋绑扎→底板砼浇注→底板砼养护→测量放线→地下墙、柱、梁、板钢筋绑扎→地下墙、柱、梁、板支模→地下墙、柱、梁、板砼浇注→地下墙、柱、梁、板砼养护
4.技术准备
4.1组织施工技术人员熟悉图纸,了解设计意图。
4.2施工方案及交底的编制。项目技术部编制详细的施工方案并进行方案交底,明确施工中应注意的事项。
4.3施工技术交底。责任工程师对操作班组进行交底,明确操作中的技术要求和质量控制标准和措钢筋进场计划单 结构分包 责任工程师 审核 技术部责任师 材料员 材料工程师 施。 程部括书理层措施4.4劳务人员培训。项目工除对劳务队伍进行交底(包面和口头)外,分包队伍管应向其操作层进行方案、交底(包括书面和口关责任工程师和质量总监参加。
物资公司 头),并请有5.材料准备
5.1钢筋原材 5.1.1钢筋原材质量控制图
收集资料验收批量 填写试验委托单 项目物资部 项目物资部 质量员 材料员 试验员按规定现场随机取样、复试 填写材料报验单 甲方和监理 - 4 - 报监理公司投入使用 各种资料技术部存档
5.1.2钢筋的检验要求
(1)材质要求
根据施工进度计划,钢筋进场按钢筋备料单分批进场,同时钢筋进场时必须具有出厂质量证明书或试验报告单。每批钢筋进场必须按规格附带该批钢筋的试验报告单,且试验报告单上的代表数量不应小于所进场的数量,试验报告单必须是原件,不得使用复印件。
(2)复试要求
钢筋出厂时,在每捆(盘)上都挂有标牌,印有厂标、钢号、炉(批)号、直径等标号。钢筋进入施工现场时应分批进行验收。
(3)外观检查
钢筋表面不得有裂缝、结疤、折叠及锈蚀。 (4)力学性能试验
同一种规格每批重量不大于60t,在每批钢筋中的任意两根钢筋上各取一套,每套试样从每根钢筋端部截去50cm,然后再截取两根,一根做拉伸试验(包括屈服点、抗拉强度和延伸率),另一根做冷弯试验(监理到场见证取样)。试验时,如有一个试验结果不符合规范所规定的数值时,则应另取双倍的试样,对不合格的项目做第二次试验,如仍有一根试样不合格,则该批钢筋为不合格品不予验收。
5.1.3钢筋堆放要求
堆放钢筋的场地要坚实平整,在场地基层上浇筑100厚的C20混凝土,并从中
- 5 -
间向两边设排水坡度,避免基层出现积水。堆放时钢筋下面要垫垫木,垫木厚度不应小于20cm,间距1500mm,以防止钢筋锈蚀和污染。
(1)原材堆放
钢筋原材进入现场后,按照现场施工平面布置的位置分规格进行堆放,不能为了卸料方便而随意乱放。
(2)成品钢筋堆放
将加工成型的钢筋分层、分段、分部和构件名称按号码顺序堆放,同一部位钢筋或同一构件要堆放在一起,保证施工方便。
(3)钢筋的标识
钢筋原材及成品钢筋堆放场地必须设有明显标识牌,钢筋原材标识牌上应注明钢筋进场时间、受检状态、钢筋规格、长度、产地等;成品钢筋标识牌上应注明使用部位、钢筋规格、钢筋简图、加工制作人及受检状态。 5.2模板架料
本工程的模板架料统一进行租赁或采购,模板支撑体系详见《地下结构模板施工方案》。 5.3混凝土
5.3.1混凝土配合比及材料要求
(1)搅拌站按照设计要求的混凝土强度等级对其所选用的水泥品种、砂石级配、含泥量和外加剂等进行混凝土试配,得出优化配合比,并把试配结果及相关材质报告报送到项目经理部,由技术负责人审核,报监理审查认可。
(2)在混凝土中掺加的混凝土外加剂的性能或种类,必须符合设计要求及规定批准使用的品种和生产厂家,并报监理认可后方准使用。
1)普通混凝土:
选用普通硅酸盐水泥,低水化热。选用中砂,含泥量应在2%之内,泥块含量不大于1%。洗净的卵碎石,最大粒径25mm,含泥量不大于1%,泥块含量不大于0.5%。搅拌用水要求清洁、可饮用、无色无味。减水缓凝剂:缓凝6小时以上(根据天气情况及施工可适当调整)。为了有效预防混凝土碱骨料反应发生所造成的危害,对于掺入混凝土的外加剂的碱含量(Na2O+0.658K2O)加以规定,由化学外加剂带入混凝土工程中的碱含量防水类应≤0.7kg,非防水类≤1.0kg。混凝土中最大碱含量
- 6 -
3.0kg/m3。
2)抗渗混凝土:
粗骨料宜采用连续级配,最大粒径不宜大于40mm,含泥量不得大于1.0%,泥块含量不得大于0.5%。细骨料最大粒径不宜大于40mm,含泥量不得大于1.0%,泥块含量不得大于0.5%。每立方米混凝土中的水泥和矿物掺和料总量不宜小于320kg。砂率为35%~45%。需进行抗渗性能试验。 5.3.2砼的供应
本工程混凝土全部采用商品混凝土,选用多家技术实力强、生产能力足、社会信誉好的砼厂家作为本工程的供应商。
混凝土坍落度由搅拌站根据季节、气温、运输路径等条件试配确定,泵送砼坍落度控制在18±2cm;混凝土泵车或塔吊吊斗下灰时,坍落度不大于18cm,水灰比不宜大于0.5,初凝时间控制在7-11小时。对防水砼和普通砼不同强度等级、不同品种的砼同时使用时,应专车专供,并在罐车前挡风玻璃上贴上标识,以防出现差错。
6.机具准备和劳动力安排
6.1机具准备(人防部分) 序号 1 2 3 4 5 6 7 8 9 10 11 机具名称 钢筋切断机 砂轮切割机 钢筋成型机 钢筋调直机 直螺纹套丝机 电焊机 断绑扎丝铡刀 塔吊 布料杆 混凝土地泵 汽车泵 单位 台 台 台 台 套 台 台 台 台 台 台 数量 4 4 8 4 8 12 4 8 2 8 4 用途 钢筋切断 钢筋切割 钢筋成型 钢筋调直 钢筋连接 钢筋连接及机电 断绑扎丝 - 7 -
12 13 14 15 16 17 砼振动棒 圆锯 平压两用刨 手电钻 手提电箱 手电锯 只 台 台 台 台 台 30 4 4 8 8 8 6.2劳动力安排(人防部分)
序号 1 2 3 4 5 6 7 工 种 钢筋工 模板工 测量人员 砼工 力工 瓦工 架子工 数量(人) 400 600 8 80 80 40 40 备注 钢筋绑扎 模板支设 测量 浇注混凝土 搬运 混凝土面抹平收光 外脚手架搭设 7.主要的施工方法和技术措施
7.1钢筋工程 7.1.1钢筋加工 (1)钢筋放样
钢筋加工前,由技术人员依据结构施工图、规范要求、施工方案及有关洽商对各种构件的每种规格钢筋放样并填写《钢筋配料单》。《钢筋配料单》应注明钢筋的规格、形状、长度、数量、应用部位等。《钢筋配料单》经项目专业责任师审核签字认可后,开始加工。
(2)钢筋下料
1)直筋下料长度=构件长度-保护层厚度+弯钩增加长度+接头连接长度-弯钩弯曲调整值。
2)弯起筋下料长度=直段长度+弯起段长度+斜段长度-弯曲调整值+弯钩增加长度+接头连接长度
- 8 -
3)箍筋下料长度=箍筋周长+箍筋调整值+2弯钩长度。 4)钢筋弯钩增加长度。
半圆弯钩增加长度6.25d,直弯钩3.5d,斜弯钩4.9d。箍筋调整值+ 两个弯钩增加长度(mm)。 (3)钢筋弯曲
1)应按:划线→试弯→弯曲成型的顺序进行。钢筋弯曲前,应根据钢筋料牌上注明的尺寸,用石笔将各弯曲点位置画出。划线时应根据不同的弯曲角度扣除弯曲调整值,扣法是从相邻两段长度中各扣除一半。钢筋端部带出圆弯钩时,该段长度划线时增加0.5d,划线工作宜从钢筋中线开始向两边进行。弯曲分部钢筋、箍筋时,应在工作台上按各段尺寸要求钉上若干标志,按标志进行操作,以确保钢筋弯曲形状正确。钢筋成型后,要求其形状正确,平面上没有翘曲不平现象,弯曲点处不得有裂缝。
钢筋的弯钩或弯折向符合下列规定:
○1I级钢筋末端需要作180度弯钩,其圆弧弯曲直径D应小于钢筋直径d的2.5倍,平直部分长度不宜小于钢筋直径d的3倍。
○2II级钢筋末端需作90°或135°弯折时,弯曲直径D不宜小于钢筋直径d的5倍,平直长度部分应按设计要求确定。
○3弯起钢筋中间部位弯折处的弯曲直径d,不应小于钢筋直径d的5倍。
2)箍筋末端应作弯钩,弯钩按照抗震规范规定为135°,即两弯钩相平行,弯
- 9 -
钩平直部分的长度不小于10d,长度误差不超过+10mm,且两个弯钩平直段相互平行。箍筋的弯心应大于受力钢筋直径且不小于箍筋直径的2.5d。
3)钢筋弯曲点不得有裂缝,I级钢筋只能进行一次重新调直和弯曲,其他级别钢筋不宜重新调直和弯曲。
4)钢筋加工施工时应根据钢筋直径、弯钩角度、弧内直径、平直段长度现场划线、并采用不同直径的轴心弯心模具(机械加工)和不同的扳手(手工加工)进行加工质量控制。并采用定型的模具检查箍筋的加工质量。
5)成型钢筋应按指定地点用垫木垫放整齐,防止钢筋变形、锈蚀、油污。 7.1.2钢筋的连接 (1)接头设置原则、
1)钢筋的接头末端至钢筋弯起点的距离不应小于钢筋直径的10倍。 2)当受力钢筋采用直螺纹连接或焊接连接时,设置在同一构件内的接头宜相互错开。在任意接头中心至长度为钢筋直径的35倍且不小于500mm的区段范围内,有接头的受力钢筋截面面积占受力钢筋总截面面积的允许百分率应按以下规定:
a.受拉区不宜大于25%;
b.接头不宜设置在有抗震设防要求的框架梁端、柱端的箍筋加密区;当无法避开时,对等强度高质量机械连接接头,不应大于50%。
c.受压区不受限制。
3)当受力钢筋采用绑扎搭接时,同一构件中相邻纵向受力钢筋的绑扎搭接接头宜相互错开。绑扎搭接接头中钢筋的横向净距不应小于钢筋直径,且不应小于25mm。从任意绑扎接头中心至搭接长度的1.3倍区段范围内,有接头的受力钢筋截面面积占受力钢筋总截面面积的允许百分率应符合以下规定:
- 10 -
a.对梁、板类构件不宜大于25%。 b.对柱类构件,不宜大于50%
c.当工程中确有必要增加接头面积百分率时,对梁类构件不应大于50%;对其他构件,可根据实际情况放宽。
纵向受压钢筋搭接接头面积百分率,不宜大于50%
4)柱纵向钢筋全部采用直螺纹接头,柱筋接头部位宜避开箍筋加密区,钢筋接头位置应错开,同一截面内钢筋接头不宜超过全截面钢筋总根数的50%,接头位置错开35d且≥500㎜。
≥500≥1.2LaE≥≥500≥35d楼板顶面基础顶面一级抗震等级剪力墙竖向分布钢筋直径<18时钢筋搭接构造楼板顶面基础顶面一级抗震等级剪力墙竖向分布钢筋直径≥18时采用机械连接剪力墙身竖向筋连接构造
本工程钢筋直径Φ≥20的钢筋水平和竖向接头均采用机械连接,钢筋直径16≥Φ≥20接头可采用机械连接或焊接,钢筋直径Φ≤16采用绑扎搭接接头。接头按照≯50%错开。
适合于梁、板、墙类构件 适合于柱类构件
位于同一连接区段的受力钢筋接头面积百分率应符合下表规定:
5)板钢筋的接头位置,上层钢筋在跨中1/3范围内,下层钢筋的接头在支座处,基础的接头位置设置与此相反,接头位置设置详见下图:
- 11 -
6)对于剪力墙底部应避免在节点核心区和加密区接头,当确实不能避免时应采用直螺纹接头,且钢筋接头面积率不得超过50%。
(2)绑扎搭接
1)核对成品钢筋的钢号、直径、形状、尺寸和数量是否与料单料牌相符,如有错漏,须立即纠正增补。
2)绑扎形式复杂的结构部位时,须先研究钢筋穿插就位顺序,并与木工讨论支模和绑扎先后次序,减少绑扎困难,钢筋确实摆放不下时,要与技术部门联系(可能涉及建设、设计、监理等单位)解决。
3)钢筋全部采用22#铁丝绑扎,所有钢筋交错点均须绑扎,且必须牢固,同一水平直线上相邻绑扣呈“八”字型,朝向混凝土体内部。钢筋搭接处,须在中心和两端用铁丝扎牢。
钢筋绑扎铁丝长度参考表(只供参考) 单位:mm
钢筋直径 6~8 10~12 14~16 16~20 6~8 150 10~12 170 190 14~16 190 220 250 18~20 220 250 270 290 4)受拉区域内,Ⅰ级钢筋绑扎接头的末端须做弯钩。 5)搭接长度的末端距钢筋弯折处,不得小于钢筋直径的10倍,接头不得位于构件最大弯矩处。
- 12 -
6)钢筋绑扎七不准:
1施工缝处浮浆未清理干净不准进行钢筋绑扎; ○
2钢筋污染清除不干净不准进行钢筋绑扎; ○
3控制线、检查线、轴线未弹不准进行钢筋绑扎; ○
4未检查钢筋位置不准进行钢筋绑扎; ○
5偏位钢筋不调整不准进行钢筋绑扎; ○
6钢筋接头错开位置未检查合格不准进行钢筋绑扎; ○
7钢筋接头质量未检查合格不准进行钢筋绑扎。 ○(3)直螺纹连接 2)丝头的加工
1丝头的加工工艺流程:钢筋端面平头→直螺纹成型→丝头质量检查→带帽○
保护→丝头质量抽检→存放待用。
钢筋丝头几何尺寸参数
套筒尺寸的允许偏差(mm) 套筒外径D ≤50 >50 ○2操作要点及要求
外径允许偏差 ±0.5 ±0.01D 长度允许偏差 ±0.5 ±0.5 - 13 -
丝扣的加工应符合上表中的要求,如丝扣不饱满,切掉2cm重新套丝;如出现丝扣超长,则用手持砂轮机磨掉;如丝扣长度不足时,需重新调整限位器并重新套丝,直至满足要求为止。
每加工10个丝头要用通规、止环规检查一次,经自检合格的丝头,应由质检人员随机抽样进行检验,以一个工作班内生产的丝头为一个验收批,随机抽检10%,且不得少于10个(填写钢筋丝头检验记录表),当合格率小于95%时,应加倍抽检,复检中合格率仍小于95%时,应对全部钢筋丝头逐个检查,切去不合格丝头,查明原因后重新加工螺纹。
加工丝头时,应用水溶性切削液,严禁用机油做切削液或不加切削液加工丝头,不得用气割下料。
对制作好的直螺纹接头进行检查100%检查并做上标记,对自检合格的丝头,在其两头拧上同规格的塑料保护帽按规格分类堆放整齐。
3)现场连接
连接钢筋时,钢筋规格和套筒的规格必须一致,钢筋和套筒的丝扣应干净、完好无损。直螺纹接头使用扭力扳手或管钳进行施工,将两个钢筋丝头在套筒中间位置相互顶紧,接头拧紧力矩应符合下表中的规定,扭力扳手的精度为±5%。
直螺纹钢筋接头拧紧力矩值一览表
钢筋直径mm 拧紧力矩N2m 18~20 160 22~25 230 28~32 300 用管钳或扭力扳手按规定的力矩值把钢筋接头拧紧直至扭力扳手在调定的力矩值上发出\咔嗒”声为止,并随手画上油漆标记,以防钢筋接头漏拧,单边外露丝扣长度不应超过2P(P为螺距)。
4)直螺纹接头验收程序:先由质检员100%检查合格并画上标记后,再报监理检查。
5)操作要点
1基础底板钢筋绑扎之前,根据结构底板钢筋网的间距,先在防水混凝土保护○
层上弹出黑色墨线,放出集水坑、墙、柱、承台梁位置线和加强带的位置边线。为了醒目便于日后定位插筋方便,在各边线每隔2.0m划上红色油漆三角。墙柱拐角处各划一个红三角,并将边线延长。
- 14 -
2根据800mm厚,1000(1200)mm厚板用25钢筋制作马凳支撑,马凳支撑为 ○
“工”字形,见下图。设置间距均为1000mm,呈一字状布置,并在底板四周外圈及中心区域内,将马凳用25钢筋焊接剪刀撑,以保证基础底板钢筋的整体稳定性。(支撑见下图)
③墙、柱插筋在基础底板内的位置及锚固长度必须按施工图要求设置,为了保证墙、柱插筋位置正确,放线人员把墙、柱位置线用红油漆标记在底板上层钢筋上,按标记线进行插筋施工。为了防止插筋位移,把墙插筋与底板钢筋绑扎并与附加定位筋点焊。为保证墙筋保护层厚度,根据墙身厚度设置用φ10钢筋焊成“∏”字型卡件,作为钢筋网限位,柱筋按要求设置后,在其上口增设一道限位箍。
墙、柱筋插完后,除检查其位置外,用线坠(2kg)检查其垂直度,并拉通线校正,确保竖向筋在同一直线上。防止倾斜、扭转、偏位。
④人防区域底板、墙体及顶板按照图纸要求设置拉筋,且间距按图纸要求设置, 拉筋为S形,梅花状排列。
(4)墙体钢筋 1)流程图
- 15 -
(2)基本项目
1)接缝宽度≤1.0mm (用工程检测仪上的楔形塞尺检查)。 2)模板表面必须清理干净,不得漏刷脱模剂(观察检查)。 3)允许偏差项目
项目 轴线位置 底模上表面标高 基础 截面内部尺寸 柱、梁 ≤5m 层高垂直度 >5m 相邻两板表面高差 表面平整度 8.3混凝土施工质量控制措施
8.3.1混凝土所用水泥、水、骨料、外加剂等必须符合规范及法规规定,检查出厂合格证和相应的试验报告是否符合质量要求。
8.3.2混凝土的配合比、搅拌、养护和施工缝处理必须符合施工规范要求。 8.3.3混凝土强度的试块取样、制作、养护和试验要符合规范要求,做好见证取样工作。
8.3.4混凝土振捣密实,不得有蜂窝、孔洞、露筋、缝隙、夹渣等缺陷。 8.3.5混凝土浇筑质量标准: 项次 1 项 目 独立基础 轴线位移 墙、柱、梁 层高 2 标高 全高 基础 3 截面尺寸 墙、柱、梁 ±5 尺量检查 ±30 +8,-5 用经纬仪检查 尺量检查 8 ±10 尺量检查 用经纬仪检查 允许偏(mm) 10 检验方法 尺量检查 8 2 5 经纬仪或吊线、钢尺寸检查 钢尺检查 2m靠尺和塞尺检查 +4、-5 6 钢尺检查 经纬仪或吊线、钢尺寸检查 允许偏差(mm) 5 ±5 ±10 检验方法 钢尺检查 水准仪或拉线、钢尺检查 钢尺检查 - 46 -
每层 4 5 6 7 8 柱、墙垂直度 全高 表面平整度 预埋钢板中心线位置偏移 预埋管、预留孔板中心线位置偏移 预留洞中心线位置偏移 5 30 -5,0 10 5 15 用2m托线板检查 用经纬仪检查 2m靠尺和塞尺检查 尺量检查 尺量检查 尺量检查 9.成品保护措施
1、成型钢筋应按指定地点摆放,用垫木垫放整齐,防止钢筋变形、锈蚀、油污。
2、绑扎墙柱筋时应事先在侧面搭临时架子,上铺脚手板。绑扎钢筋人员不准蹬踩钢筋。底板、楼板上下层钢筋绑扎时,支撑马凳绑牢固,防止操作时蹬踩变形。严格控制马凳加工精度在3㎜以内,防止底板、楼板上部砼保护层偏差过大。
3、严禁随意割断钢筋。当预埋套管必须切断钢筋时,按设计要求设置加强钢筋。
绑扎钢筋时禁止碰动预埋件及洞口模板。
4、模板内面涂脱模剂,要在地面事先刷好,防止污染钢筋。
5、安装电线管、暖卫管线或其他设施时不得任意切断和移动钢筋。如有相碰,则与土建技术人员现场协商解决。
6、不得在配好的模板上随意践踏、重物冲击;木背楞分类堆放,不得随意切断或锯、割。不准在模板上任意拖拉钢筋。在支好的顶板上焊接钢筋(固定线盒)时,必须在模板上加垫铁皮或其它阻燃材料,以及在顶板上进行预埋管打弯走线时不得直接以模板为支点,须用木方作垫进行。
7、拆除模板按标识吊运到模板堆放场地,由模板保养人员及时对模板进行清理、修正、刷脱模剂,标识不清的模板应重新标识;作到精心保养,以延长使用期限。
8、模板上的脱模剂晾干后才可吊运。
9、浇筑楼板砼时,砼输送泵管要用铁马凳架高300㎜,防止由于过重的泵管压塌板上部筋。去往操作面的主要通道也需设铁马凳,上铺跳板,边浇边撤。
10、在浇筑砼过程中,为了防止钢筋位置的偏移,在人员主要通道处的梁、板
- 47 -
钢筋上铺设跳板,操作工人站立在跳板上,避免踩踏梁板的钢筋和弯起钢筋,不碰动预埋件和插筋。
11、拆模时,对各部位模板要轻拿轻放,注意钢管或撬棍,不要划伤混凝土表面及棱角,不要使用锤子或其他工具剧烈敲打模板面。用塔吊吊装模板靠近柱时,要缓慢移动位置,避免模板撞击砼柱。
12、独立柱及突出墙面的柱角、处于通道或运输工具所能到达的墙阳角、门窗洞口等处各个阳角均用废竹胶板包起来,用铅丝绑扎固定,防止各个阳角被碰掉或碰坏。
13、机电材料进场时间必须配合使用时间,防止进场太早在现场闲置时间过长,增加材料保护成本和看护难度。
14、交叉作业看护:机电专业在进行机电预留预埋施工时,如需要碰动其它专业(如已钢绑扎好的钢筋及支好的模板)的成品时,必须以书面形式上报项目经理部,项目经理部经与其他专业分包协调后,其他专业派人协助分包单位施工,待施工完成后,其他人员恢复其成品。
15、机电预留预埋完成后除采取“护、包、盖、封”的保护措施外还应在土建砼浇注时派专人进行看护。
10.安全生产与文明施工措施
1、进入现场的钢筋机械在使用前,必须经项目工程部、安全部检查验收,合格后方可使用。操作人员需持证上岗作业,并在机械旁挂牌注明安全操作规定。
2、钢筋机械必须设置在平整、坚实的场地上,设置机棚和排水沟,防雨雪、防砸、防水浸泡。焊机必须接地,焊工必须穿戴防护衣具,以保证操作人员安全。
3、钢筋加工机械要设专人维护维修,定期检查各种机械的零部件,特别是易损部件,出现有磨损的必须更换。现场加工的成品、半成品堆放整齐。
4、钢筋加工机械处必须设置足够的照明,保证操作人员在光线较好的环境下操作。在进行加工材料时,弯曲机、切断机等严禁一次超量上机作业。
5、施工机械必须设置防护装置,每台机械必须一机一闸并设漏电保护开关。工作场所保持道路通畅,危险部位必须设置明显标志,保证安全用电。严禁踩在钢筋或钢管上操作。
6、现场在进行钢筋加工及成型时,要控制各种机械的噪音。将机械安放在平
- 48 -
整度较高的平台上,下垫木板。并定期检查各种零部件,如发现零部件有松动、磨损,及时紧固或更换,以降低噪音。浇筑砼时不要振动钢筋,降低噪声排放强度。
7、钢筋原材、加工后的产品或半产品堆放时要注意遮盖(用苫布或塑料),防止因雨雪造成钢筋的锈蚀。如果钢筋已生片状老锈,钢筋在使用前必须用铁丝刷或砂盘进行除锈。
8、为了减少除锈时灰尘飞扬,现场要设置苫布遮挡,并及时将锈屑清理起来,待统一清运到无锡市规定的垃圾集中地。直螺纹套丝的铁屑装入尼龙口袋送废品回收站回收再利用。垃圾及时运出现场,时刻保持现场的文明。
9、支模前必须搭好相关脚手架,脚手架必须稳固。在拆柱、墙模前不准将脚手架拆除,拆木胶板和竹胶板模板时,可把模板临时靠在脚手架上。用塔吊拆模时要有起重工配合;拆除顶板模板前必须划定安全区域和安全通道,将非安全区域用钢管、安全网封闲,并挂“禁止通行”安全标志,操作人员必须在铺好跳板的操作架上操作。已拆模板起吊前认真检查螺栓是否拆完、是否有勾挂的地方,并清理模板上杂物,仔细检查吊钩是否有开焊、脱扣现象。
10、浇筑混凝土前必须检查支撑是否可靠、扣件是否松动。浇筑混凝土时必须由模板支设班组设专人看模,随时检查支撑是否变形、松动,并组织及时恢复。
11、木工机械必须使用专用开关箱、禁止使用倒顺开关,一次线不得超过3米,外壳接保护零线,且绝缘良好。电锯和电刨必须接漏电保护器,锯片不得有裂纹(使用前检查,使用中随时检查);且电锯必须具备皮带防护罩、锯片防护罩、分料器,并接漏电保护器,电刨传动轴、皮带必须具备防护罩和护手装置。使用木工多用机械时严禁电锯和电刨同时使用;使用木工机械严禁戴手套;长度小于50cm或厚度大于锯片半径木料严禁使用电锯;两人操作时相互配合,不得硬拉硬拽;机械停用时断电加锁。
12、浇筑混凝土时若塔式起重机配合施工时,地面人员一定要配戴好安全帽并注意吊斗,不要被其碰伤。
13、在使用混凝土振捣器进行振捣时,操作人员必须穿绝缘鞋,戴绝缘手套。 14、振捣设备应设有开关箱,并装有漏电保护器。在指定电箱接线;振捣棒有专用开关箱,并接漏电保护器(必须达到两极以上漏电保护),接线不得任意接长。电缆线必须架空,严禁落地。
- 49 -
15、在使用混凝土输送泵进行浇筑时,严禁施工人员或其他人员站在泵管前端,以免混凝土泵喷浆时将人喷伤。
16、由于浇筑混凝土需连续不间断进行,因此必须合理的安排施工人员的交接时间让施工人员有适当的休息时间,以免施工人员出现疲劳作业发生危险。
17、在浇筑混凝土时要及时清理落在混凝土泵周围的混凝土,并将混凝土泵内和罐车内流出的循环水做好引导,以免影响市容环卫。
18、接拆泵管时,应在泵管架子上挂安全带,泵机运行时,机手不得离岗,并经常观察压力表、油温等是否正常。泵管连接,由专人操作,其他人不得随意拆接。混凝土泵送过程中定时、定人检查连接件及卡具有无松动现象。
19、对预拌混凝土运输车要加强防止遗撒的管理,要求所有运输车卸料溜槽处,必须安装防止遗撒的活动挡板,混凝土卸完后必须清理干净,方准离开现场。
20、罐车冲洗后,将清洗用过的废弃水经初步沉淀后,用于现场洒水、降尘,并定期将池内沉淀物清除。
21、现场混凝土采用低噪音混凝土振动棒,振捣混凝土时,不得振钢筋和模板,并做到快插慢拔。
22、 进入施工现场必须戴安全帽,禁止穿拖鞋或光脚,在无防护设施的高空施工时必须系安全带,严禁酒后操作。
23、使用电气焊时要有操作证,加强电、气焊作业,氧气、乙炔及其它易燃、易爆物的管理,氧气瓶与乙炔瓶的间距应大于10米,及时清除施焊点周围的易燃物,并设专人看火,备好消防用具,杜绝火灾事故的发生。
24、各种机电材料码放位置符合要求,码放高度应符合安全规定,并有防雨措施。
25、所有施工人员在施工完毕后,须做到工完料净场地清,保持现场清洁整齐,以免影响下道工序的施工。
江苏省建工集团德尔三期工程项目部
2015年12月20日
- 50 -
(7)楼梯钢筋 1)工艺流程
铺设楼梯底模 画位置线 绑平台梁主筋 绑踏步板及平台板主筋 绑分布筋 绑踏步筋 安装踏步板侧模 验收 浇筑砼
2)施工要点
1在楼梯段底模上画主筋和分布筋的位置线。 ○
2楼梯为板式楼梯,在绑扎楼梯间剪力墙钢筋时,先将楼梯板钢筋沿板走向○
弯折在楼梯间剪力墙内,楼梯板钢筋按20d、55d(距剪力墙边长度)各50%预留。待浇筑完楼梯间剪力墙砼后,再把楼梯板钢筋剔出,单面焊10d连接成楼梯板钢筋。绑扎板式楼梯
钢筋时,先绑扎主筋后绑扎分布筋,每个交点均应绑扎;
3当休息平台有梁时,在浇筑墙砼先在梁位置处预留梁豁,梯梁伸入墙内与○梯板一同浇筑砼。梁豁深度为3/4墙厚,在楼梯剪力墙外侧留出1/4墙厚,确保梁钢筋满足锚固长度且砼不出现色差。(见下图) 1/4墙厚A板筋预埋在楼梯剪力墙内楼梯梁、板梯梁在侧墙上预埋洞口A墙厚AA4楼梯板钢筋锚固到墙、梁内长度为30d(上筋)○、15d(下筋). 5楼梯板钢筋的砼保护层厚度为18mm(或15mm)○,为保证保护层厚度用塑料卡卡住板下铁。 (8)汽车坡道钢筋施工 1)作业条件
待墙模拆除后,剔除墙体上部的浮浆,露出石子;将预留的钢筋清理干净并进行校正,并将坡道板范围内的墙体混凝土凿毛;坡道底模已验收合格。
2)工艺流程
(铺设坡道底模)→画位置线→绑平台梁主筋→连接绑扎坡道板下部受力钢筋
- 21 -
→水电配管→绑马蹬→连接绑扎坡道板上层钢筋→验收→浇筑混凝土
3)施工要点
汽车坡道部位钢筋绑扎施工难点在于标高的控制,可先根据图纸中每段汽车坡道板的起始标高和结束标高在坡道板两侧的墙体钢筋上标出坡道板顶标高定位点,然后两点拉通线,每间隔1米的距离在墙体钢筋上标定一个板顶标高定位点,根据图纸中汽车坡道的坡度计算相应标高定位点的标高,测量人员根据此标高对标定的定位点进行复查,将标高定位点的偏差控制在±2mm以内。
根据校验好的标高定位点在坡道模板上弹钢筋定位线,然后进行钢筋的绑扎,其施工要求同楼板钢筋施工要求。
另要特别注意的是车道的标高控制和防水连接部位的处理。要严格检查。 (9)人防密闭门钢筋 1)人防密闭门钢筋按设计要求绑扎,在门洞处除横向和纵向加筋外,还在洞口四角处加设与水平方向成450角钢筋,配筋型号、长度及数量详见图纸。 洞高45d45d 洞宽人防密闭门门洞加固图2)在绑扎门洞处钢筋时,先将防护密闭钢门框预埋在钢筋内,且钢门框上附加墙钢筋与墙体钢筋点焊牢固,保证防护密闭钢门框的平直稳固。(见下图) 预埋防护密闭钢门框A 门洞宽钢门框附加钢筋与墙筋点焊牢固墙筋 - 22 - A节点
7.1.3 地下室人防区钢筋要求
(1)人防地下室的底板、顶板、墙板均设置Φ6≤500梅花形排列的拉结钢筋。 (2)人平板防护密闭门门框墙、门洞四角的内外侧配置两根直径Φ16mm的斜向钢筋,长度为1100mm。双面防护门墙体不小于500mm,并四角插筋3根Φ16。
(3)防门框墙的水平钢筋、箍筋做成封闭型。墙、柱插入底板部分设水平筋、箍筋,间距不大于500,且不小于2道。暗柱箍筋在密闭止水钢板处断开应与止水钢板焊接。
(4)各井口预埋角钢及钢筋扣,与底板整体浇筑。人防门下槛钢筋应与底板钢筋焊牢,防止踩下。
(5)人防染毒井、集水井、底板各种井口的止口要插钢筋 。 (6)地下室人防区管割断的墙筋须点焊在穿墙管上。
(7)地下室人防区梁与边柱交接处,外墙与顶、底板交接处钢筋构造要求为: 1)边柱外铡纵向钢筋伸地、顶梁内的锚固长度应≥1.5Lae;
2)当顶板厚度小于外墙厚芳时,顶板上排筋伸入外墙内锚固长度≥1.5Lae; 3)当顶板厚度大于和等于外墙厚度时,外墙外侧纵向钢筋伸入顶板内锚固长度≥1.5Lae;
4)外墙外侧纵向钢筋伸入底板内锚固长度≥1.5Lae。 7.1.4检验标准
(1)钢筋应有出厂质量证明书或试验报告单,钢筋表面和每捆(盘)钢筋均有标志。进场时应按批号及直径分批检验。检验内容包括查对标志、外观检查,并按现行国家有关标准的规定抽取式样做力学性能试验,合格后方可使用。
钢筋加工过程中,如发现脆断、焊接性能不良或力学性能显著不正常等现象,尚应对该批钢筋进行化学成分检验或其他专项检验。
(2)钢筋的级别、种类和直径应按设计要求采用。当需要代换时,应征得设计单位同意。
- 23 -
(3)钢筋的弯钩或弯折应符合下列规定:
1)HPB225级钢筋末端需做180°弯钩,其圆弧弯曲直径不应小于钢筋直径的2.5倍,平直部分长度不宜小于钢筋直径的3倍;
2)HRB335和HRB400级钢筋末端需做90°或135°弯折,HRB335级钢筋的弯曲直径不宜小于钢筋直径的4倍,HRB440级、RRB400级钢筋不宜小于钢筋直径的5倍;平直部分长度应按设计要求确定;
3)弯起钢筋中间部位弯折处的弯曲直径不应小于钢筋直径的5倍。 (4)钢筋加工的允许偏差,应符合下表规定:
项目 受力钢筋顺长方形全长净尺寸 弯起钢筋的弯折位置 允许偏差(mm) ±10 ±20 (5)钢筋接头应符合下列规定: 1)钢筋接头严格按照图纸施工,且满足设计总说明中规定。
2)焊接接头距钢筋弯折处,不应小于钢筋直径的10倍,且不宜位于构件最大弯矩处。
3)受拉钢筋绑扎接头的搭接长度,应符合下表规定:受压钢筋的绑扎接头的搭接长度,应取受拉钢筋绑扎接头搭接长度的0.7倍
受拉钢筋绑扎接头的搭接长度
钢筋类型 C20 HPB235级钢筋 月牙纹 HRB335级钢筋 HRB400级钢筋 RRB400级钢筋 35d 45d 55d 混凝土强度等级 C25 30d 40d 50d 高于C25 25d 35d 45d (6)钢筋保护层厚度设计无要求时,正常环境下,不宜小于256mm;在高湿度环境下,不宜小于45mm。(本人防工程钢筋保护层厚度是否依据11G101图集有待设计确认)
(7)绑扎或焊接的钢筋网和钢筋骨架,不得有变形、松脱和开焊。钢筋位置允许偏差应付下表规定:
- 24 -
项目 钢筋网的长度、宽度 网眼尺寸 骨架的宽度、高度 骨架的长度 间距 受力钢筋 排距 焊接 绑扎 中心线位置 水平高差 梁、柱 墙、板(拱) 焊接 绑扎 允许偏差(mm) ±10 ±10 ±20 ±50 ±10 ±10 ±5 ±10 ±20 5 ±30 ±5 ±3 箍筋、构造筋间距 焊接预埋件 受力钢筋保护层 (8)禁止使用冷加工的钢筋。 (9)注意墙、柱和梁的箍筋开口朝向。 7.2模板工程
7.2.1楼座、地库集水坑及电梯坑模板 (1)模板支设及设计概况 使用部位 主背楞及间距 次背楞及间距 模板厚度 对拉螺栓 备注 人防外墙、临空墙、防护密闭墙、密闭隔墙墙体对拉螺栓设置止水环且严禁采用PVC做套管及使用混凝土预制件。 墙体 圆48双架50*100mm管,1/2墙以方木,间距下450、以300mm 上500mm 100*100mm方木或圆50*100mm方木间距250mm 18mm 14mm(带止水环的对拉螺栓止水环规格为50*50*3mm) 板 48双架管间距15mm - 25 -
1000mm 圆48双架柱 管间距600mm 50*100mm方木,间距200mm 18mm 14mm 电梯井坑和集水坑,四周砌筑240mm厚砖墙,砖墙砌到电梯、集水坑的筏板底部标高位置(留出底板垫层及防水做法)。内侧模采用18厚多层板,周边龙骨为503100木方@300设置一道;按照图纸尺寸要求事先在现场制作完成,底口周边设一道250宽水平挡板,先浇筑地坑混凝土,待其初凝前半小时,再浇筑上部混凝土。具体详见下图:
- 26 -
- 27 -
为保证模板的垂直度和平整度,安装前事先在坑侧竖向主筋上捆绑钢筋保护层垫块,限制坑模侧向移位。 (2)注意事项
◆人防外墙、临空墙、防护密闭墙、密闭隔墙、水池侧墙及有密闭要求的隔墙采用止水螺杆,止水螺杆的止水片规格为50*50*3mm。
◆本工程人防部位墙螺杆不得使用套管及混凝土预制件。
◆本工程独立柱单独浇筑,墙与梁、板同时浇筑,地下室外墙及水池侧墙施工缝位置须埋设止水钢板。 7.2.2地库、楼座地下墙体模板 (1)模板选型
地下外墙墙模板背楞竖向为503100方木,间距300mm;水平采用双架管固定在竖向架管的外侧,1/2墙高以下间距为400mm,以上为500mm。支模时支撑系统支撑在双架管上,模板采用φ14止水螺杆(与墙两端接触处用用止水胶塞)加固,止水螺杆水平@450,竖向1/2墙高以下@400mm,以上@500mm ;用“山”型卡卡在横向双架管上,1/2墙高以下用双山型卡加双螺母紧固。
在内外墙及内墙与内墙交汇处,如不满足上述要求,可进行适当调整对拉螺栓或木模板,但应以其具有相应的刚度、强度及稳定性为原则。
1)对拉螺栓及止水胶塞设置
- 28 -
2)地下内外墙模组拼模板时,两模板之间的拼缝应不大于2mm,且缝隙内塞满海绵条。
3)地下内墙体模板采用18mm厚多层板,竖向采用50*100mm方木及双架管背楞,墙体两侧与满堂红脚手架连接,与满堂红脚手架的连接的竖向高度范围为900~1200mm,钢管与钢管之间用扣件锁牢。对拉螺杆间距同外墙布置。安装详见下图:
4)阴阳角模板
阴阳角模板采用木模板拼接,模板每面宽度控制在200mm之内。面板采用18mm厚多层板,阴角处使用100*100mm木方,木方必须刨平光滑,保证阴角的角度。在木方的角上必须粘贴单面海绵条,海绵条严禁贴出木方面,阴角模板拼接必须压在海绵条上,防止漏浆。
(2)地下外剪力墙及地库挡土墙
- 29 -
当进行外剪力墙及地库挡土墙模板支设时,墙体在房间(地库)的一侧,水平支撑与满堂红脚手架连接,连接方式同内墙。墙体在室外的一侧,模板支设后,应事先在筏板基础上预埋好¢25钢筋@900,高出筏板面200mm,采用钢管斜拉支撑,楼座外墙纵向斜撑应不少于4道,地库挡土墙应不少于6道,斜撑水平间距应不大于1.5m。 (3)工艺要点
◆人防外墙导墙高度为500mm。
◆模板组片完毕后,要求留设清扫口,检查模板的对角线,平整度和外形尺寸。 ◆安装第一片模板用铅丝与柱子主筋临时绑扎固定。 ◆随即安装第二、三、四片模板,作好临时支撑或固定。 ◆先安装上下两个柱箍,并用脚手管和架子临时固定。
◆逐步安装其余的柱箍,校正柱模板的轴线位移、垂直偏差、截面、对角线,并做支撑。
◆按照上述方法安装一定流水段柱子模板后,全面检查安装质量,注意在纵横方向上都挂通线检查,并作好群体的水平拉(支)杆及剪力支杆的固定。
◆将柱模内清理干净,封闭清理口,检查合格后办预检。
◆对于模板高于浇筑高度的情况,应特别注意控制砼的浇筑标高,浇筑标高=与柱相交的最低梁底标高+20mm。
◆为了有效地减小侧压力,浇筑混凝土时一定要控制浇筑速度,不能大于2.0m/小时。混凝土塌落度对侧压力也有很大影响,以混凝土能出泵管为宜,最大不能超过180mm。 7.2.3顶板模板
地下车库层高为4.5m,楼座地下室层高为分别为3.6m、3.32m。 (1)顶板模板设计
楼座顶板采用15mm厚覆膜多层板,地库顶板采用18mm厚覆膜多层板。楼座支撑采用扣件式满堂脚手架支撑体系,立杆上设有可调顶托。地库顶板采用碗扣式满堂红脚手架。顶板次龙骨采用503100mm木方,间距250,主龙骨采用1003100木方或圆48双架管,间距为1000。楼座地下顶板脚手架立杆间距900*900mm,横杆步距1500mm,扫地杆距地面200mm。地库顶板脚手架立杆间距600*900mm,步距
- 30 -
1200m。地库独立柱帽范围内脚手架立杆间距600*600mm,步距1200mm。现浇钢筋混凝土板,当短跨跨度等于或大于4m时模板应起拱,起拱高度见下表。
起拱高度控制表
短跨跨度(m) 起拱数值(mm) 4~5 9 5~6 11 6~7 13 7~8 15 (2)顶板模板支设 脚手架从墙边开始往另一侧开始搭设。立杆下口必须垫50*100木方或18*200*200mm厚多层板垫片,木方要求长度、方向一致,立杆位置要求上下层位置对应。住宅楼每间屋脚手架搭设完后支设主次龙骨,车库搭设完每跨脚手架后支设主次龙骨。然后在墙柱钢筋上用白线拉设50线网,调节龙骨高度,再铺设顶板。龙骨必须刨平,尺寸一致。
顶板由墙边或梁边开始铺设,向中心部位后退铺设。墙边或梁边模板尽量选用整张新板,铺设前对单张多层板四边的方正进行校对,不方正的必须经过修理后再铺设,防止接缝不严密导致漏浆。顶板模板与墙体接触面在模板的侧面贴单面海绵条,海绵条粘贴时必须准确,严禁贴出板面。模板与墙体的接触面必须挤实压紧。
模板起拱形式实行中间起拱,用木楔间距1000mm钉进主龙骨和面板的中间使模板中间抬高至所需起拱高度。
顶板模板支设详图、顶板与墙体连接节点详图。
- 31 -
- 32 -
(3)楼座内暗梁模板支设
(4)工艺要点
◆脚手架按照模板设计要求搭设完毕后,根据给定的水平线调整上支托的标高及起拱的高度。
◆按照模板设计的要求支搭板下的大小龙骨,其间距必须符合模板设计的要求。
◆铺设模板,用电钻打眼,螺丝与龙骨拧紧。必须保证模板拼缝的严密,且所有板接缝处用胶带封严。
◆模板铺设完毕后,用靠尺、塞尺和水平仪检查平整度与楼板标高,并进行校正。
◆将模板内杂物清理干净,检查合格后办预检。
◆剪刀撑斜杆与地面倾角为45°~50°,剪刀撑跨越立杆最多根数为6根。剪刀撑纵向及横向间距为一个跨距(即柱间距)。
◆扫地杆:必须设置纵、横向扫地杆,固定在距底座上皮200mm处的立杆上。 ◆注意图纸中板中拉结筋,且忘施工。
- 33 -
7.2.4门窗洞口模板 门窗洞口模板采用15mm厚的红木板制作定型模板,背楞采用503100mm双木方,在模板的四角分别采用一根503100mm木方连接固定。 墙面上的门、窗及预留孔模板支设可根据以下详图进行支设。 1)当预留孔宽度小于1500mm时 503100木方503100木方胶合面板<1500 预留洞模板设置图 2)当预留孔宽度大于1500mm时 503100木方胶合面板振导孔预留洞模板设置图 3)当预留孔为圆洞时 木方胶合面板预留圆洞模板设置图 - 34 - 人防门框墙的水平筋、箍筋应做成封闭式,且开口的一面不在门框处。墙、柱竖筋,插入底板部分的水平筋、箍筋间距不大于500mm且不少于两道。 7.2.5检验标准
(1)阴阳角或丁字墙模板拼缝要求密闭、严实且海绵条位置放置准确。 (2)保证工程结构和构件各部分形状、尺寸和相互位置正确。 (3)模板的接缝不应漏浆。
(4)临空墙、门框墙的模板安装,其固定模板的对拉螺栓上应严禁采用套管、混凝土预制件等。
(5)模板及其支架在安装过程中,必须设置防倾覆的临时固定设施。 (6)现浇钢筋混凝土梁、板,当跨度等于或大于4m时,模板应起拱;当设计无具体要求时,起拱高度宜为全跨长度的1‰~3‰。
(7)模板安装的允许偏差应符合下表规定
项目 轴线位置 标高 截面尺寸 表面平整度 垂直度 相邻两板表面高低差 预埋管、预留孔中心线位置 预埋螺栓 中心位置 外露长度 中心线位置 截面内部尺寸 允许偏差(mm) 5 ±5 ±5 5 3 2 3 2 +100 10 +100 预留洞 (8)模板及其支架拆除时的混凝土强度,应符合设计要求;当设计无具体要求时,应符合下列规定:
1)侧模,在混凝土强度能保证其表面及棱角不因拆除模板而受损坏后,方可拆除;
2)底模,在混凝土强度符合下表规定后,方可拆除。
结构类型 结构跨度(m) 按设计的混凝土强度 - 35 -
标准值的百分率计(%) ≤2 板 2~8 >8 梁、拱、壳 ≤8 >8 50 75 100 75 100 (9)已拆除模板及其支架的结构,在混凝土强度符合设计混凝土强度等级的要求后,方可承受全部使用荷载;当施工荷载所产生的效应更为不利时,必须经过核算,加设临时支撑。 7.3混凝土工程 7.3.1施工流程安排
底板混凝土浇筑→排架搭设 → 柱子和墙钢筋绑扎 → 柱子和墙模板支设 → 验收 →柱子和墙砼浇注 → 柱子模板吊装移至下流水段 → 梁、板模板支设 → 梁、板钢筋绑扎 → 验收 → 梁、板混凝土浇注 7.3.2混凝土浇筑方法和技术措施
(1)作业准备和混凝土运送
1)混凝土搅拌站必须把配合比通知单、合格的水泥、砂、石、外加剂、掺合料材质证明、原材复试报告、合格证、准用证、抗压强度试验报告、抗渗强度试验报告等质量保证资料上报以及施工方取得混凝土浇注确认单方可开始浇注混凝土。
2)配置两台混凝土地泵,四台混凝土汽车泵。现场配备一台发电机,已备停电时保障混凝土浇筑用电。
3)砼泵管运输道路尽量平整,以减少运输时的震荡,避免造成混凝土的分层离析。水平砼泵管用马凳支撑,垂直泵管在弯管处搭脚手架固定,泵管连接必须牢固、稳定,各管卡位置不得与地面或支撑物接触,管卡在水平方向距离支撑物≥100mm,距离地面≥100mm,接头密封严密(垫圈不能少)。拆泵管时管内混凝土清洗干净。
4)接泵管时,把泵管连接端80cm范围内混凝土掏净,并把接头擦干净。 5)柱子混凝土采用塔吊配合布料杆浇筑。
- 36 -
(2)混凝土浇注 1)浇筑分层厚度
浇筑层厚度≤振捣棒作用部分长度的1.25倍。本工程采用50型振动棒(作用部分长度38.5cm),混凝土分层厚度500mm。现场制作五根混凝土浇筑厚度控制杆(在50mm325mm35000mm)木条上刷黄油漆,自下而上每500mm用红油漆标上刻度,刻度字体要大而醒目)随时探测、调整混凝土(包括柱、梁混凝土等)浇筑厚度。浇筑混凝土时用手电筒照明读取厚度控制杆上数据,从而控制浇筑厚度。
2) 混凝土振捣
1振捣时振捣棒要快插慢拔,且必须插入下层≥50mm(根据分层厚度,在振动○
棒上作红漆刻度线来控制)。振动棒移动间距≤60cm。振捣时间通过观察(混凝土表面泛出浆、不再显著下沉、不再出现气泡)来确定。振捣器距离模板≥20cm。
2振捣时注意钢筋密集及洞口部位,○为防止出现漏振,须在洞口两侧同时振捣,
振捣棒应距洞边30cm以上,下灰高度也要大体一致,大洞口的洞底模板应留出气孔,并在此处浇筑振捣。
3从施工缝处开始浇筑混凝时,不能直接靠近缝边下料,振捣时由远而近向施○
工缝处推进,距离缝边900mm±100mm(用卷尺来控制)处停止振捣,对此处混凝土改用人工加强振捣,使其结合紧密。顶板、梁采用斜向振捣,振动棒与混凝土表面成42°,严禁振捣棒直接振捣钢筋、模板和预埋件。
4混凝土拌合料在搅拌、浇筑入模后,必须振动捣固。 ○
5浇筑时,每条泵管配备足够的振捣棒。使混凝土自然缓慢流动,然后全面振○
捣。根据混凝土泵送时自然形成的坡度,在每个浇筑层的前后布置两道振动器。第一道布置在混凝土卸料点,解决上部混凝土的振实,由于底皮钢筋间距较密,第二道布置在混凝土坡角处,解决下部混凝土的密实,随着混凝土浇筑工作的向前推进,振动棒相应跟上,保证整个高度混凝土的质量。
6振捣过程中应将振捣棒上、下来回抽动50~100mm,以使上、下震动均匀。○
每点振捣时间一般为20~30 秒,使混凝土表面不显著沉降,不出现气泡,表面泛出灰浆为止。每个流水段应设专人指挥振捣工作,严防漏振、过振造成混凝土不密实、离析的现象产生。防止先将表面混凝土振实而与下面混凝土发生分层、离析现象,填满振捣棒抽出时造成的空洞。
- 37 -
7振捣器插点要均匀排列,采用“行列式”或“交错式”的次序移动。不应混○
用,避免漏振。振动器移动间距为500mm。
8插入式振捣器操作要点是:○“直上直下,快插慢拔;插点要均匀,切勿漏点
插;上下要振动,层层要扣搭;时间掌握好,密实质量佳。”
9振捣时应避免碰撞钢筋、模板、芯管、吊环、预埋件等。 ○
3)底板混凝土浇注
本工程采用斜面分层浇筑,分层高度以尺杆衡量。遵循“斜面分层,一个坡度,薄层覆盖,循序渐进” 的原则,每层厚度为300cm,从短边开始沿长边浇。施工时应从浇筑层下端开始,逐渐上移,以保证混凝土的质量。
将所有泵管支设到位,浇筑时各排输送管定点,各负其责。
利用泵管或泵管前连接的软管在底板上皮钢筋的表面上直接布料,在保证混凝土不出现冷缝的前提下,利用软管左右移动,作扇形状散布混凝土,尽量使入模混凝土散布面积大以增加散热与热量交换。
4)集水坑、电梯基坑内混凝土的浇筑
根据大面积基础底板混凝土流淌速度的范围,需提前进行临近集水坑内泵送混凝土的施工,并振捣密实。将集水坑、电梯基坑混凝土浇筑至与大底板平齐,与基础底板混凝土部分交接严密。
由于本工程集水坑、电梯基坑较深,故采用间歇浇筑的方法,其模板做成整体式并预先架立好,先将基坑底板浇至与模板平,待坑底混凝土流动性不大,可以承受坑壁混凝土压力时,再浇筑基坑坑壁混凝土,要保证底与壁接触处的质量。间歇时间在2h 左右。
派专人检查集水坑、电梯基坑底板混凝土状态,在混凝土初凝之前进行大面积
- 38 -
基础底板混凝土施工。坑底浇筑顺序由长度方向从一端向另一端浇筑推进,或由两端向中间浇筑。坑壁应形成环行回路分层浇筑。集水坑、电梯基坑侧壁混凝土浇筑时,采用对称浇筑的方法,确保侧壁模板受力均匀。
5)地下室外墙导墙混凝土
地下室外墙随底板一起浇筑高于底板500mm的导墙。
将导墙的吊帮模板安装好后,先浇筑底板混凝土,在底板混凝土初凝前浇筑外墙导墙混凝土。
6)竖向结构浇注
工程口部(竖井、扩散室、密闭通道、防毒通道、洗消间、除尘室、滤毒室、出口防护密闭以外的通道等)、防护密闭段、采光井、水库、水封井、防毒井、防爆井等有防护密闭要求的部位,应一次整体浇注混凝土。
浇筑顺序是外墙、内墙。墙体浇筑前在底部应先填以75±25mm厚同配比水泥砂浆,以免底部出现蜂窝现象。使用φ50和φ30振捣棒,墙体砼必须分层循环浇筑,一次浇筑高度为50cm,用标尺杆随时检查混凝土高度,浇筑同一部位时不得使用两种振捣棒,移动间距分别为≤50cm(50振捣棒)、≤40cm(30振捣棒,在钢筋加密区如连梁位置),振捣时间通过观察(砼表面泛出浆、不再显著下沉、不再出现气泡)来确定,振捣时上层要插入下层≥50mm,严禁用振捣棒直接振捣模板。砼自高处倾落的自由高度不得超过2m。上下层的间隔时间不应超过2h,预先安排好混凝土下料点位置和振捣棒操作人员数量、振捣插入点位置。(见下图)
(300)200振捣点成一字型布置400400200-300厚墙砼振捣插入点布置图门窗洞口砼浇筑必须从两侧均匀下料(高差≤50cm),以避免模板位移先浇筑窗台下口,后浇筑窗与窗、窗与门、门与门间墙。不同强度交接部位应用钢丝网片拦挡,外墙体砼应比内墙砼先浇筑一个分层高度(即500mm高)。砼浇筑间歇时间不得大于混凝土的终凝时间。 应派专人看护模板,发现模板有变形、位移时立即停止浇筑,并在已浇筑的混
- 39 -
凝土终凝前修整完好,再继续浇筑。振捣时须保证砼填满、填实。在混凝土凝固前,及时用湿抹布将上部筋擦净。
标高要一致,严禁出现高低差。
须在砼强度达到要求,由现场工长填写拆模报告,经质量及技术负责人等相关人员签字确认后才允许拆模。
墙上口找平:墙体砼浇筑完后,将上口甩出的钢筋加以整理,用木抹子按标高线添减砼,将墙上表面砼找平,高低差控制在10mm以内。
7)梁板混凝土浇注
梁、板砼应同时浇筑,浇筑方法由一端开始用“赶浆法”即先浇筑梁,根据梁高分层浇筑成阶梯形,当达到板底位置时再与板的砼一起浇筑,随着阶梯形不断延伸,梁板混凝土浇筑连续向前进行。浇筑与振捣必须紧密配合,第一层下料慢些,梁底充分振实后再下第二层料,保持水泥浆沿梁底包裹石子向前推进,每层均应振实后再下料,梁底及梁帮部位要注意振实,振捣时不得触动钢筋及预埋件。
浇筑同一部位时不得使用两种振捣棒,震捣时快插慢拔,震点均匀排列、逐点移动、顺序进行、不得遗漏。振捣时间通过观察(砼表面泛出浆、不再显著下沉)来确定。
派专人看护模板、钢筋、止水片,调整纠偏,发现模板有变形、位移时立即停止浇筑,并在已浇筑的混凝土凝结前修整完好。对柱梁板交叉处,钢筋过密,振捣时须保证砼填满、填实,以防出现孔洞。
钢筋根部用塑料布包扎(高度为50cm),以防被砼污染,混凝土浇筑完毕后,凝固前,及时用湿抹布将局部漏浆、掉渣擦去。混凝土浇筑完毕终凝前必须顺南北方向用扫毛塑料刷子扫毛,扫毛纹路要清晰均匀、方向及深浅一致。在墙体两侧位置各10cm范围内用铁抹子抹光,该位置砼表面的平整度要求控制在3mm以内。
梁柱节点钢筋较密时,浇筑此处混凝土时用小粒径石子同强度等级的砼用塔吊吊斗浇筑,并用φ30振捣棒振捣。
双层板浇筑时,先浇筑到上层板底20-30mm,等其强度达到设计值,在浇筑上层板。
同层如果梁混凝土强度等级比柱混凝土强度等级低5Mpa(含)时内,则节点区可按照梁混凝土强度等级,如梁混凝土强度等级比柱混凝土强度等级低5Mpa以
- 40 -
上,则节点区需按照柱混凝土强度等级,在浇筑此处部位时应在柱梁交接处设置钢丝网,先浇筑柱混凝土,后浇筑梁板混凝土。
浇筑板混凝土的虚铺厚度应略大于板厚,用平板振捣器垂直浇筑方向来回拖动振捣,并用铁插尺检查混凝土厚度,振捣完毕后用木刮杠刮平,浇水后再用木抹子压平、压实。施工缝处或有预埋件及插筋处用木抹子抹平。浇筑板砼时不允许用振捣棒铺摊砼。
防空地下室的顶板不允许抹灰,密闭通道、防护密闭通道、洗消间、简易洗消间、滤毒室、扩散室等战时易染毒的房间通道,其墙面、顶面、地面均应平整光洁,易于消洗。
8)楼梯砼的浇筑
楼梯间竖墙砼随结构剪力墙一起浇筑砼。
楼梯段砼自下而上浇筑,先振实底板混凝土,达到踏步位置时再与踏步混凝土一起浇捣,不断连续向上推进,并随时用木抹子将踏步上表面抹平。
施工缝位置:楼梯砼宜连续浇筑完;多层楼梯的施工缝应留置在楼梯段1/3的部位。
(3)平整度控制
1)施工现场按照6*6米间距设置水准控制点,水准点设置在柱子钢筋部位,做为混凝土浇注以及收平的控制依据,且在绑楼板钢筋前、绑完钢筋后、浇注混凝土过程中均须不断复测,并及时调整。
2)施工过程中及时排除混凝土振捣产生的泌水,在混凝土浇筑后用长刮尺刮平,在初凝前由抹灰工配合收光机逐步收平:有建筑找平层部位收平并拉毛(顺南北或东西方向用扫帚扫毛,扫毛纹路要清晰均匀、方向及深浅一致),并提高混凝土的密实度和抗裂性能,减少表面裂缝。
3)为保证混凝土面质量,浇注混凝土前,应防止遇到大或暴雨,并提供足够的彩条布做好准备,对已浇注的混凝土面及时进行覆盖养护。 (4)混凝土养护
1)混凝土的养护期间必须严格控制其内外温差,确保不出现有害裂缝,确保混凝土质量,养护是一项十分关键的工序,应根据气候条件采取控温措施。
2)混凝土养护要达到保温、保湿的目的。保温能使混凝土表面温度不致过快
- 41 -
散失,减少混凝土表面的热扩散和温度梯度,从而避免产生表面裂缝;保湿使混凝土在强度发展阶段保持湿润,防止混凝土表面脱水而产生干缩裂缝,使水泥水化顺利进行,提高混凝土的极限拉伸强度。
3) 本工程基础底板混凝土养护,采用浇水保湿降温养护。
4) 在基础底板上铺放塑料布后进行浇水养护,保证塑料布内外湿润。塑料布应叠缝,以减少水分的散发。
5) 为保证混凝土内部与混凝土表面温差小于25摄氏度,表面温度与大气温度之差小于25摄氏度,采用塑料薄膜覆盖养护的同时,还要覆盖麻袋。
6) 在养护过程中,如发现遮盖不好,表面泛白或出现干缩细小裂缝时,要立即仔细加以覆盖,加强养护工作采取措施,加以补救。
7) 为了确保新浇筑的混凝土有适宜的硬化条件,防止在早期由于干缩而产生裂缝,混凝土浇筑完毕后,在6小时内加以覆盖。混凝土养护时间不得少于14天。
8)柱混凝土采用喷养护剂或淋水方式进行养护。
9)浇筑完成的混凝土强度≤1.2Mpa前,不得上人和进行其它作业。 7.3.3检验标准
(1)大体积混凝土的浇筑应合理分段分层进行,使混凝土沿高度均匀上升;浇筑应在室外气温较低时进行,混凝土浇筑温度不宜超过28℃。
(2)防护密闭段、采光井、水封井、防毒井、防爆井等由防护密闭要求的部位,应一次整体浇筑混凝土。
(3)建筑混凝土时,应按下列规定制作试块: 1)口部、防护密闭段应各制作一组试块; 2)每浇筑100m3混凝土应制作一组试块;
3)变更水泥品种或混凝土配合比时,应分别制作试块; 4)防水混凝土应制作抗渗试块。 (4)后浇带的施工应符合下列规定:
1)后加缝宜在其两侧混凝土龄期达到42d后施工
2)施工 前,应将接缝处的混凝土凿毛,清楚干净,保持湿润,并刷水泥浆; 3)后浇带应采用补偿收缩混凝土,其配合比应经试验确定,强度宜高于两侧混凝土一个等级;
- 42 -
4)后浇带混凝土的养护时间不得少于28d。 (5)施工缝的位置留设应符合下列规定:
1)本人防工程底板及顶板的施工缝位置留设在后浇带处。
2)侧墙施工缝应设在高处底板表面不小于500mm的墙体上;当侧墙上有孔洞时,施工缝距孔洞边缘不宜小于300mm;
3)垂直施工缝应避开地下水和裂隙水较多的地段。 (6)混凝土表面缺陷的修整应符合下列规定:
1)面积较小且数量不多的蜂窝或露石的混凝土表面,可用1:2~1:2.5的水泥砂浆抹平,在抹砂浆之前,必须用钢丝刷或加压水洗刷基层;
2)较大面积的蜂窝、露石或露筋,应按其全部深度凿去薄弱的混凝土和个别突出的骨料颗粒,然后用钢丝刷或加压水洗刷表面,再用比原混凝土等级高一个级别的细骨料混凝土堵塞并捣实。
注:补修需在人防专业人员验收通过后进行。
(7)门框应八字形支撑且支撑要稳定、牢固;在浇筑门框墙混凝土时,必须跟踪监测钢门框的位置和垂直度,发现问题及时调整,浇筑混凝土要均匀投料,小心振捣,不要猛烈震荡模板,以防门框移位,供安装人防门扇使用的吊钩,须在浇筑混凝土前,按设计要求布设到位(也可与人防门厂家沟通布设)。
(8)门框墙:
门框墙对地下室的防护作用关系极大,在施工中必须认真对待,以保证门框墙的质量要求,严禁有蜂窝、孔洞、露筋等现象。
为保证门框墙结构尺寸准确、表面平整,支撑时模板要压住人防门框的角钢边,要确保模板的刚度、强度和稳定性,要加强、加密门框墙模板的支撑体系;门框四周配模时,应贴上一圈塑料泡沫胶带,以防漏浆。
(9)混凝土工程验收
1)混凝土构件有蜂窝、孔洞、主筋露筋、缝隙夹渣层时,其蜂窝、孔洞面积、主筋露筋长度和缝隙夹渣层长度、深度,应符合下列规定:
①梁、柱上任何一处的蜂窝面积不大于1000cm2,,累计不大于2000 cm2,;孔洞面积不大于40cm2,累计不大于80cm2,主筋露筋长度不大于10cm,累计不大于20cm;缝隙夹渣层长度和深度均不大于5cm。
- 43 -
②墙、板上任何一处的蜂窝面积不大于2000 cm2,累计不大于4000cm2;孔洞面积不大于100cm2,累计不大于200cm2;主筋露筋长度不大于20cm,累计不大于40cm;缝隙夹渣层长度不大于20cm,深度不大于5cm,且不多于2处。
2)现浇钢筋混凝土结构的允许偏差应符合下表规定:
项目 轴线位置 标高 层高 全高 柱、梁 截面尺寸 墙、板(拱) 柱、墙垂直度 表面平整度 预埋管、预留孔中心线位置 预埋螺栓中心线位置 预留洞中心线位置 电梯井 井筒长、宽对中心线 井筒全高垂直度 允许偏差(mm) 10 ±10 ±30 ±5 ﹢8 -5 5 8 5 5 15 +250 H/1000且不大于30 注:H为电梯井筒全高(mm)。 8.质量保证措施
8.1钢筋工程质量控制
8.1.1钢筋安装绑扎允许偏差和检查方法
序 1 2 3 4 项 目 绑扎骨架 绑扎钢筋网 受力主筋 宽、高 长度 长、宽 网眼尺寸 间距 排距 允许偏差值(mm) ±5 ±10 ±10 ±10 ±10 ±5 ±10 检查方法 尺量 钢尺检查 钢尺检查 尺量 尺量连续五个间距 绑扎箍筋、横向钢筋间距 - 44 -
5 6 钢筋弯起点位置 基础 受力主筋保护层 梁、柱 墙板、楼板 ±15 ±5 ±3 ±3 1个 3个 4 +3,0 尺量 尺量受力主筋外表面至模板内表面垂直距离 目测 7 8 直螺纹接头外露丝扣 预埋件位置 锥筒外整扣 锥筒外半扣 中心线位置 水平高差 8.1.2钢筋工程的观感质量 (1)现场钢材和钢筋半成品堆放保管工作规范,标识清晰。
(2)钢筋骨架安装绑扎及其构成的钢筋半成品质量和控制保护层措施,应符合基本规定。
(3)洞口构造加筋、预埋件、电器线管、线盒、预应力筋及其配件等,位置准确,绑扎牢固,需焊接固定部位,不准咬伤受力钢筋。
(4)钢筋工程整体观感质量好,现场整洁。 8.2模板工程质量控制 8.2.1质量控制程序
班组内实行 “三检制”,合格后报分包工长检验,再依次报项目木工工长、质量总监进行核定,并按国标及天津市地方性标准填写预检记录表格、检验批表格和报验单,并向监理报验。每个环节检查出质量问题,视性质、轻重等查处上一环节责任,并由上一环节负责人负责改正问题。 8.2.2质量控制注意点
(1)浇筑混凝土前必须检查支撑是否可靠、扣件是否松动。浇筑混凝土时必须由模板支设班组设专人看模,随时检查支撑是否变形、松动,并组织及时恢复。
(2)混凝土吊斗不得冲击顶模,造成模板几何尺寸不准。 (3)在柱墙根部、梁柱交接处加粘憎水海绵条。 (4)支模前仔细检查脱模剂是否涂刷均匀。 8.2.3结构模板安装质量标准
(1)保证项目
模板及其支架、支撑必须有足够的强度、刚度和稳定性。
- 45 -
正在阅读:
基础人防工程施工方案11-14
2018标准化监理项目工程部(业主项目工程部)人员配置标准11-23
初中语文实词虚词词性练习题及答案09-05
备考2018年初级银行从业资格考试《公司信贷》真题练习卷一28(乐考网)09-06
关于“可食用水球”调查报告01-28
店面管理工作手册07-17
小学实践作文06-15
印刷飞达调节方法-印刷之家07-10
- exercise2
- 铅锌矿详查地质设计 - 图文
- 厨余垃圾、餐厨垃圾堆肥系统设计方案
- 陈明珠开题报告
- 化工原理精选例题
- 政府形象宣传册营销案例
- 小学一至三年级语文阅读专项练习题
- 2014.民诉 期末考试 复习题
- 巅峰智业 - 做好顶层设计对建设城市的重要意义
- (三起)冀教版三年级英语上册Unit4 Lesson24练习题及答案
- 2017年实心轮胎现状及发展趋势分析(目录)
- 基于GIS的农用地定级技术研究定稿
- 2017-2022年中国医疗保健市场调查与市场前景预测报告(目录) - 图文
- 作业
- OFDM技术仿真(MATLAB代码) - 图文
- Android工程师笔试题及答案
- 生命密码联合密码
- 空间地上权若干法律问题探究
- 江苏学业水平测试《机械基础》模拟试题
- 选课走班实施方案
- 人防
- 工程施工
- 基础
- 方案
- 中央银行学(含答案)
- 管理类SCI期刊总结分析
- 许昌新乡平顶山三市2013届高三第二次调研考试--数学理
- 环境影响评价持证单位日常考核表(报告表)
- 3、信用管理师复习判断题(55题)
- 物理竞赛简谐运动习题-2
- 龅牙的几种解决办法
- 我给学生讲爱情
- 2017年广东公需课四门考试答案(全)专题一工匠精神解读与培育的思考专题二精益专题三创新精神专题四让技能
- 2019届高三一轮复习单元测试 文言文阅读之断句
- 分析化学课后习题答案
- 叶茂中谈案例探析:营销中如何拉起土豪的手?
- 南昌大学2010-2011-2有机化学期末考试试卷(B)及答案剖析
- 劳动力过剩条件下的非正规就业问题研究
- 中班上学期幼儿发展
- 英语笔译实务 3级配套训练 第十六单元 英译汉(二)Meat and Milk from Cloning Are Safe
- 原位固化法管道修复方案
- 小学信息技术(豫科版)五年级教案上册
- 第一章习题与答案
- 广东省某重点中学2015届高三专题练习之选择题专题训练2015高考