义马气化厂应急总预案
更新时间:2024-06-05 11:50:01 阅读量: 综合文库 文档下载
- 河南义马气化厂推荐度:
- 相关推荐
义马气化厂应急预案目录
1. 火灾与爆炸应急预案········································2 2.义马气化厂电网故障应急预案·································8 3.义马气化厂煤气系统事故预案·································16 4.全厂火炬系统事故预案·······································21 5.义马气化厂仪表空气中断事故预案·····························25 6.外供水断事故预案···········································32 7.应急预案简要程序(调度)····································33 8.突发事件现场应急救护·······································35 9.中毒应急预案···············································39 10.暴雨应急预案··············································40 11.煤气泄漏应急预案··········································42 12.甲醇泄漏应急预案··········································44 13.液氯泄漏应急预案··········································46 14.氨气(液氨)泄漏应急预案··································48 15.二异丙基醚泄漏应急预案····································49 16.硫化氢泄漏应急预案········································51 17.粗酚泄漏应急预案··········································53 18.煤轻油泄漏应急预案········································55 19.液碱泄漏应急预案··········································56 20.浓硫酸泄漏应急预案········································58 21.食物中毒应急预案··········································59 22.传染病防治预案············································61
1
火灾与爆炸应急预案
1 目的
对火灾、爆炸潜在隐患严格布控,并进行应急准备,对偶发事故积极响应,把事故造成影响和损失减小到最低限度。 2 范围
适用于本厂对由于危险化学品的使用和生产过程中产生的火灾与爆炸事故的应急准备与响应的管理 3 职责
3.1厂长负责火灾、爆炸事故发生时对本厂内所有人员及物质的调配,确保应急预案实施;
3.2生产厂长负责事故现场抢救的指挥,并负责向厂长及有关领导汇报事故或事件的发生、现状与处理情况。安环部、生产部负责协调、调度并在事故处理中执行《消防法》的有关规定;
3.3各部门负责人应服从应急指挥中心的调度和指挥,组织内部人员参加救护和抢险工作。 4 控制要求
4.1危险目标包括重大危险源及其所在区域见Q/YMQG20627-2005重大危险源管理标准的规定。 4.2应急救援组织机构的设置 4.2.1应急救援指挥中心
本厂建立以厂长为总指挥,以生产副厂长为副总指挥,包括其他厂级领导,各部、车间负责人在内的应急救援指挥中心,其职责为:
a)负责应急物资的准备、应急方案的演练和各种危险化学品泄漏、火灾及其他重大事故发生后的抢险指挥和内、外部协调工作;
b)负责配合上级有关部门在救险工作结束后对事故原因进行调查分析并对损失进行评估。
4.2.2应急响应的常设机构为安环部,事故发生初期设在总调度室。 4.2.3应急救援指挥中心下设如下几个工作组: a)通信联络组
成立以生产部部长为组长,以生产部副部长(主管总调)为副组长,由总调度室人员为成员的通信联络组,负责内、外信息的收集、汇报、传递、
2
反馈、救险情况的通报和联络等工作。 b)抢险抢修组:
由设备副厂长为组长,机动部部长及三修车间主任、事故车间主任为副组长,机动部副部长及三修车间的副主任、事故车间副主任及其工作人员为成员的抢险抢修组:负责事故现场的抢险、抢修工作。 c)治安、保卫组
由工会主席为组长,厂办、安环部部长为副组长,厂办、安环部工作人员为成员的治安、保卫组,负责事故现场的治安秩序、交通秩序、设立警戒、指导群众疏散和保护事故现场等工作。 d)消防、救护组:
由安环部部长为组长,消防队长、医务室负责人、事故车间义务消防队长为副组长,消防队专职消防、气防人员、厂办医务人员、义务消防人员等为成员的消防、救护组并负责:在接到事故现场中毒人员及伤员的抢救、医疗救治工作,并将需要住院治疗人员送入指定医院及灭火和进入毒区人员的清洗消毒等工作。 e)物资供应组:
由管理副厂长为组长。厂办、机动部部长为副组长,厂办、机动部副部长及其工作人员为成员的物资供应组,负责事故现场的伤员生活必需品和抢救、抢修物资供应和运输工作。 f)调查处理组:
由生产副厂长为组长,由设备副厂长、工会主席为副组长,工会、财务、厂办、人力资源部、生产部、企管部、机动部、安环部部长及工作人员和事故发生车间的主任、副主任、技术员及当班人员为成员的调查处理组,负责事故原因的调查、分析和处理工作。 g)善后处理组:
由党委书记为组长,工会主席为副组长:纪委、劳人部、财务部、厂办、工会、企管部等有关工作人员为成员的善后处理组,负责事故受害人员家属安抚,受伤人员安置和财产赔偿等善后工作。 4.3应急准备
4.3.1安环部应针对不同的隐患、重要环境因素及潜在的事故岗位配置相应的消防、救护器材和设施,并组织相关人员进行消防和救护知识的培训;
3
4.3.2安环部应定期组织相关人员和义务消防人员按应急预案的要求进行实际操作演练,包括消防器材、消防栓和其他救护设施的使用。对发现的不足之处应加以修正或纠正并作出记录。
4.3.3安环部每月应配合相关部门,对厂里的所有消防设施与电器设备的标识、数量、完整性及有效性进行检查并作出记录。
4.3.4安环部负责健全包括消防、医院及集团公司等有关单位与本厂内部的厂领导、各相关部门在内的通讯联络表,并下发至各相关部门备用。 4.3.5各部门应对本部门内的消防设施与救护器材进行维护保养,严禁私自挪用或使用。
4.3.6储存易燃品的各类仓库要设专人专区管理。严禁带火种进入化学危险品储存区。
4.3.7本厂的新、改、扩建项目,设计时应符合消防与安全、环保的有关规定。
4.3.8应急物资包括:
4.3.8.1消防设备:消防水带、水枪、防火服、隔热服、安全绳、空气呼吸器、手提灭火器、推车灭火器等。
4.3.8.2危险物质泄漏控制设备:防爆工具、堵漏设备、堵漏材料等。 4.3.8.3个体防护设备:防护服、手套、靴子、过滤器、防毒面具、长管面具、氧气呼吸器等。
4.3.8.4通讯联络设备:对讲机、移动电话、电话、传真机等。 4.3.8.5医疗设施:救护车、担架、夹板、氧气、急救箱等。 4.3.8.6照明设施:事故应急灯、手电筒、安全行灯等。 4.3.8.7交通设施:救护车、小轿车、工具车、班车等。 4.3.8.8重型设备:吊车、装载机等。
4.3.8.9相关资料:工艺文件、材料清单、图纸、参考书等。 4.4火灾、爆炸的应急响应 4.4.1警报
总调度室在接到发生紧急情况或火灾报告后,应及时通过电话等方式向全厂通报紧急情况或火灾发生的有关情况,以便厂内各部门和车间人员采取紧急防范措施。 4.4.2事故通报应做到:
4
a)发现情况的目击者应及时通知部门负责人;
b)紧急情况下,任何人员都应就近向总调及值班人员报告事故原由; c)值班人员应立即向厂领导报告,以便采取应急措施(包括启动应急预案)。 4.4.3紧急疏散
当接到发生紧急情况或火灾电话通知后,应急救援指挥中心成员要迅速赶到事故现场,当班的人员要忠于职守,根据总调度室的安排留守一部分人员对工艺系统采取必要的安全措施,其他人员在部门负责人或安环部的指挥下按顺序疏散。当事故现场烟火较大时,人员应尽可能使用防护面罩或湿手巾护面,撤离现场。必要时采取措施进行扑救和人员抢救。疏散时要注意以下事项:a)在允许情况下,无关人员应迅速离开工作岗位; b)按指定路线有序离开,切勿盲目奔跑; c)切勿因收拾个人物品而延误疏散时间; d)离开现场后,未经许可不准重返现场。
厂内的外来人员由负责接待的部门指派专人,以最近的安全路线护送到安全区域。
4.4.4各级人员应做到:
4.4.4.1发现紧急情况的第一目击者要以最快的方式报告部门负责人与总调度室,情况严重时可直接向厂领导报告,同时报警8119。当有人员受伤时,应立即转关医院或拨打“5120”,通知急救中心赶赴现场进行紧急救护。 4.4.4.2当班负责人接到报告后,要记下报告者的单位、姓名、报告时间、地点、现场情况。
4.4.4.3当班负责人在记录的同时,迅速向本厂领导简捷报告,并到指定地点接引消防车。应急救援指挥中心需向政府与消防部门报告时,均要在报告中说明:
a)发生紧急情况或火灾的详细地点; b)发生紧急情况或火灾的简要原因; c)爆炸物、燃烧物的种类; d)情况的严重性; e)人员伤亡情况; f)其他有关事项。
4.4.4.4应急救援指挥中心成员、各部门负责人、义务消防员与相关人员在
5
接到发生重大事故通知后,立即按应急预案的要求赶赴现场,各类人员根据应急救援指挥中心的具体安排,针对具体的情况采取不同的措施进行抢救或灭火、疏散人员和物资、抢救被困人员与伤员等,尽量减少人员与财产的损失。
4.4.4.5厂员工疏散后必须到指定地点集合,等候应急救援指挥中心做出进一步指示。
4.4.4.6未经消防培训的人员不得参加抢救、灭火行动。
4.4.4.7安环部应按照车间提供的当班人数及外来人员资料,检查是否有失踪人员,如发生伤亡或失踪事件时,须登记有关人员的资料,包括:a)姓名、工作岗位、家属联系电话及住址。
b)必要时上报有关部门,如公安局、安全生产监督局、劳动局等请求协助处理。
4.5临近单位爆炸事故
4.5.1当日值班人员要及时报警,同时向安环部负责人报告发生事件的临近单位地点、方向及对我厂的波及情况。
4.5.2当临近单位提出支援时给予人力与物质的援助。
4.5.3安环部负责人接到通知后,立即到达对我厂涉及部分及现场,并组织有关部门进行防范处理,保证我厂生产的正常进行。
4.5.4若爆炸涉及到我厂的设施,并影响到生,应急救援指挥中心要对此提出对策,以尽快恢复生产。 4.6火灾、爆炸事故原因分析及处置
火灾、爆炸事故发生后,厂应急救援指挥中心应组织相关部门配合上级主管单位,对事故原因进行调查、分析,查明原因全按《不符合、纠正和预防措施控制程序》进行整改,并对“应急预案”进行评审与修订,使其不断完善。
4.7厂救援中心主要使用电话号码:
企业内部:厂长、副厂长、各部门、车间领导办公室和住宅电话(见工作联系手册)。
总调度室:行政5625272、5625678、5625789 调度:3 消防队:行政5625141 调度:8119(报警)8132 医疗急救电话:5625120
6
企业外部电话:火警119急救120 义马市政府办公室电话:5832122 义马市安委会办公室电话:5831333
7
义马气化厂电网故障应急预案
根据经济运行模式以及避免电网出现故障导致全厂停车,将全厂供电模式由I/II期电网并运切换为I/II期电网分离运行,当任何一套电网故障,都将影响气化厂的安全生产,一旦遇到恶劣天气或其他可能造成一、二期电网故障的情况时,首先及时调整发电机负荷与厂内用电量相当,尽最大努力保持厂内电网的运行。
当出现厂内电网故障时要及时通知厂总值班和各车间值班人员或相关负责人到厂组织好生产恢复工作,同时将装置停车情况逐级汇报生产部领导(电话:13903985231),负责生产的副厂长(电话:13939805906),负责安全的副厂长(电话:18839822168),厂长(电话13938119699),煤气化公司调度(电话:0371-67985060/67985055)。
供电模式:Ⅱ高气带厂一期负荷,Ⅰ高气带厂二期负荷
运行模式:五炉三机、一大一小两套空分、四台气化炉、净化三系列、甲醇合成三套、甲醇精馏装置和二甲醚装置根据销售和库存情况随时调整。
失电方式共分三种:Ⅰ期电网失电;Ⅱ期电网失电;I、II期电网同时失电。
1. Ⅰ期电网失电预案 1.1 Ⅰ期电网失电恢复步序
1.1.1 Ⅱ高气电网失电将造成Ⅰ期装置失电停车(521#、221#、526#部分设备、1#、2#锅炉,1#、2#发电机,A/B套空分,气化1#、2#、3#气化炉、400#a\\b部分设备、800a、900a,净化500#/550#一期装置及6、8万吨甲醇合成、精馏装置、461#循环水装置)。
1.1.2 Ⅰ期锅炉停车将造成高、低压蒸汽压力降低,立即降3#发电机负荷,维持高压蒸汽及低压蒸汽管网压力,保证C套空分运行。各车间控制室应注意停运装置压力、温度及水位状况,严谨超温、超压、缺水。 1.1.3 立即通知十万吨甲醇合成保温保压停车,气化炉负荷降至14000NM/运行,净化车间迅速开大198阀,以控制系统压力并保证长线压力,400#a/b操作人员保证锅炉给水压力。
1.1.4 551/552停车并迅速切断蒸汽,谨防551/2#K01/2塔超压,51/52中控室主操迅速关闭51/52HCV001,并迅速关闭粗煤气现场界区阀。 1.1.5 甲醇停车导致净煤气压力升高,通知气化控制室降气化炉负荷,净
8
化立即关闭中压氮气调节阀及前后截止阀,净煤气直接送入长线。 1.1.6甲醇精馏装置、二甲醚装置、900#a停车,并迅速关闭各蒸汽界区阀。 1.1.7通知电气车间迅速查明失电原因,恢复供电。
1.1.8调度室先通知601#送电并启动灰水泵,再依次通知电调211#、521#、461#送电并开车。211#首先启动P07泵,以保证脱盐水供应;521#首先启动低压生产泵以保证生产用水和消防用水;461#本着先启泵后启风机、先热电后工艺的原则进行启动设备,因一期主变负荷小(1#/2#主变只能各带到5500),1#/2#发电机没有并网发电,不必要的设备尽量不得启动。 1.1.9调度室人员通知电调一期锅炉、备煤一期送电,以保证一期锅炉开车。 1.1.10调度室通知第三台气化炉通氧恢复。
1.1.11调度室人员通知A套空分(B套空分)蒸汽暖管并通知电调送电,待461#工艺循环水压力也稳定后,调度室人员通知A套空分(B套空分)压缩机冲转,热电1#或2#发电机组冲转、定速后并网。 1.1.12调度室通知第四台气化炉空气恢复。
1.1.13调度人员待一期锅炉送电正常后,通知热电车间开第三台锅炉并网后通知净化552#、51#开车。空分车间2#氧压机启动、
1.1.14热电车间开第三台并网后,迅速退出煤气,调度人员通知第四台锅炉点火、551#、52#开车;六、八万吨甲醇合成压缩机各启一台进行升温、热电一期第二台发电机组冲转、定速后并网,1#氧压机启动。
1.1.15第四台锅炉并网,51#/552开车,51#净煤气合格后并入净煤气管网,甲醇合成加负荷,通知2#氧压机开车,压力合格后并入中压氮管网。 1.1.16第五台锅炉点火、并网,3#发电机开始加负荷。 1.2 Ⅰ期停电送电批次:
1.2.1 35KV外线受电后,首先完成301#站内1#、2#主变受电工作。 1.2.2 301#站内受电完成后,依次为201#、308#、381#、382#、309#开闭所受电。
1.2.3 201#高压及308#变电所受电完成后,首先恢复1#、2#锅炉给水泵和601#1#、2#、3#冲灰水循环泵送电工作,以保证锅炉水位,避免发生锅炉干锅及气化炉灰渣沟现象。其次为1#、2#汽轮机盘车及油泵用电,再次为1#、2#锅炉送电,为恢复开车做准备,最后为201#其他高、低压用户及308#其他低压用户。
9
1.2.4 381#受电后,首先完成303#、304#低压、中压锅炉水水泵送电工作,其次为302#680#仪表空压站和1#、2#、3#气化炉送电,准备恢复开车。再次为空分汽机、压缩机油泵及1#氮压机、2#氧压机、1#氧压机,最后为381#其它高、低压用户及303#、304#、305#其他低压用户。
1.2.5 382#受电完成后,首先完成306#、307#变电所受电和521#P05、P07及221#4#反渗透、P05A、P05B、P05C、P07A、P07C、 461#1#、2#、3#、4#、5#、6#、7#循环水泵、甲醇1#、2#压缩机及305#变电所和精馏系统低压电用户电。最后为461#循环水风机、382#其他高压用户及305#、306#、307#变电所其它低压电用户。
1.2.6 309#受电完成后,应抓紧恢复526#J101A、B、C风机和SBRA池、B池、C池及氧化塘、C9池、污水回用等所有用电设备。 2. Ⅱ期电网失电预案: 2.1Ⅱ期电网失电恢复步序
2.1.1Ⅱ期电网失电将造成Ⅱ期全部装置因失电停车(热电4#、5#锅炉,3#发电机,C套空分,气化4#、5#气化炉,净化53#系列、553#/554#,260#循环水系统,十万吨合成及精馏、650#a\\b、521#/221#部分设备失电停运)。 2.1.2 调度立即通知气化炉负荷降至6000Nm3/h运行,400a保证锅炉用水。各车间控制室应注意停运装置压力、温度及水位状况,严谨超温、超压、缺水。
2.1.3 迅速将1#/2#发电机负荷带满,通知净化车间迅速关闭中压氮气调节阀及手动阀,打开3#净煤气阀,43#关闭去53#粗煤气阀。热电车间密切注意高压蒸汽及低压蒸汽管网压力,六/八万吨甲醇合成保温保压停车。 2.1.4通知空分车间立即启动2#低压氮压机补充全厂仪表空气,液氧柱塞泵冷却。
2.1.5 通知电气车间迅速查明失电原因,消除缺陷,恢复Ⅰ高气供电。 2.1.6 Ⅱ期恢复供电后,521#/221#停运设备投运,260#循环水系统开车,液氧柱塞泵启动并外送氧气,4#、5#锅炉扬火开车,C套空分装置开车。 一台循环流化床锅炉并网后二期净化装置开车。
2.1.7 气化车间根据气化炉停车时工况选择一台气化炉切氧,另外一台气化炉待C套空分装置空气并网后通空气点火,尽快供出粗煤气;十万吨甲醇启动一台压缩机。
10
2.1.8 53#净化装置接受粗煤气,调整合格后供甲醇车间,全线恢复并向长线送气。
2.1.9 另一台锅炉并网后,热电3#发电机开车。C套空分氧气及氮气正常外供后,主工艺系统提负荷,甲醇提负荷。 2.2 Ⅱ期停电送电批次:
2.2.1 35KV外线受电后,首先完成301#站内3#、4#主变受电工作。 2.2.2 301#站内受电完成后,依次为223#开闭所、3#锅炉6KV、201#3#变送电,3#汽机盘车装置、汽机油泵302#3#变、611#变、260#循环水、净化Ⅱ期、十万吨甲醇、309#3#变受电。
2.2.3 223#开闭所受电完成后,首先恢复Ⅱ期锅炉1#、2#锅炉给水泵和611#变1#、2#、3#反渗透、P01A、P01B、P01C、P07B、P07D及304#3#变受电和400b#P01A、P01C送电工作,以保证脱盐水、锅炉水供应,避免锅炉缺水、干锅。其次为4#、5#及3#锅炉送电,为恢复开车做准备,再次为303#3#变的4#、5#气化炉及800#b、900#b低压用户送电。最后为223#开闭所其他高压、低压用户和308#3#变和611#变低压用户。
2.2.4 302#3#变受电后,首先恢复1#液氧柱塞泵及C套汽机油泵用电,其次为302#Ⅱ期其他低压用户。
2.2.5 260#循环水受电后,首先完成260#3#、4#、5#、6#、7#循环水泵送电开车工作,其次为260#1#、2#、循环水泵,最后为其它循环水泵及风机。 2.2.6 260#循环水受电完成后立即为净化Ⅱ期P03A、P05A、P06A、送电,准备开车,其次为304#3#及其低压电用户电。最后为P03R、P05R、P06R送电备用。
2.2.7 甲醇5#/6#/7#压缩机及油泵送电完成后立即完成十万吨甲醇变及其低压用户送电工作。
2.2.8 309#3#变受电完成后,抓紧恢复526#J101D、E风机及SBRD池、E池、及其它Ⅱ期所有用电设备。
3. I、II期电网均故障时,按全厂停电事故预案处理。 3.1 全厂停电恢复步序
3.1.1通知各车间控制室应注意停运装置压力、温度及水位状况,严谨超温、超压、缺水。气化炉两台保温保压,另两台气化炉泄压(全厂失电后调度及时联系气化车间要求关闭400b#脱盐水阀门,防止221#二期脱盐水外供
11
管线出现蒸汽或冷凝液窜入管线引起水击)。
3.1.2 Ⅰ、Ⅱ期电网失电将造成Ⅰ、Ⅱ期全部装置因失电停车。通知电气车间迅速查明失电原因,消除缺陷,恢复供电。供电原则:先二期后一期的原则,空分除外
3.1.3 调度通知电气461#、521#、400a/b、221#、680#、2#低压氮压机送电(2#氮压机不用时应处于压仪表空气状态,保证提前开车时间)并开车,保证仪表空气、锅炉给水供应。
3.1.4调度通知3#、5#锅炉上水、开车,260#、601#开车。
3.1.5 待一台锅炉并网后,一小套空分开车、启液氧柱塞泵、两台气化炉切氧其余气化炉泄压做好通空气运行准备、1#发电机冲转后并网。 3.1.6净化53#/553#开车,气化炉并网后,气化炉逐步加负荷维持在8000Nm3/h运行,53#引气(500#在没有低压氮气的情况下开车,正常情况500#装置没有低压氮气是无法建立循环,由于K03塔一段和K05塔一段压力需要充低压氮气保正压力建立再生循环,紧急停车状态下,500#操作人员先关闭CP011截止阀保持K03塔一段的压力保证系统及时开车)调度室请示煤气公司调度同意后净煤气通过198#阀门进入长线。
3.1.7 在第二台锅炉并网后通知C套空分、554#开车、2#发电机冲转后并网。
3.1.8 在调度接到小套空分装置空气并网后,通知第三台气化炉通空气点火, 1#氧压机开车,仪表空气并网后停2#低压氮压机,盲板倒通至N2系统,启1#、2#低压氮压机,526#开车。
3.1.9 第三锅炉并网后通知551#、52#、900#a、900#b开车,3#发电机开始暖管冲转,1#发电机投抽气,6/8/10万吨甲醇合成各启一台压缩机进行系统升温,根据长线压力调度室决定甲醇合成负荷,投锅炉焚烧甲醇废水。 3.1.10 第四台锅炉并网后,51#/552开车,二甲醚装置、8万吨精馏开车,51#净煤气合格后并入净煤气管网,甲醇合成加负荷,通知1#、2#中压氮压机开车,压力合格后并入中压氮管网,900#a、900#b开车,根据城市煤气热值启2#氧压机。
3.1.11第五台锅炉并网后,3#发电机开始加负荷。 3.2 全厂停电送电批次
3.2.1电气车间组织好35KV受电。
12
3.2.2 35KV受电后,在301#站内组织好1#、2#、3#、4#主变的受电工作。 3.2.3 四台主变受电后,立即组织381#、382#、223#、201#的受电工作,受电完成后优先461#循环水泵、2#低压氮压机、锅炉给水泵送电。 3.2.4
(1)303#、304#受电,低压锅炉水泵送电,启低压锅炉给水泵向锅炉送水,启锅炉给水泵防止锅炉干锅。(400#b23101B、D泵为一期电,其它为二期电)中压锅炉给水泵送电。
(2)307#、306#受电,受电后521#P05、P06、P07(其中P05、 P07为一期电,P06为二期电)受电,泵启动后向全厂供低压生产消防水。 (3)302#受电后,680#空压机送电,2#低压氮压机送电。 (4)221#脱盐水泵送电(P07A、C为一期电,P07B、D为二期电) 3.2.5 在301#站内完成260#各循环水泵受电,二期5#锅炉高压电机受电恢复开车。
3.2.6 671#C送低压电开车,4#锅炉高压电机受电进行开车,601#1#3#泵送电后启泵,308#受电恢复备煤用电。
3.2.7 空分柱塞液氧泵受电,两台气化炉送电恢复开车,553#、554#、53#(高低压泵送电)恢复开车向长线送净煤气。 3.2.8 461#循环水泵受电开车建立一期循环水管网。
3.2.9 1#、3#锅炉高低压电机受电恢复开车,1#、2#、3#发电机受电逐步进行开车,一期空分受电。
3.2.10 1#低压氮,1#、2#氧压机受电1#、2#中压氮压机受电,其余气化炉受电开车,同时净化一期受电开车。
3.2.11 309#受电;在301#站内完成309#3#变受电,526#开车。 3.2.12 621#压缩机送电开车。
3.2.13 305#受电,303#未送电的装置送电:900#、甲醇精馏、650#相继受电开车。
3.2.14 甲醇压缩机受电开车。 3.2.15 260#、461#循环水风机送电。 4.高压用电设备甩负荷批次
我厂一期装置全厂用电负荷最高为25000KW,1#、2#发电机满发为24000KW,1#、2#主变额定视在功率为16000KVA,额定有功功率共为12800KW
13
(16000*0.8),按主变的可靠运行容量能带12160KW(12800*0.95)负荷。因此外线事故状态下,没有甩掉1#、2#发电机前,一期装置应减负荷为12840KW (25000-12160)。 4.1一、二期电网所带装置及设备 4.1.1一期电网所带装置及设备
热电车间1#、2#锅炉;1#、2#发电机,601#、602#泵房 空分车间A、B套;680#;活塞液氧泵A。
气化车间400a#;800#一期、900#一期、1#、2#、3#气化炉;400b#23101B、D
净化车间51#、52#、551#、552#;681# 甲醇车间6万吨、8万吨
给排水车间221#P07A、C;521#P05、P07;461#、691#、526# 4.1.2二期电网所带装置及设备
热电车间3#锅炉、4#锅炉、5#锅炉;3#发电机。 空分车间C套、活塞液氧泵B。
气化车间4#、5#气化炉;800#二期;900#二期;400b#23101A、C 。 净化车间53#、553#、554# 甲醇车间10万吨、两套甲醚
给排水车间526#D、E池、230#、521P06、P08、P09;221#P07B、D。 4.2 一期供电系统高压用电设备甩负荷批次:
第一批:1#氧压机,621#1#、2#、3#压缩机,甲醇闪蒸汽压缩机;(约3000KW)
第二批:461#T01、T02、T03、T04、T07冷却塔风机;甲醇1#、2#压缩机,2#氧压机、1#低压氮压机、1#、2#中压氮压机;(约6000KW)
第三批:461#T05、T06冷却塔风机、剩余运行甲醇压缩机;(约1500KW) 第四批:51# P03A/R泵、52# P03A/R泵,461#P01泵;(约1000KW) 4.3 二期供电系统高压用电设备甩负荷批次:
第一批:260#T02、T03冷却塔风机,甲醇6#压缩机;(约1500KW) 第二批:260#T03、T04、T06冷却塔风机;甲醇7#、8#压缩机;(约1500KW)
第三批:53#P03A/R、P05A/R、P06A/R泵,260#P01泵(约1200KW)
14
第四批:260#P02、P03泵,4#锅炉一次送风机、二次送风机、引风机;(约3000KW)
5. 在出现事故停车后必须在最短的时间内将城市煤气供出,才能确保煤气供应不中断。各生产车间在缺水、断煤、失电等特殊情况下,尽快恢复生产装置运行,对造成紧急停车的故障排除后各主要生产装置恢复时间要求 5.1
热电车间
煤粉炉:引风机启动至锅炉并汽 1.5 h; 流化床锅炉:引风机启动至锅炉并汽 1 h; 5.2
空分车间
汽轮机冲转至膨胀机启动2.5 h; 膨胀机启动至氧气外送1.5 h; 膨胀机启动至氮气外送2 h; 5.3
气化车间
气化炉空气点火至切氧 1h,切氧至并气1.5h; 气化炉直接切氧至并气 0.5h; 5.4
净化车间:
气化炉并气时必须接气; 接受粗煤气至净煤气外送 0.5h。
15
义马气化厂煤气系统事故预案
煤气系统(加压气化、煤气冷却、低温甲醇洗、氨吸收制冷、甲醇合成等煤气生产装置以及粗煤气、净煤气、驰放气、城市煤气、火炬气等煤气管网)是我厂的主生产系统,煤气系统的正确操作是保证安全生产的基础。为了避免在煤气系统出现故障时的不合理操作使事故扩大,尽量减少事故损失,特制订《煤气系统事故预案》,望相关单位和人员认真学习执行。
1 事故状态下的调整原则
1.1 各车间管辖的煤气系统发生故障时发现人要迅速向调度室及班长、车间汇报,汇报内容为故障位置、故障现象、是否需要停车、隔离、卸压等情况,调度室根据汇报的故障情况迅速判断甩负荷程度,并立即通知相关车间煤气系统发生故障,命令其迅速甩负荷并采取应对措施,各车间操作工可根据自己系统压力情况降负荷或停车,确保系统不超压,避免出现不知情而询问导致影响处理时间。
1.2 甩负荷时要果断、要狠、要准,一步甩到位,必要时可紧急停车,各车间执行命令要迅速,不许多问原因。甩负荷时中压氮要同步调节。
1.3 停车时优先考虑保压停车,以缩短恢复时间,隔离、卸压时要严密监控气化炉压力、净煤气压力、300#压力、火炬总管压力以及气化开车火炬的通过量等,必要时将调节阀打手动控制,严禁出现超压现象。
1.4 甲醇减负荷时直接调整压缩机负荷,必要时空载运行,保证压缩机入口净煤气压力。降负荷后系统压差减小,粗煤气压力可由51/52CH001调整。合成系统向300#卸压时要缓慢,并通过调度室密切关注300#压力变化。
1.5 气化大幅度甩负荷时,要保证锅炉对空排汽阀能自动迅速打开稳定高压蒸汽压力(压力联锁要确保投用),锅炉负荷调整时优先考虑煤粉炉并投气枪稳燃,必要时可先紧急停运一台锅炉(若两台流化床锅炉运行时,优先停运一台流化床锅炉)。
1.6 暂时不受故障影响的其它系列维持原有的运行状态,等系统稳定后再考虑调整负荷。
2 气化装置故障 2.1 部分气化炉停车
2.1.1 停车气化炉暂时保压,迅速调整甲醇压缩机负荷,必要时空载
16
或停运压缩机,维持净煤气压力稳定。
2.1.2 系统稳定后安排运行气化炉逐步加负荷至最高,后续净化和甲醇逐步加负荷。
2.1.3 查明原因,停车气化炉恢复开车或卸压,卸压速率要严格按规程控制。
2.2 气化厂房内出现较大的煤气泄漏
2.2.1 所有气化炉紧急停车,空分车间氧压机和液氧泵紧急停运、其余设备维持正常运行,净化、甲醇迅速保温保压停车,热电车间紧急停运一台或两台锅炉维持高压蒸汽压力稳定,并调整抽汽维持低压蒸汽压力。
2.2.2 迅速关闭400#入口粗煤气阀门及200#相关阀门,隔离泄漏点。 2.2.3 通过200#火炬泄压,要考虑火炬承受能力,注意卸压速率、充氮和自身防护。
2.3 气化炉厂房外粗煤气总管(包括400#)出现大的煤气泄漏 2.3.1与泄漏点相对应系列的1#2#3#或4#5#气化炉紧急停车,气化炉若需卸压,则要控制好卸压速率,严禁火炬超压,同时51#52#或53#紧急保压停车,迅速调整甲醇压缩机负荷,使其空载或停运,维持净煤气压力稳定。
2.3.2 隔离200#粗煤气总管联通阀。
2.3.3 通过400#CP051将泄漏管线卸压后隔离400#对应的系列。 3 低温甲醇洗装置故障
3.1 51/52一个系列(或两个系列)入口粗煤气调节阀关闭 3.1.1 根据500#其它一个或两个系列的设计总能力判断出应该保留几台气化炉运行,其它气化炉紧急停车。
3.1.2 甲醇压缩机迅速减负荷,使其空载或停运,维持净煤气压力稳定。
3.1.3 净化现场迅速关闭故障系列粗、净煤气大阀。
3.1.4 通过41/42/43CP051向1300#火炬卸压,通过200#火炬卸压。 3.1.5 注意500#运行系列的负荷,待系统稳定后才能逐步加负荷。 3.1.6 查明原因,恢复开车,逐步加负荷。
3.2 500#任何一个(或两个)系列甲醇洗涤泵大面积跳车使粗煤气无法净化
17
按照3.1处理
3.3 500#三个系列同时出现甲醇洗涤泵大面积跳车
此种情况出现的最大原因是全厂停电,其它原因造成的可能性不大,但确实出现时按以下方法处理:
3.3.1所有气化炉立即紧急停车。空分车间氧压机和液氧泵紧急停运、其余设备维持正常运行,热电车间紧急停运一台或两台锅炉维持高压蒸汽压力稳定,并调整抽汽维持低压蒸汽压力。
3.3.2净化立即控制室关闭入口粗煤气阀和中压氮气调节阀,同时现场人员迅速关闭净煤气大阀、粗煤气大阀及中压氮手动阀。
3.3.3甲醇根据净煤气压力迅速减压缩机新鲜气至零负荷,合成装置保温保压停车。
3.4 净煤气管网出现较大煤气泄漏
3.4.1所有气化炉立即紧急停车。空分车间氧压机和液氧泵紧急停运、其余设备维持正常运行,热电车间紧急停运一台或两台锅炉维持高压蒸汽压力稳定,并调整抽汽维持低压蒸汽压力。甲醇合成装置紧急保温保压停车。
3.4.2净化控制室立即关闭入口粗煤气阀和中压氮气调节阀,现场人员迅速关闭粗煤气大阀、净煤气大阀及中压氮手动阀,500#紧急停车。
3.4.3甲醇车间立即关闭脱硫塔进口,与净化车间配合隔离泄露点。 3.4.4 净煤气管网泄漏点隔离后,如确认仍能向长线送气,可恢复开车。
4 氨吸收制冷装置故障
4.1 551#/552#一个或两个系列停车
按照51#52#突然停车处理,处理方法同3.1 4.2 553#/554#中一个系列停车 4.2.1 53#减负荷调整;
4.2.2 气化炉手动按调度指令立即降负荷,必要时一台气化炉停车。 4.2.3甲醇压缩机迅速减负荷,必要时空载或停运,维持净煤气压力稳定。
4.3 553#/554#两个系列停车
按照53#事故停车处理,处理方法同3.1。
18
5 甲醇合成装置故障 5.1 一台甲醇压缩机跳车
5.1.1 气化炉立即紧急手动降5000Nm3/h的氧负荷。
5.1.2 调整好粗煤气压力和净煤气压力,组织备用压缩机开车后加负荷。
5.2 两台或两台以上甲醇压缩机同时跳车
此种情况出现的机会不多,但确实出现时按以下方法处理: 5.2.1 迅速判断出应该减多少净煤气和粗煤气、气化炉应该保留多少氧负荷,多余的氧量一次性先减10000Nm3/h,最好是一台气化炉迅速降负荷同时另一台气化炉紧急停车,然后再减至需保留的氧量。空分维持运行,热电按照调整原则维持蒸汽压力。
5.2.2 适当调整其它运行压缩机的新鲜气负荷,维持净煤气压力稳定。停运的合成装置保温保压。
5.2.3 调整净化粗煤气入口阀51/52CH001维持粗煤气压力,组织备用压缩机开车后加负荷。
5.3 甲醇合成装置煤气管线泄漏
受泄漏影响的一套或多套装置的新鲜气负荷即为多余的净煤气
量,按照5.2的方法减负荷调整,泄漏装置停车、隔离卸压、处理,若其它装置具备增加气量的条件则可缓慢增加气量。
6 城市煤气管线泄漏
气化炉、低温甲醇洗、甲醇合成必须立即紧急保压停车,保留两台台或三台锅炉保证发电机和一套空分运行外供低压氮气和中压氮气,300#停止配送中压氮,待净化、甲醇、及首站将城市煤气管线隔离后再充少量中压氮。 各有关车间:
为了真正能够将《煤气系统事故预案》落到实处,避免在煤气系统出现故障时因不合理操作导致事故扩大,尽量减少事故损失,需各车间作好以下日常性工作。
1 长输管线作为事故状态下净煤气排放的备用管线,操作工必须严格控制300#煤气压力,300#煤气压力最高不得超过2.0MPa,一般情况下维持在1.8MPa-2.0MPa之间,调度室和净化车间的主要领导必须随时掌握。
19
2 净化车间牵头、仪表车间配合、其它职能部门支持,将火炬总管压力信号引入控制室画面并作报警信号,随时掌握火炬总管压力,此项工作3月15日前必须完成。火炬管线的日常维护由净化车间负责,每天在气化办公楼前对火炬管线排液一次并作好记录(排放人员、排放量多少等),火炬外管线每周排液一次并作好记录。
3 各车间与仪表车间配合尽快对以下调节阀进行调校检修,保证完好可用、动作灵活、前后手动阀打开、投入自动调节。净煤气压力由调度室根据生产需要下令给有关车间控制,各调节阀的设定值由所在车间负责,各单位领导负责检查落实情况,具体如下:
50CP001 设定值为实际运行时需要控制的净煤气压力; 51/52/53CP007 设定值比实际运行时需要控制的净煤气压力的设定值
高50KPa;
53CP198 目前设定值暂定为比51/52/53CP007的设定值
高50KPa,当需用此调节阀向长输管线配净煤气 时,设定值改为与50CP001一致;
30CP004 设定值为2200KPa;
41/42/43CP051 设定值比实际运行时的粗煤气压力高50KPa; 200#CP035、HV034 设定值比实际运行时的粗煤气压力高50KPa; 甲醇压缩机旁路调节阀PIC0101 根据所需的净煤气压力随时调
整设定值;
氧气管网放空阀20CH004 正常情况下保持联锁自动开阀投用,
仪表车间确保该阀的严密性,空分车 间检查确认拆除阀前盲板,若需停运 氧气管网时等机会,但要提前准备好 材料备件。
氧压机、中低压氮压机、液氧泵、液氮泵的回流阀和放空阀等由空分车间牵头、仪表车间配合校验维护。
锅炉对空排汽阀由热电车间牵头、仪表车间配合校验维护,确保联锁投用。
4.各车间每周对以上各阀进行校验维护一次并作好记录。
20
7.2.4 SBR排水时若出现仪表空气中断,继续完成排水操作后,直接关闭P123出水手动阀。
7.2.5 SBR进气时若出现仪表空气中断,打开该池进气旁路阀直到该池进气完毕。
7.2.6 T110/T111运行过程中若出现仪表空气中断,停运过滤开P129旁路阀。
7.2.7 T110/T111反洗过程中若出现仪表空气中断,停止反洗,停运反洗泵。 7.2.8 若出现仪表空气中断,吹气式液位计无指示,加强现场检测做好液位平衡避免池子溢流,罐冒顶现象发生。
7.2.9 仪表空气恢复后要求岗位人员再次确认各气动阀门状态,立即将上述非正常操作恢复,同时报车间值班领导。
31
外供水中断事故预案
1.1 生产用水紧缺带来的隐患:直接影响到气化厂的运行负荷,严重时生产系统需大幅度甩负荷,导致供应城市煤气量不足,部分城市煤气用户的用气量受到限制,造成不良的社会影响。
1.2总调接外供水中断报警电话,迅速问清中断持续时间、原因;若外供水在两小时以内能够恢复,则维持正常生产运行;若外供水超过两小时后才能够恢复,立即通知供应部(电话:5625052)协调外供水量,同时汇报厂部值班人员、生产部领导(13903985231),负责生产的厂领导(电话:13839805906),煤气化公司调度(电话:037167985060)并按外供水中断预案执行。
1.3通知给排水车间进行以下操作:
1.3.1 控制循环水浓缩倍数在3.5以上,并加大杀菌量,减少补水量,节约用水。
1.3.2在保证上水温度的前提下,尽可能减少风机的运行台数,减少蒸发损失的水量,杜绝单纯依靠大排大补降低循环水温度的方法。
1.3.3 减少521#脉冲池和虹吸滤池排泥和反洗次数,降低排泥损失水量。 1.3.4保持 522#蓄水罐的液位在2.5米以上,循环水停止排水,相应减少循环水补充水量。
1.4 若供水中断时间内,522#蓄水罐的液位不能维持气化厂现有负荷生产,则减少发电机负荷,减少循环水补充水。
1.5 请示煤气化公司总调(电话:037167985060),工艺系统降至最低负荷,减少工艺生产用水量,但保证长线用气量。
1.6若供水中断时间内,522#蓄水罐的液位不能维持气化厂最低负荷生产,请示煤气化公司总调(电话:037167985060),减少城市煤气供应量,维持气化厂工艺生产运行不中断。
32
应急预案简要程序(调度)
1. 火灾或爆炸事故:
1.1 总调接报警电话,问清事故时间、地点、原因、爆炸(燃烧) 物的种类、情况严重性、人员伤亡情况;
1.2 通知消防队(8119)出警,煤气、液氨、二甲醚出动水罐车,甲醇、油类等出动泡沫车;
1.3 通知安环部、生产部及事故单位主任到现场指挥事故处理;
1.4 根据事故程度,通知保卫封锁通往事故现场各条道路及厂大门,禁止闲杂人员及车辆进入;
1.5 若有人受伤,拨打120急救电话,立即转送医院; 1.6根据事故程度汇报厂领导及上级调度。 2. 煤气(二甲醚、液氨、液氯)泄露事故:
2.1 总调接报警电话,问清事故时间、地点、原因、泄露物的种类、情况严重性、人员中毒情况;
2.2通知泄露点下风向的单位注意预防中毒,闲杂人员疏散并停止一切动火作业;
2.3 通知消防队(8119)出警出动水罐车在现场上风向监控;通知气防站(8132)现场监控;
2.4根据事故程度,通知保卫封锁通往事故现场及下风向的各条道路及厂大门,禁止闲杂人员及车辆进入;
2.5通知安环部、生产部及事故单位主任到现场指挥事故处理; 2.6 若有人中毒,拨打120急救电话,立即转送医院; 2.7根据事故程度汇报厂领导及上级调度。 3.甲醇、油类泄露事故:
3.1 总调接报警电话,问清事故时间、地点、原因、泄露物的种类、情况严重性、人员中毒情况;
3.2通知事故单位注意泄露物的流向,不得流入雨水管网;现场闲杂人员疏散并停止一切动火作业;
33
3.3 若泄漏物流入污水管网,通知526#生活污水切进事故池;
3.4 通知消防队(8119)出警,出动泡沫罐车在现场上风向监控;通知气防站(8132)现场监控,预防中毒;
3.5根据事故程度,通知保卫封锁通往事故现场各条道路及厂大门,禁止闲杂人员及车辆进入;
3.6通知安环部、生产部及事故单位主任到现场指挥事故处理; 3.7 若有人中毒,拨打120急救电话,立即转送医院; 3.8根据事故程度汇报厂领导及上级调度。
34
突发事件现场应急救护
1目的
当突然发生意外事故,使受伤职工掌握必要的医学常识及处理措施,尽量减轻或避免意外带来的各种伤害。 2范围
适用于本厂范围内山洪、雷电击等自然灾害及意外火灾、爆炸、触电等现场应急救护。 3职责
本厂厂长为安全第一责任人,负责突发事件应急救护全面指挥。 管理者代表负责环境管理体系运行及突发事件救护的协调和组织。 责任部门/车间领导负责现场应急救护的实施。 4现场应急救护 4.1应急要求
4.1.1当事故发生,当事人应尽快拨打3/8119/5120电话和本单位领导电话。 4.1.2采取有效措施遏制事态发展或蔓延,同时拨打总调度室电话。 4.1.3值班中心立即拨打电话告知厂长和管理者代表。 4.1.4责任单位领导到达现场后,立即进行现场营救。
4.1.5医务人员到达现场后,应在本厂领导统一指挥下进行救援,必须与消防人员及其它救援人员密切合作。
4.1.6现场营救、救援准则及方法:自救互救。 4.2应急处理
4.2.1事故发生后,营救出的伤员应进行自我检测:一看,看一看身体各部位有无出血,伤口和畸形。二感觉,活动一下肢体是否可正常活动。 4.2.2伤情互检
4.2.2.1伤员或救护人员应尽快进行伤情互检。
4.2.2.2用“喂,您怎么样了?”询问伤员,观察伤员意识是否清楚。 4.2.2.3测量脉搏是否正常,大于120次/分是重症表现。 4.2.2.4观察呼吸次数及困难程度。
4.2.2.5摸或触及皮肤,判断其体温(腋窝)是否正常。
4.2.2.6看瞳孔是否等大等圆,对光反射灵敏性,不等大或放大显示已处危险状态。
35
4.2.3现场救护人员应在医护人员指导下对伤员分类处置同时对外呼救。 4.2.3.1人工呼吸,包扎止血,胸外心脏按压,创伤救护最好在医护人员指导下或由医护人员进行。 4.2.3.2重大意外灾害的正确呼救
凡遇意外途害事故严重创伤,在进行现场救护同时,拨打5120及5678呼救,呼救时应该:
a)详细说明意外事故发生时间、地点、事故性质。 b)伤情及人数。 c)需哪方面救护。
d)呼救人姓名、单位、所用呼救电话号码。
4.2.3.3现场人员应进行相互安抚、鼓励等待救护车的到来。 4.3几种主要灾害发生的现场救护: 4.3.1触电的脱险与急救
4.3.1.1立即使伤员脱离电源,关闭电闸,用绝缘物体(木棒、竹杆)挑起伤员身上电线、电器。 4.3.1.2立即检查伤员
a)当心脏停止跳动,应立即在其心前区用拳叩击两次,然后触摸颈动脉刘否恢复博动。
b)不恢复心跳者,立即原地进行人工心肺复苏术(人工呼吸),直至医生到达。
4.3.1.3对恢复心跳者,应安静,千万不得搬动、移动,以防心室颤动再次发生,等医生达到后,按医生嘱咐办理。
4.3.1.4对电灼伤的创伤表面,仅用干纱布覆盖,不要涂抹任何药膏。 4.3.1.5当伤员被高输电线击倒后,千万不可冒然接近,防止强大电磁场及电流同时使抢救人员触电身亡/。只有将高压线(电器)关闭或移开10米远后,方可接近伤员进行救护。 4.3.2溺水的脱险及救护
4.3.2.1抢救人员快速游向伤员,尽量从其背后接近,并用手托起他,对正在水面挣扎者抢救时,谨防其紧抱救护员造成双方溺水。
4.3.2.2上岸后,简单地清除伤员口中泥土、异物,对呼吸停止者进行口对口的人工呼吸。
36
4.3.2.3上岸后伤员心脏停止跳动,立即进行人工心肺复苏术。
4.3.2.4抢救中应注意为伤员保暖,复温,盖上棉衣、被褥等,防止体温下降。
4.3.2.5当伤员恢复呼吸并正常后,将其置于侧卧位,拍打其背部,帮助其将气管和肺内残留的少量水咯出。
4.3.2.6对溺水人员,虽心跳和呼吸均消失,也不要放弃抢救,应呼叫救护车,溺水3小时后被抢救成功的不在少数。 4.3.3爆炸伤员的急救
4.3.3.1瞬间爆炸可释放出巨大能量,伤员伤情与作用于其身体冲击波大小及作用部位和时间长短有很大差异。
4.3.3.2一般伤员表面看上去完好,但可能内伤严重。 4.3.3.3抢救措施:
a)爆炸发生时,应迅速卧倒,要大减轻伤害。 b)立即让伤员处于半卧,并避免一切体力活动。 c)保持气道通畅,有条件者输氧气。
d)有大量血性泡沫涌出时应在氧气过滤瓶内加50%酒精同时输入。 e)伤后不可喝水、饮食。
f)用清水洗清皮肤及烧伤表面,但不可贴任何膏药。 g)固定可疑有骨折的伤肢,包扎伤口及进行有效止血。
h)快速请医生前来协助抢救或快速送医院,防止早期生命平稳,数小时或数日后出现严重症状。 4.3.4交通事故伤员的现场抢救
4.3.4.1厂内拨打5051/5120或8152请求援助。
4.3.4.2发生火灾或意外时应关闭引擎,关闭电源,封好油箱,转移易燃易爆品。
4.3.4.3组织清醒伤员展开自检、互检并救护。 4.3.4.4专人保护肇事现场,严防破坏现场。
4.3.4.5派专人看管受伤人员的行李物品,警方来到可移交警方及相关单位。
4.3.4.6原地抢救伤员,包扎止血,固定伤肢。
4.3.4.7分清轻重缓急,重点抢救重伤员,选择最近医院就医。
37
4.3.4.8用救护车专人护送伤员,寒冷冬季注意保暖。 4.3.4.9不宜采用一般车辆转运伤员。
4.3.4.10护送伤员必要时应使伤员平卧,并托起重伤肢体,减少振动。 4.3.4.11急救车条件完善,尽可能用急护车,可以在极短时间内有效地救护伤员。
4.3.5火灾现场伤员脱险与救护
4.3.5.1火灾现场救援,应注意灭火及营救火灾现场的伤员,尤其是要想到被浓烟烈火围困在室内的人员。
4.3.5.2一旦发生烈火,应首先拨打119及本厂值班室电话,以最快方式告诉本厂领导。
4.3.5.3现场人员立即进行人员疏散。
4.3.5.4用自来水扑灭伤员身上烈火,千万不要乱跑。 4.3.5.5抢救伤员或物资应注意自我防护: a)用防毒面具或湿毛巾捂住口鼻。 b)穿石棉服或用水打湿衣服。 c)选择好进入及返回路线。
d)腰系石棉绳或铁丝,一旦发生意外可用其将抢救人员拉上来。 e)用最低姿式出入,高度越高烟气、毒气越大。 4.3.5.6伤员及被困人员自救与脱险
a)火灾发生时,千万不呆夺门而逃,以防浓烟及高温气流使人窒息而亡。 b)用湿毛巾捂住鼻口或头顶打湿棉被,选择最近通道逃离现场。 c)高层楼房中可用水打湿毛巾、衣物,捂住口鼻,躲在打开窗户下或在顺风口或暂烧不到地方等待救援。
d)当衣服燃着火时,应用水浇灭或躺在地上慢滚压灭或脱去被燃衣物。 e)被烧伤人员不可接近化学品,以免造成化学灼伤。 f)烧伤时不要大量饮水,防止发生致命的水中毒。
g)对烧伤创面不要贴任何膏药和药水,不可用胶布粘贴在皮肤上,也不要将水疱弄破,听从医生处置。 4.3.5.7伤员现场救护
a)伤员抬邮火场,用水龙头扑灭其身上烈火,冲洗应20分钟。 b)剪去身上衣服,千万不可硬脱伤员身上衣服,谨防衣服粘连皮肤,而造
38
成新伤,换上新被褥,为其保暖。
c)被浓烟窒息病人,放在通风处,专人观察其变化。 d)对呼吸停止人员应立即进行人工呼吸。 e)对化学灼伤人员用清水或生理盐水冲洗。
f)对有声嘶,气憋,气道阻塞人员,马上请医生手术,防止窒息死亡。 g)烧伤人员不得大量饮水,可用含盐饮料,但不超过500毫升。 h)抬动伤员应将其置于布单中,担架搬抬不可用力持握受伤部位,防止大片皮肤撕脱。
i)最近选择医院就医、抢救,待病情稳定后可送专业性烧伤医院就治。 4.3.6高空坠落伤员脱险与救护
高空坠落伤员主要易发生多发性骨折,颈、腰椎骨折,内出血等症状,现场救护人员应及时拨打5120与5678呼救,并根据医生要求搬运抢救伤员。注意在专业医生未到前严禁移动伤员。
中毒应急预案
1目的
对危险化学品严密控制,防止外泄而引起中毒事故的发生,对中毒事件应急准备要充分,并积极响应。 2范围
适用于本厂由于危险化学品的使用和生产过程中中毒事故的应急准备与响应的管理。
3组织机构及职能分工
3.1厂部成立化学毒物急性中毒抢救领导组。由厂长担任组长,成员有:工会、安全、环保、医疗卫生、保卫等部门负责人,其职责是:
3.1.1当接到中毒事故报告后,应立即赶赴现场指导抢救工作,同时向上级有关部门报告。
3.1.2负责组织事故现场的处理、抢救人员和物资的调配,以及伤员运输等现场指挥工作。
3.1.3据事故发展,决定是否请求有关单位支援,并负责中毒事故的善后处理。
39
3.2气体防护站昼夜值班,其职责是:
3.2.1负责发生事故现场的中毒者或伤员的抢救、搜寻与运送。 3.2.2负责对中毒人员的救送、人工呼吸或强制自动输氧等。
3.2.3负责对各车间事故柜内和个人防护器材、药剂的检查与维修,防止因误用器材或失效的药剂而酿成意外事故。 4控制要求
4.1发生中毒事故时应将中毒者迅速转移到安全和空气新鲜及温度适合的地方,立即进行抢救,在抢救的同时联系气体防护站(电话:8120)和厂办医各室(电话:5120),在事故情况较严重时厂办医务室应及时联系医院。 4.2立即解除妨碍呼吸动作的衣服等服饰,对中毒者施行人工呼吸,进行抢救。
4.3有毒物污染的衣物等,应将其全部脱去,并用温水洗身然后换上清洁干燥的衣服,要保持体温。
4.4若中毒者面色有青紫、缺氧时,应及时给氧气或混有定量空气的氧气混全体。
4.5若中毒者呈呼吸停止或呼吸不规则时,应施行人工呼吸,但造成肺水肿者例外。必要时可利用人工输氧。
4.6应随时检查心脏、脉搏与血压和反射情况等。有必要时,应注射强心剂(但触电者除外);如呈神经不安和痉挛时,应给予镇静剂。
4.7由食道进入的毒物,应立即给予呕吐剂(酸性碳酸钠的碱性溶液)或洗胃;中毒时间相当长的,就应灌肠,静脉注入生理食盐(氯化钠)水和葡萄糖溶液。
4.8对于各种不同物质造成的中毒事故参见相应的应急预案。 4.9在对中毒者进行急救后应将其送入医院进行护理和检查。
暴雨应急预案
1目的
对暴雨提前防范,保证全厂安全渡过汛期,实现长周期生产运行。 2范围
适用于全厂及各车间汛期防暴雨,抗洪水特殊恶劣天气下生产的管理。 3职责
40
正在阅读:
义马气化厂应急总预案06-05
公证书02-12
2002年诺贝尔化学奖获得者访谈02-12
关于饭店用语--点菜的情景会话02-12
论中小企业购地建厂与租赁厂房之利弊06-19
参观浙江大学02-12
开学典礼发言稿开学典礼教师代表致辞09-25
- 多层物业服务方案
- (审判实务)习惯法与少数民族地区民间纠纷解决问题(孙 潋)
- 人教版新课标六年级下册语文全册教案
- 词语打卡
- photoshop实习报告
- 钢结构设计原理综合测试2
- 2014年期末练习题
- 高中数学中的逆向思维解题方法探讨
- 名师原创 全国通用2014-2015学年高二寒假作业 政治(一)Word版
- 北航《建筑结构检测鉴定与加固》在线作业三
- XX县卫生监督所工程建设项目可行性研究报告
- 小学四年级观察作文经典评语
- 浅谈110KV变电站电气一次设计-程泉焱(1)
- 安全员考试题库
- 国家电网公司变电运维管理规定(试行)
- 义务教育课程标准稿征求意见提纲
- 教学秘书面试技巧
- 钢结构工程施工组织设计
- 水利工程概论论文
- 09届九年级数学第四次模拟试卷
- 义马
- 气化
- 预案
- 应急
- 2.紫薇809项目市场定位报告(HP)
- 黑龙江省哈三中四校联考2011届高三一模考试(数学文)
- 销售工作的理解
- 2019届高三数学上学期第一次教学质量检查考试试题 理(含解析)
- 如何看待“普世价值”观
- 本科心理学试卷库
- ps重点难点剖析
- 四年级下册劳动与技术教学计划
- 第十章《数据的收集整理与描述》测试卷
- 日语初级文法
- 00015自考英语(二)教材课后练习题完整版
- 2017年宜城市中考适应性考试题
- 恒温控制电路的设计
- 一年级数学下册永威教案第五单元(第1课时)
- 政治生活1.1.1人民民主专政:本质是人民当家作主导学案
- 马克思主义经典作家社会矛盾思想的发展历程
- 小区给水改造施工组织设计
- 全国电子商务三创赛省赛优秀作品
- 北京市高中生物会考说明题 - 图文
- 水利06级《水力学》试卷B