ESSENCE OF PMBOK & PMP EXAM
ESSENCE OF PMBOK & PMP EXAM PMBOK及PMP考试精要(考试串讲教材)
PROJECT MANAGEMENT KNOWLEDGE AREAS项目管理知识体系 ........................................................................................... 2 PROJECT LIFE CYCLE / PROJECT MANAGEMENT PROCESS GROUPS项目生命周期及过程组 ..................................... 10 SCOPE范围管理 ......................................................................................................................................................................................... 10 HUMAN RESOURCE人力资源管理 ....................................................................................................................................................... 11 COMMUNICATIONS沟通管理 ................................................................................................................................................................ 14 TIME时间管理 ............................................................................................................................................................................................. 16 COST成本管理 ............................................................................................................................................................................................ 17 RISK风险管理 .............................................................................................................................................................................................. 20 QUALITY质量管理 ..................................................................................................................................................................................... 22 PROCUREMENT采购管理 ....................................................................................................................................................................... 22 INTEGRATION整体管理 ........................................................................................................................................................................... 19 PROFESSIONAL RESPONSIBILITIES职业道德.................................................................................................................................. 19 POSSIBLE EXAM QUESTIONS考点 .................................................................................................................................................... 20
1
ESSENCE OF PMBOK & PMP EXAM
PROJECT MANAGEMENT KNOWLEDGE AREAS项目管理知识体系
Knowledge Areas知识体系 INTEGRATION整体 制定项目章程 Develop Project Charter Primary Inputs输入 1.合同(如果适用) Contract(When applicable) 2.项目工作说明书 Project statement of work 3.事业环境因素 Enterprise environmental factors 4.组织过程资产 Organizational process assets 1.项目章程 Project charter 2.项目工作说明书 Project statement of work 3.事业环境因素 Enterprise environmental factors 4.组织过程资产 Organizational process assets 1.项目初步范围说明书 Preliminary project scope statement 2.项目管理各过程 Project management processes 3.事业环境因素 Enterprise environmental factors 4.组织过程生产 Organizational process assets 1.项目管理计划 Progece management plan 2.批准的纠正措施 Approved corrective actions 3.批准的预防措施 Approved preventive actions 4.批准的变更申请 Approved change requests 5.批准的缺陷补救 Approved defect repair 6.确认的缺陷补救 Validated defect repair 7.行政收尾程序 Administrative closure procedure Tools & Techniques工具及技术 1.项目选择方法 Project selection methods 2.项目管理方法论 Project management methodology 3.项目管理信息系统 Project management information system 4.专家判断 Expert judgment 1.项目管理方法系 Project management methodology 2.项目管理信息系统 Project management information system 3.专家判断 Expert judgment 1.项目管理方法系 Project management methodology 2.项目管理信息系统 Project management information system 3.专家判断 Expert judgment Primary Outputs输出 1.项目章程 Project charter 制定项目初步范围说明书 1.项目初步范围说明书 Preliminary project scope statement 制定项目管理计划 Develop Project management Plan 1.项目管理计划 Progece management plan 指导与管理项目执行 Direct and Manage Project Execution 1.项目管理方法系 Project management methodology 2.项目管理信息系统 Project management information system 1.可交付成果 Deliverables 2.请求的变更 Requested changes 3.实施的变更请求 Implementde change requests 4.实施的纠正措施 Implementde corrective actions 5.实施的预防措施 Implementde preventive actions 6.实施的缺陷补救 Implementde defect repair 7.工作绩效信息 Work performance information 1.推荐的纠正措施 Recommended corrective action 2.推荐的预防措施 Recommended preventive action 3.预测 Forecasts 4.推荐的缺陷补救 Recommended defect repair 5.请求的变更 Requested changes 1.批准的变更申请 Approved change requests 2.否决的变更请求 Rejected change requests 3.项目管理计划(更新) Project management plan(updates) 4.项目范围说明书(更新) Project scope statement(updates) 5.批准的纠正措施 Approved corrective actions 6.批准的预防措施 Approved preventive actions 7.批准的缺陷补救 Approved defect repair 8.确认的缺陷补救 Validated defect repair 9.可交付成果 Deliverables 1.行政收尾程序 Administrative closure procedure 2.合同收尾程序 Contract closure procedure 3.最终产品,服务或成果 Final product,service or result 4.组织过程资产(更新) 监控项目工作 Monitor and Control Project Work 1.项目管理计划 Progece management plan 2. 工作绩效信息 Work performance information 3.否决的变更请求 Rejected change requests 1.项目管理方法系 Project management methodology 2.项目管理信息系统 Project management information system 3.实现价值技术 Eamed value technique(EVT) 4.专家判断 Expert judgment 整体变更控制 Integrated Change Control 1.项目管理计划 Progece management plan 2.请求的变更 Requested changes 3.工作绩效信息 Work performance information 4.推荐的纠正措施 Recommended corrective action 5.推荐的预防措施 Recommended preventive action 6.推荐的缺陷补救 Recommended defect repair 7.可交付成果 Deliverables 1.项目管理方法系 Project management methodology 2.项目管理信息系统 Project management information system 3.专家判断 Expert judgment 项目收尾 Close Project 1.项目管理计划 Progece management plan 2.合同文件 Contract documentation 3.事业环境因素 Enterprise environmental factors 4.组织过程资产 Organizational process assets 5.工作绩效信息 Work performance 1.项目管理方法系 Project management methodology 2.项目管理信息系统 Project management information system 3.专家判断 Expert judgment 2
ESSENCE OF PMBOK & PMP EXAM
information 6.可交付成果 Deliverables Organizational process assets(updates) SCOPE范围 范围规划 1.事业环境因素 Enterprise environmental factors 2.组织过程资产 Organizational process assets 3.项目章程 Project charter 4.项目初步范围说明书 Preliminary project scope statement 5.项目管理计划 Project management plan 1.组织过程资产 Organizational process assets 2.项目章程 Project charter 3.项目初步范围说明书 Preliminary project scope statement 4.项目范围管理计划 Project scope management plan 5.批准的变更申请 Approved change requests 1.组织过程资产 Organizational process assets 2.项目范围说明书 Project scope statement 3.项目范围管理计划 Project scope management plan 4.批准的变更申请 Approved change requests 1.专家判断 Expert judgment 2.样板,表格与标准 Templates,forms,standards 1.项目范围管理计划 Project scope management plan 范围定义 1.产品分析 Product analysis 2.其他方案识别 Alternatives identification 3.专家判断 Expert judgment 4.利害关系者分析 Stakeholder analysis 1.项目范围说明书Project scope statement 2.请求的变更 Requested changes 3.项目范围管理计划 Project scope management plan 制作工作分解结构 Create WBS 1.工作分解结构模板 Work breakdown structure templates 2.分解 Decomposition 1.项目范围说明书(更新) Project scope statement(updates)_ 2.工作分解结构 Work breakdown structure 3.工作分解结构词汇表 WBS dictionary 4.范围基准 Scope baseline 5.项目范围管理计划(更新) Project scope management plan(updates) 6.请求的变更 Requested changes 1.验收的可交付成果 Accepted deliverables 2.请求的变更 Requested changes 3. 推荐的纠正措施 Recommended corrective actions 1.项目范围说明书(更新) Project scope statement(updates) 2.工作分解结构(更新) Work breakdown structure(updates) 3.工作分解结构词汇表(更新) WBS dictionary(updates) 4.范围基准(更新) Scope baseline(updates) 5.请求的变更 Requested changes 6.推荐的纠正措施 Recommended corrective action 7.组织过程资产(更新) Organizational process assets(updates) 8.项目管理计划(更新) Project management plan(updates) Scope Verification范围核实 1.项目范围说明书Project scope statement 2.工作分解结构词汇表 WBS dictionary 3.项目范围管理计划 Project scope management plan 4.可交付成果 Deliverables 1.检查 Inspection 范围控制 Scope Control 1.项目范围说明书Project scope statement 2.工作分解结构 Work breakdown structure 3.工作分解结构词汇表 WBS dictionary 4.项目范围管理计划 Project scope management plan 5.绩效报告 Performance reports 6.批准的变更申请 Approved change requests 7.工作绩效信息 Work performance information 1.变更控制系统 Change control system 2.偏差分析 Variance analysis 3.补充规划 Replanning 4.配置管理系统 Configuration management system TIME进度 活动定义 Activity Definition 1.事业环境因素 Enterprise environmental factors 2.组织过程资产 Organizational process assets 3.项目范围说明书 Project scope statement 4.工作分解结构 Work breakdown structure 5.工作分解结构词汇表 WBS clictionary 6.项目管理计划 Progece management plan 1.项目范围说明书 Project scope statament 2.活动清单 Activity list 3.活动属性 Activity attributes 4.里程碑清单 Milestons list 1.分解 Decomposition 2.样板 Templates 3.滚动式规划 Rolling wave planning 4.专家判断 Expert judgment 5.规划组成部分 Planning componet 1.活动清单Activity list 2.活动属性 Activity attributes 3.里程碑清单 Milestone list 4.请求的变更 Requested changes 活动排序 Activity Sequencing 1.紧前关系绘图法(PDM) Precedence Diagramming Method(PDM) 2.箭线绘图法(ADM) Arrow Diagramming Method(ADM) 1.项目进度网络图 Project schedule network diagrams 2.活动清单(更新) Activity list (updates) 3
ESSENCE OF PMBOK & PMP EXAM
5.批准的变更请求 Approved change requesta 3.进度网络样板 Schedule network tempiates 4.确定依赖关系 Dependency determination 5.利用时间提前量与滞后量 Applying leads and lags 1.专家判断 Expert judgment 2.多方案分析 Alternatives analysis 3.出版的估算数据 Published estimating data 4.项目管理软件 Project management sortware 5.自上而下的估算 Bottom estimating 3.活动属性(更新) Activity attributes(updates) 4.请求的变更 Requesaed changes 1.活动资源要求 Activity resource requirements 2.活动属性(更新) Activity attributes(updates) 3.资源分解结构 Resource breakdown structure 4.资源日历(更新)Resource calendars 5.请求的变更 Requested changes 1.活动持续时间估算 Activity duration estimates 2.活动属性 Activity attributes(updates) 活动资源估算Activity Resource Estimating 1.事业环境因素Enterprise environmental factors 2.组织过程资产 Organizational process assets 3.活动清单Activity list 4.活动属性Activity attributes 5.资源可利用情况 Resouce availability 6.项目管理计划Project management l 活动持续时间估算Activity Duration Estimating 1.事业环境因素Enterprise environmental factors 2.组织过程资产Organizational process assets 3.项目范围说明书 Project scops statement 4.活动清单 Activity list 5.活动属性 Activity attributes 6.活动资源要求 Activity resource requirements 7.资源日历 Resource calendars 8.项目管理计划 Project management plan ●风险登记册 Risk register ●活动费用估算 Activity cost estimates 1.组织过程资产 Organizational process assets 2.项目范围说明书Project scope statement 3.活动清单 Activity list 4.活动属性 Activity attributes 5.项目进度网络图 Project schedule network diagrams 6.活动资源要求 Activity resource requirements 7.资源日历 Resource calendars 8.活动持续时间估算 Activity duration estimates 9.项目管理计划 Project management plan ●风险登记册 Risk register 1.专家判断 Expert judgment 2.类比估算 Analogous estimating 3.参数估算 Parametric estimating 4.三点估算 Three-point estimates 5.后备分析 Reserve analysis 制定进度表Schedule Development 1.进度网络分析 Schedule network analysisi 2.关键路线法 Critical path method 3.进度压缩 Schsdule compression 4.假设情景分析What-if scenario analysis 5.资源平衡 Resource leveling 6.关键链法 Critical chain method 7.项目管理软件 Project management software 8.应用日历 Applying calendars 9.调整时间提前滞后量 Adjusting leads and lags 10.进度模型 Schedule model 进度控制 Schedule Control 1.进度管理计划 schedule management plan 2.进度基准 Schedule baseline 3.绩效报告 Performance reports 4.批准的变更要求 Approved change requests 1.进度报告 Progress reporting 2.进度变更控制系统 Schedule change control system 3.绩效衡量 Performance measurement 4.项目管理软件 Project management software 5.偏差分析 Variance analysisi 6.进度比较横道图 Schedule comparison bar chars 1.项目进度表 Project schedule 2.进度模型数据 Schedule model data 3.进度基准 Schedule baseline 4.资源要求 Resource requirements(updates) 5.活动属性(更新) Activity attributes(updates) 6.项目日历(更新)Project calendar 7.请求的变更 Requesaed changes 8.项目管理计划(更新) Project management plan(updates) ●进度管理计划(更新) Schedule management plan(updates) 1. 进度模型数据(更新) Schedule model data(updates) 2. 进度基准(更新) Schedule baseline(updates) 3. 绩效衡量 Performance measurements 4. 请求的变更 Requesaed changes 5.推荐的纠正措施Recommended corrective action 6.组织过程资产(更新) Organizational process assets(updates) 7.活动清单(更新) Activity list(updates) 8.活动属性(更新) Activity attributes(updates) 9.项目管理计划(更新) Project management plan(updates) COST费用 费用估算Cost Estimating 1.事业环境因素 Enterprise environmental factors 2.组织过程资产 Organizational process assets 3.项目范围说明书Project scope statement 4. 工作分解结构 Work breakdown structure 1.类比估算 Analogous estimating 2.确定资源费率 Determine resource cost rates 3.自上而下估算 Bottom-up estimating 4.参数估算 Parametric estimating 5.项目管理软件 Project management 1.活动费用估算 Activity cost estimates 2.活动费用估算支持细节 Activity cost estimate supporting detall 3.请求的变更 Requested 4
ESSENCE OF PMBOK & PMP EXAM
5.工作分解结构词汇表 WBS dictionary 6.项目管理计划 Progece management plan ●进度管理计划 Schedule management plan ●人员配备管理计划Staffing management plan ●风险登记册 Risk registor 1.项目范围说明书Project scope statement 2.工作分解结构 Work breakdown structure 3.工作分解结构词汇表 WBS dictionary 4.活动费用估算 Activity cost estimates 5.活动费用估算支持细节 Activity cost estimate supporting detall 6.项目进度 Project schedule 7.资源日历 Resource calendars 8.合同 Contract 9.费用管理计划 Cost management plan 1.费用基准 Cost baseline 2.项目资金要求 Project funding requirements 3.绩效报告 Performance reports 4.工作绩效信息 Work performance information 5.批准的变更申请 Approved change requests 6.项目管理计划 Project management plan software 6.供货商投标分析 Vendor bid analysis 7.准备金分析 Reserve analysis 8.质量成本 Cost of quality changes 4.费用管理计划(更新) Cost management plan(updates) 费用预算 Cost Budgeting 1.费用汇总 Cost aggregation 2.储备基金分析 Reserve analysis 3.参数估算 Parametric esrimating 4.资金限制平衡 Funding limit reconciliation 1.费用基准 Cost baseline 2.项目资金要求 Project funding requirements 3.项目管理计划(更新) Project management plan(updates) 4.请求的变更 Requested changes 费用控制Cost Control 1.费用变更控制系统 Cost change control system 2.绩效衡量分析 Performance measurements analysis 3.预测 Forecasting 4.项目绩效审核 Project performance reviews 5.项目管理软件 Project management software 6.偏差管理 Variance management 1.费用估算(更新) Cost estimates(update) 2.费用基准(更新) Cost baseline(update) 3.绩效衡量 Performance measurements 4.预测完工 5.请求的变更 Requested changes 6.推荐的纠正措施 Recommended corrective action 7.组织过程资产(更新) Organizational process assets(updates) 8.项目管理计划(更新) Project management plan(updates) RISK风险 风险管理规划 Risk Management Planning 1.事业环境因素 Enterprise environmental factors 2.组织过程资产 Organizational process assets 3.项目范围说明书 Project scope statement 4.项目管理计划 Progece management plan 1.事业环境因素 Enterprise environmental factors 2.组织过程生产 Organizational process assets 3.项目范围说明书 Project scope statement 4. 风险管理计划 Risk Management Plan 5. 项目管理计划 Project management plan 1.组织过程生产 Organizational process assets 2.项目范围说明书 Project scope statement 3. 风险管理计划 Risk Management Plan 4. 风险登记册 Risk register 1.规则会议和分析 Planning meeting and analysis 1.风险管理计划 Risk Management Plan 风险识别Risk Identification 1.文件审查 Documentation reviews 2.信息搜索技术 Information gathering techniques 3.核对表分析 Checklist analysis 4.假设分析 Assumptions analysis 5.图解技术 Diagiamming techniques 1.风险概率与影响评估 Risk probability and impact assessment 2.概率和影响矩阵 Probablity and impact matrix 3.风险数据质量评估 Risk data quality assessment 4.风险分类 Risk categorization 5.风险紧迫性评估 Risk urgency assessment 1.数据收集和表示技术 Data gathering and representation techniques 2.定量风险分析和模型技术 Quantitative risk analysis and modeling techniques 1.风险登记册 Risk register Qualitative Risk Analysisi风险定性分析 1.风险登记册(更新) Risk register(updates) 定量风险分析 Quantitative Risk Analysis 1.组织过程生产 Organizational process assets 2.项目范围说明书 Project scope statement 3. 风险管理计划 Risk Management Plan 4. 风险登记册 Risk register 5. 项目管理计划 Project management plan ●项目进度管理计划 Project schedule management plan ●项目费用管理计划 Project cost management plan 1.风险管理计划 Risk Management Plan 2.风险登记册 Risk register 1.风险登记册(更新) Risk register(updates) 风险应对规划 Risk Response Planning 1.消极风险或威胁的应对策略 Strategies for negative risk or threats 2.积极风险或机会的应对策略 Strategies for 1.风险登记册(更新) Risk register(updates) 2.项目管理计划(更新) Project 5
ESSENCE OF PMBOK & PMP EXAM
positive risk or opportunities 3.威胁或机会的应对策略 Strategies for both threats and opprtunities 4.应急应对策略 Contingent response strategy 1.风险再评估 Risk reassessment 2.风险审计 Risk audits 3.变差和趋势分析 Variance and trend analysis 4.技术绩效分析 Technical performance measurement 5.储备金分析Reserve analysis 6.状态审查会 Status meetings management plan(updates) 3.与风险有关的合同协议 Risk-related contractual agreements 风险监控 Risk Monitoring and Control 1.风险管理计划 Risk Management Plan 2.风险登记册 Risk register 3.批准的变更申请 Approved change requests 4.工作绩效信息 Work performance information 5.绩效报告 Performance reports 1.风险登记册(更新) Risk register(updates) 2.请求的变更 Requested changes 3.推荐的纠正措施 Recommended corrective action 4.推荐的预防措施 Recommended preventive action 5.组织过程资产(更新) Organizational process assets(updates) 6.项目管理计划(更新) Project management plan(updates) QUALITY质量 质量规划 Quality Planning 1.事业环境因素 Enterprise environmental factors 2.组织过程资产 Organizational process assets 3.项目范围说明书Project scope statement 4.项目管理计划 Progece management plan 1.成本效益分析 Cost-benefit analysis 2.基准对照 Benchmarking 3.试验设计 Design of experiments 5.质量成本(COQ) Cost of quality (COQ) 6.其他质量规划工具 Additional quality planning tools 1.质量管理计划 Quality management plan 2.质量测量指标 Quality metrics 3.质量核对表 Quality checklists 4.过程改进计划 Process improvement plan 5.质量基准 Quality baseline 6.项目管理计划(更新) Project management plan(updates) 1.请求的变更 Requested changes 2.推荐的纠正措施 Recommended corrective action 3.组织过程资产(更新) Organizational process assets(updates) 4.项目管理计划(更新) Project management plan(updates) 实施质量保证Perform Quality Assurance 1.质量管理计划 Quality management plan 2.质量测量指标 Quality metrics 3.过程改进计划 Process improvement plan 4.工作绩效信息 Work performance information 5.批准的变更申请 Approved change requests 6.质量控制衡量 Quality control measurnments 7.实施的变更请求 Implementde change requests 8.实施的纠正措施 Implementde corrective actions 9.实施的缺陷补救 Implementde defect repair 10.实施的预防措施 Implementde preventive actions 1.质量管理计划 Quality management plan 2.质量测量指标 Quality metrics 3.质量核对表 Quality checklists 4.组织过程资产 Organizational process assets 5.工作绩效信息 Work performance information 6.批准的变更请求 Approved change requests 7.可交付成果 Deliverables 1.质量规划工具与技术 Quality planning tools and techniques 2.质量审计 Quality audits 3.过程分析 Process analysis 4.质量控制工具与技术 Quality control tools and techniques 实施质量监控 Perform Quality Control 1.因果图 Cause and effect diagram 2.控制图 Control charts 3.流程图 Flowcharting 4.直方图 Histogram 5.帕雷托图 Pareto chart 6.趋势图 Run chart 7.散点图 Scatter diagram 8,统计抽样 Statistical sampling 9.检查 Inspection 10.缺陷补救审查 Defect repair review 1.质量控制衡量 Quality control measurnments 2.确认的缺陷补救 Validated defect repair 3.质量基准(更新) Quality baseline(updates) 4.推荐的纠正措施 Recommended corrective action 5.推荐的预防措施 Recommended preventive action 6.请求的变更 Requested changes 7.推荐的缺陷补救 Recommended defect repair 8.组织过程资产 Organizational process assets 9.确认的可交付成果 Validated deliverables 10.项目管理计划(更新) Project management plan(updates) HUMAN RESOURCE人力资源 人力资源规划 1.事业环境因素 Enterprise environmental factors 2.组织过程资产 Organizational process assets 1.组织机构图和岗位描述 Organization charts and position descriptions 2.交际 Networking 3.组织理论 Organization theory 1.角色与职责 roles and responsibilities 2.项目组织图 Projece organization chares 6
ESSENCE OF PMBOK & PMP EXAM
3.项目管理计划 Progece management plan ●活动资源需求 Activity resource requirements 项目团队组建 Acquire Project Team 1.事业环境因素 Enterprise environmental factors 2.组织过程资产 Organizational process assets 3.角色与职责 roles and responsibilities 4.项目组织图 Projece organization chares 5.人员配备管理计划 Staffinf management plan 招聘惯例 1.项目人员分派 Project staff assignments 2.人员配备管理计划 Staffinf management plan 3.资源可利用情况 Resource availability 3.人员配备管理计划 Staffinf management plan 1.项目人员分派到位 Project staff assignments 2.资源可利用情况 Resource availability 3.人员配备管理计划(更新) Staffinf management plan(updates) 1.预分派 Pre-assignment 2.谈判 Negotiation 3.招募 Acquisition 4.虚拟团队Virtual teams 项目团队建设 Develop Project Team 1.通用管理技能 General management skills 2.培训 Training 3.团队建设活动 Team-building activities 4.规则 Ground rules 5.集中办公 Co-location 6.奖励与表彰 Recognition and rewards 1.观察与交谈 Observation and conversation 2.项目绩效评估 Project performance appraisals 3.冲突管理 Conflict management 4.问题登记薄 Lssue log 1.团队绩效评估 Team performance assessment 项目团队管理 Manage Project Team 1.组织过程资产 Organizational process assets 2.项目人员分派 Project staff assignments 3.角色与职责 roles and responsibilities 4.项目组织图 Projece organization chares 5.人员配备管理计划 Staffinf management plan 6.团队绩效考核 Team performance assessment 7.工作绩效信息 Work performance information 8.绩效报告 Performance reports 1.请求的变更 Requested changes 2.推荐的纠正措施 Recommended corrective action 3.推荐的预防措施 Recommended preventive action 4.组织过程资产(更新) Organizational process assets(updates) 5.项目管理计划(更新) Project management plan(updates) COMMUNICATIONS沟通 Communications Planning沟通规划 1.事业环境因素 Enterprise environmental factors 2.组织过程生产 Organizational process assets 3.项目范围说明书Project scope statement 4.项目管理计划 Progece management plan ● 制约因素 Constraints ● 假设 Assumptions 1. 沟通管理计划 Communications management plan 1.沟通需求分析 Communications requirements analysls 2.沟通技术 Communications technology 1.沟通管理计划 Communications management plan Information Distribution信息发布 Performance Reporting绩效报告 利害关系者管理 Manage Stakeholders 1.工作绩效信息 Work performance information 2.绩效衡量 Performance measurements 3.完工预测 Forecasted completion 4.质量控制衡量 Quality control measurnments 5.项目管理计划 Project management plan ●绩效衡量分析 Performance measurements baseline 6.批准的变更申请 Approved change requests 7.可交付成果 Deliverables 1.沟通管理计划 Communications management plan 2. 组织过程资产 Organizational process assets 1.沟通技能 Communications skills 2.信息收集和检索系统 Information gathering and retrieval system 3.信息发布系统 Information distribution methods 4.经验教训总结过程 Lessons learned process 1.信息演示工具 Information presentation tools 2.绩效信息收集和汇总 Performance information gathering and compilation 3.状态审查会 Status review meetings 4.工时汇报系统Time reporting systems 5.费用汇报系统Cost reporting systems 1. 组织过程生产(更新) Organizational process assets(updates) 2. 请求的变更 Requested changes 1.绩效报告 Performance reports 2.预测 Forecasts 3.请求的变更 Requested changes 4.推荐的纠正措施 Recommended corrective action 5.组织过程资产(更新) Organizational process assets(updates) 1.沟通方法 Communications methods 2.问题登记薄 lssue logs 1.问题得以解决Resolved issues 2.批准的变更申请 Approved change requests 3.批准的纠正措施 Approved corrective action 4.组织过程资产(更新) Organizational process assets(updates) 5.项目管理计划(更新) Project management plan(updates) 7
ESSENCE OF PMBOK & PMP EXAM PROCUREMENT采购 采购规划 Plan Purchases and Acquisitions 1.事业环境因素 Enterprise environmental factors 2.组织过程生产 Organizational process assets 3.项目范围说明书Project scope statement 4.工作分解结构 Work breakdown structure 5.工作分解结构词汇表 WBS clictionary 6.项目管理计划 Progece management plan ●风险登记册 Risk register ●与风险有关的合同协议 Risk-related contractual agreements ●资源要求 Resource requirements ●项目进度计划 Project schedule ●活动费用估算 Activity cost estimate ●费用基准 Cost baseline 1.采购管理计划 Procurement management plan 2.合同工作说明书 Contract statement of work 3.自制或外购决策 Maker-or-buy changes 4.项目管理计划 Project management plan ●风险登记册 Risk register ●与风险有关的合同协议 Risk-related contractual agreements ●资源要求 Resource requirements ●项目进度计划 Project schedule ●活动费用估算 Activity cost estimate ●费用基准 Cost baseline 1.组织过程资产 Organizational process assets 2.采购管理计划 Procurement management plan 3.采购文件 Procurement documents 1.组织过程资产 Organizational process assets 2.采购管理计划 Procurement management plan 3.评估标准 Evaluation criteria 4.采购文件包 Procurement document package 5.建议书 Proposals 6.合格卖方清单 Qualified sellers list 7.项目管理计划 Project management plan ●风险登记册 Risk register ●与风险有关的合同协议 Risk-related contractual agreements 1.合同 Contract 2.合同管理计划 Contract management plan 3.选中的卖方 Selected sellers 4.绩效报告 Performance reports 5.批准的变更申请 Approved change requests 6.工作绩效信息 Work performance information 1.自制或外购分析 Make-or-buy analysls 2.专家判断 Expert judgment 3.合同类型 Contract types 1.采购管理计划 Procurement management plan 2.合同工作说明书 Contract statement of work 3.自制或外购决策 Maker-or-buy changes 4.请求的变更 Requested changes 发包规划 Plan Contracting 1.标准表格 Standard forms 2.专家判断 Expert Judgment 1.采购文件 Procurement documents 2.评估标准 Evaluation criteria 3.合同工作说明书(更新) Contract statement of work(updates) 询价Request Seller Responses 1.招标人会议 Bldder conferences 2.刊登广告 Advertising 3.制定合格卖方清单 Develop qualifid sellers list 1.加权系统 Weighting system 2.独立估算 Independent estimates 3.筛选系统 Screening system 4.合同谈判 negotiation 5.卖方评级系统 Seller rating systens 6.专家判断 Expert judgment 7.建议书评估技术 Proposal evaluation techniques 卖方选择Select Sellers 1.合格卖方清单 Qualified sellers list 2.采购文件包 Procurement document package 3.建议书 Proposals 1.选中的卖方 Selected sellers 2.合同 Contract 3.合同管理计划 Contract management plan 4.资源可利用情况 Resource availability 5.采购管理计划(更新) Procurement management plan(updates) 6.请求的变更 Requested changes 合同管理 Contract Administration 1.合同变更控制系统 Contract change control system 2.买方进行的绩效审核 Buyer-conducted per-formance review 3.检验和审计 Inspections and audits 4.绩效报告 Performance reporting 5.支付系统 Payment system 6.索赔管理 Claims administration 7.合同档案管理系统 Records management system 8.信息技术 Information technology 1.合同文件 Contract documentation 2.请求的变更 Requested changes 3.推荐的纠正措施 Recommended corrective action 4.组织过程资产(更新) Organizational process assets(updates) 5.项目管理计划(更新) Project management plan(updates) ●采购管理计划 Procurement management plan ●合同管理计划 Contract management plan 1.合同收尾Contract closures 2.组织过程资产(更新) Organizational process assets(updates) 合同收尾 Contract Closure 1.采购管理计划 Procurement management plan 2.合同管理计划 Contract management plan 3.合同文件 Contract documentation 4.合同收尾程序 Contract closure procedure 1.采购审计 Procurement audits 2.合同档案管理系统 Records management system 8
ESSENCE OF PMBOK & PMP EXAM
PROJECT LIFE CYCLE / PROJECT MANAGEMENT PROCESS GROUPS项目生命周期和项目管理过程组
INITIATION启动 (Concept) Select project选择项目 PLANNING计划 (Development) Create Scope Statement & scope management plan创建范围说明和范围管理计划 Determine project team组织计划编制 EXECUTION 执行 (Implementation) Execute the project plan执行项目计划 Manage project progress管理项目进程 Complete work packages or tasks完成工作包或任务 Distribute information信息发布 Quality assurance质量保证 Team development团队发展 Progress meetings状态评审 CONTROL控制 CLOSE-OUT结束 (Termination) (Finishing) Procurement audits采购审计 Product verification产品确认 Determine project objectives确定项目目标 Determine high level deliverables, time & cost estimates确定主要可交付物、时间及成本估计 Determine high level constraints & assumptions 高级别的限制和约束 Determine business need 确定业务需求 Develop product description Define responsibilities of the project manager确定项目管理者责任 Determine high-level resource requirements 制定高水平资源需求 Finalize project charter 制订项目章程 Create WBS创建工作分解结构 Integrated change control综合变更控制 Project performance reporting项目绩效报告 Performance reporting绩效报告 Formal acceptance正式接收 Finalize the team & create resource management plan人员获取及创建资源管理计划 Create WBS dictionary创建工作分解结构字典 Create Network Diagram创建网络图 Scope change control范围变更控制 Quality control质量控制 Risk monitoring & control风险监控 Schedule control计划控制 Cost control成本控制 Scope verification范围确认 Manage by exception to the project plan对项目进行中的突发事件进行管理 Ensure compliance with plans确保按计划进行 Reassess plans补充计划 Take corrective action纠正措施 Lessons learned经验教训 Update records更新记录 Archive records文档记录 Release resources人员遣散 Estimate time & costs估算时间及成本 Determine Critical path确定关键路径 Develop Schedule & schedule management plan制定进度及进度管理计划 Develop Budget制定预算 Create Communications Management Plan创建沟通管理计划 Overall整体 Create Quality Management Plan创建 质量管理计划 Risk management planning, identification, qualification, quantification & response planning风险管理计划,识别、定性、定量分析及应对计划编制 Create procurement management plan 创建采购管理计划 Create stakeholder management plan 创建对发起人或干系人的管理计划 Create project control plan创建项目控 制计划 Develop formal project plan制定正式 项目计划 Gain formal project plan approval获取 对项目计划的正式许可 Hold kickoff meeting项目动员大会 Influencing the Leading领Solving Negotiating谈organization组织problems解决判 导 机构的影响 问题 Communicating沟通 Holding meetings召开会议 Stakeholder management干系人管理 9
ESSENCE OF PMBOK & PMP EXAM
SCOPE范围
Project Scope Management 项目范围管理- processes required to ensure that the project includes only the work required to complete the project
successfully.此过程必须确保项目只包括能保证项目成功完成的工作 Management by Objective (MBO)基于目标的管理 – determining company’s objective and how the project fits into them. MBO focuses on the goals of
an activity rather than the activity itself (manager is responsible for results rather than performing certain activities)决定公司目标及项目如何满足该目标。MBO关注于活动的目标而不仅仅是活动本身(管理者对绩效结果而不仅仅是某项活动负责) Project Scope 项目范围- the work that must be done in order to deliver a product; completion is measured against the project plan.为交付产品而必须完成的工作,通过计划来评价。 Product Scope产品范围 - features and functions that are to be included in a product; completion is measured against the requirements.产品或服务所包含的特征或性能,通过需求来评价。 Design Scope范围计划编制 – contain the detailed project requirements (used for FP contract)包含详细的项目要求(用于固定价合同) Scope Definition范围定义 – subdividing major project deliverables.细分主要项目可交付成果
Decomposing分解 – subdividing project work packages into smaller, more manageable components (activities/action steps). The heuristic (rule of
thumb) used in project decomposition is 80 hours. 将项目分解为更小的更易管理的工作包(活动或工作步骤)。首选的项目分解原则(大拇指原则)为80小时 Scope Management Plan范围管理计划 - describes how scope will be managed and how changes will be integrated into project; also includes
assessment of expected stability of project scope. (e.g. project manager would refer to the Scope Management Plan to make a change)描述项目范围如何被管理及项目范围变更如何被集成到项目中去,也包括对项目范围预测稳定性的评估。(例如,项目管理者应依据范围管理计划去进行变更) Stakeholder Management干系人管理 – the project manager must identify the stakeholders, determine their needs and expectations, then manage and
influence expectations to ensure project success.项目管理者必须识别干系人,确定他们的需求及期望,管理并影响这些期望以确保项目成功。 Configuration Management配置管理 - a means of monitoring and controlling emerging project scope against the scope baseline; its purpose is to
control change throughout the project. It is any documented procedures used to apply technical and administrative direction and surveillance to audit the items and system to verify conformance requirements. . It documents the physical characteristics of formal project documents and steps required to control changes to them (e.g. would be used by a customer who wishes to expand the project scope after the performance measurement baseline has been established). When more than one individual has sign a Charter, you have to be concerned with
competing needs and requirements impacting your efforts on configuration management一种对基于范围基线所形成项目范围的监控方法;它的用途是控制项目的全部变更。配置管理是任何成文的程序,这些程序对工作项和系统进行技术和行政的指挥与监督,通过审计证实其与要求相一致。识别一个工作项或系统的物理特性和功能特性并形成文档,控制对这些特性所做的任何变更(例如:应用于那些希望在绩效测量基线被建立之后扩大项目范围的客户)当多于一个个体签署协议,你必须关注于与配置管理 WBS工作分解结构 - subdividing project deliverables into smaller, more manageable components. It is a deliverable-oriented grouping of project
elements that organizes and defines the total scope of the project. It is a communication tool and it describes what needs to be done and what skills are required. Anything missing in the WBS should be added. The 1st level should be the project life-cycle (not product). The WBS is created by the team (helps to get buy-in) and it is used to make certain that all the work is covered. It provides a basis for estimating the project and helps to organize the work. Its purpose is to include the total project scope of all the work that must be done to complete the project. Defines the project’s scope baseline. 将项目可交付成果分解为更小的更易管理的单元。以可交付成果为导向对项目元素的分组。它是一个沟通工具,描述什么必须去做什么技术是必须具备的。任何在工作分解结构中被遗漏的需要被添加进来。第一层是项目生命周期(不是产品生命周期)。工作分解结构由项目团队产生,它用于确定所有工作都被覆盖到。它提供对于项目估算的基础并帮助组织工作。它组织并定义整个项目范围。定义项目的范围基线。 The 3 most common types of WBS are system/sub systems, life-cycle phasing and organizational工作分解结构最常见的三种形式是系统/子系统,
生命周期方式,组织的分解结构
WBS Dictionary 工作分解结构字典– Defines each item in the WBS, including description of the work packages and other planning info such as
schedule dates, cost budgets and staff assignments..定义工作分解结构中的所有元素,包括工作包描述和其他计划编制信息如进度计划日期,成本预算和人员安排。 Scope Statement范围说明 - a documented description of the objectives, work content, deliverables, and end product; it includes a description of
project assumptions and constraints. Provides stakeholders with a common understanding of the scope of the project and is a source of reference for making future project decisions.目标,工作内容,可交付成果,最终产品的备有证明文件的描述;它包括对项目的约束和假设的描述。为干系人提供一个了解项目范围的一般共识及对未来项目决策的基础 Statement of Work 工作说明- a narrative description of products or services to be supplied under contract.合同之下的关于产品和服务的叙述性说明。 Project Charter项目章程 - formal document used and approved by senior management that explains purpose of the project including business needs
addressed and the resulting product (deliverables and objectives). It describes responsibilities and authority of the project manager to apply organizational resources to project activities. Clarification to the Project Charter must be addressed to the sponsor(s) who approved the charter. Resources cannot be committed without the Charter. The Charter is an input to ALL the project management processes.一个正式批准的项目文件包括商业需求,产品描述,需要由项目以外的高级管理层发布。授予项目经理执行项目活动而使用组织资源的权利。项目发起人发布项目章程。资源必须依照章程规定使用。章程贯穿于整个项目管理过程。 Code of Accounts账目编码- any numbering system used to uniquely identify each element of the WBS.用于区分工作分解结构的所有元素唯一标识的
编码系统 Project Selection Method项目选择方法 - Benefit Measurement (comparative approach) and Constrained Optimization (mathematical approach).收益
测量法(比较方法,经济模型)和约束优化(数学模型) Work Package 工作包- deliverable at the lowest level of WBS. They are control points in the WBS and are used for assignments to work centers. They
are used to pass a group of work for further breakdown in the executive organization. 工作分解结构的最低层次的可交付成果。他们控制工作分解结构的要点并用于工作中心的分配。他们用于审查职能机构进一步细分的工作。
10
ESSENCE OF PMBOK & PMP EXAM
Scope Verification范围确认 – to verify that the work done satisfies the scope of the project. It must be done at the end of each phase. A similar activity
during closure is Product Verification. Focus on customer acceptance /performance measurement, not change to project scope. Scope
Verification is normally done in parallel with quality control (which checks for product correctness). Occur during the control phase of the project, not at the end. The review at the end of the project phase is called phase exit, stage gate, or kill point.证实所做的工作服和项目范围。在每一个阶段都要做这个范围确认工作。在收尾阶段的一个类似活动是产品确认。关注于客户满意/绩效测量,而不是变更项目范围。范围确认与质量控制(检验产品正确性)同步进行。发生于项目的控制阶段而非收尾阶段。项目阶段末的检查通常被称为阶段出口,阶段门或终止点。 Cost Account成本账号 – one level above the Work Package.工作包的上一层
Cost/Benefit analysis成本/利益分析– (part of scope planning) technique used to validate that the project can meet the technical/business objectives
set forth by Sr. Management(范围计划编制的一部分)技术用于证实项目可以达到由高级管理所确定的技术/商业目标 Project success depends primarily on customer satisfaction.项目成功主要依赖于客户的满意度。
Assumptions假设 – factors that, for planning purposes, are considered to be true, real or certain在计划编制过程中被认为真的、对的、确定的因素 The principal sources of project failure are organizational factors, poorly identified customer needs, inadequate specified project requirements, and
poor planning and control.主要的项目失败原因是组织因素,差的客户需求定义,不充分的项目需求说明和缺少计划编制和控制
Constrained optimization约束优化 – includes analytic hierarchy process, logical framework analysis and multi-objective programming.包括层次分析
法,逻辑框图分析法和多目标编程 Most Change Requests are the result of: 多数变更请求的原因 An external event 一个外部事件 An error or omission in defining the scope of the product 产品范围定义中的错误或冗长 An error or omission in defining the scope of the project 项目范围定义中的错误或冗长 A value-adding change 一个增值变更 A Change Request is the most effective way of handling the disconnect between what users actually want and what management thinks they want. The project manager’s role related to project change is to influence the factors that affect change. He should ask for a change order and look for impacts to the triple constraint. Scope Changes on project can be minimized by spending more time developing the scope baseline.一个变更请求是处理客户真正需求和管理所认为其需求之间差异的最有效的方法。项目经理在项目变更中的相关角色是对变更的因素施加影响。他决定提交一个变更申请并平衡三重约束之间的矛盾。花更多的时间制订范围基线可以使项目范围变更的可能性降至最低。
If there is enough reserve to accommodate a change, the Project Manager can approve the change (we are paid to manage the scope completion within our budget and reserves)在可以允许的范围之内,项目经理可以批准变更(用预算和应急储备支付)
HUMAN RESOURCE人力资源
Project Human Resource Management项目人力资源管理 - process required to make the most effective use of the people involved with the project保
证参加项目的人员能够被最有效使用所需要的过程 Responsibility Assignment Matrix (RAM) 责任分配矩阵– Show who does what (x=person, y=phase). The most important feature of the RAM is the
participatory development process involving all stakeholders. Show who is participant, who is accountable, who handles reviews, who provides input and who must sign off on specific work packages or project phases.谁做什么(x轴代表人, y轴代表阶段 )大多数角色和责任分配给积极参与项目工作的主要项目工作人。在特殊的工作包和项目阶段中说明谁是参与人,谁是负责人,谁进行审查,谁提供输入,谁进行签收。 Linear Responsibility Chart (LRC)线性责任图 – identifying responsibility, assignments by work packages and action required. Also referred to as
RAM.确认责任,分配必须完成的活动和工作包。也被看作是责任分配矩阵 Organizational Breakdown Structure (OBS)组织分解结构 - A depiction of the project organization arranged so as to relate work packages to
organization units.反映不同组织单位各自负责的工作包 Resources Histogram 资源柱状图– often part of Staffing Management Plan; shows resource usage (eg staff hours) per time period (eg wk, mth) of a
specific job function. 经常作为人员配备管理计划的一部分,用时间段(如周、月)表示人力资源消耗(如人时)情况的详细工作函数 Rewards and Recognition Systems奖励和表扬体系 -- to be effective, must make the link between performance and reward clear, explicit and
achievable.为达到效果,必须在业绩和奖励之间建立清晰并可实施的联系 Types of Power权力类型 Legitimate合法 (Formal)正式 Derived from formal position来自于正式的职位 Coercive惩罚 Predicated on fear源于对某种后果的惧怕 Reward奖励 Involves positive reinforcement and ability to award something of value包括对有贡献的进行物质奖励 Project often needs their own rewards system to affect employee performance. Used correctly, bring the team’s goals and objectives in line with each other and with the project.项目经常需要带有奖励机制来影响成员的绩效。正确的行使激励,将使团队的目标和项目的目标取得一致。 Expert专家 Held in esteem because of special knowledge or skill (requires time)由于专门的知识和技能带来的影响力(源自自身的威望) Referent潜示 Ability to influence others through charisma, personality, etc.借用一个权力更大的人的职权来增强自己的权力 The best forms of power are generally Reward and Expert最好的权力形式一般是奖励和专家
11
ESSENCE OF PMBOK & PMP EXAM Conflict Management冲突管理 Problem Solving / Confrontationaddress conflict directly in problem solving mode 在问题解决中直接面对问题的方法 [win/win] 解决/面对问题 Compromising妥协 bargaining and searching for solutions; neither party wins but each gain some satisfaction [lose/lose] this is very rarely a good way to resolve technical issues.通过讨价还价寻找一定程度上使双方满意的解决办法,这是一个解决技术问题的好办法。 Smoothing缓和 de-emphasize differences and emphasize commonalities; friendly but avoids solving root causes; delaying (eg. Manager says an issue is valid but doesn’t think it will be a big problem later)淡化分歧强调一致性,努力保持友好的氛围是求同存异的解决办法;这种方法暂时有效,缓和不解决根本问题(例如,经理说一个事情是有效的但不认为它随后会成为一个大问题) Withdrawal (Ignoring)撤退(忽retreating from actual or potential disagreement; delaying (e.g. “Just document the problem”)从实际的或潜略) 在的争吵中退出,不解决问题(例如,只是记录问题) Forcing强制 exerting one’s viewpoint; a last resort [win/lose] (e.g. “Call the customer and demand that you receive the approval today.”强调一方观点,最后的手段(例如,通知客户你今天需要一个正式批准) Collaborating合作 Involves incorporating multiple ideas and viewpoints from people with different perspectives and offers a good opportunity to learn from others (good when project is too important to be compromised)统一大家的意见,提供一个彼此学习的好机会(项目很重要必须折中时) EXECUTION & Most INITIATIONPLANNINGCONTROL执行CLOSE-OUT Tension启动 计划编制 收尾 最主要压控制 力 1 1 + 2 3 3 2 1 2 3 1 3 2 + + + Sources of Conflict 冲突的原因 Priorities项目优先级 Admin Procedures行政管理程序 Schedules进度 Technical Issues技术规范 Personnel Resources人力资源 Personality Conflict个性冲突 3 steps of problem solving: 解决问题的三个步骤 1. 2. 3. Motivational Theory: Content & Process Theories动机理论:满足/过程理论 Content: “What” energizes, directs behavior –满足:“什么”激发,导致行为 1. 2. Maslow’s Hierarchy of Needs Theory (Physiological, Safety, Social/Belonging, Esteem, Self-Actualization)马斯洛需求层次理论(生理需求,安全需求,社会/归属需求,尊重,自我实现) Hertzberg’s Motivator/Hygiene Theories (Motivator: Self-Actualization, Esteem ; Hygiene: Social, Safety, Physiological)赫兹博戈卫生与动机理论(动机:自我实现,尊重;卫生:社会,安全,生理) McGregor’s Theory X and Theory Y (X: Assumes people lack ambition, dislike responsibility, are inherently self-centered and are not very bright; motivate by reward and punishment. Y: Assumes people become lazy w/o recognition, will accept responsibility, can become self-motivated and exercise self-control; motivate by removing obstacles and providing self-directed environment.) 麦克雷戈德X理论和Y理论(X:人缺乏责任感,自私,需要被人监管,不聪明,受制于奖惩。Y:假设人有创造力,能自我管理,能实现自我激发,能主动扫清障碍,创造以自我为中心的环境 ) Ouchi’s Theory Z/Japanese Theory ( focus on team, company; usually lifetime employment, collective decisionmaking )奥奇Z理论和日本理论(关注于团队,公司;一般是终身雇佣,集体决策) Analyze the situation / Document the situation分析/证实情况 Develop alternatives with the team团队开发替代方案 Go to management执行管理 Process: “How” personal factors influence behavior作用:个人因素“如何”影响行为 1. 2. Other Motivational Theories:其他动机理论
Behaviorism 行为主义– people behavior can be modified through manipulation of rewards and punishments人们的行为会因为奖惩而改变
Expectancy Theory期望理论 – Motivation is explained in terms of expectations that people have about (1) their ability to perform effectively on the job, (2) the rewards they might obtain if they do perform effectively and (3) the value or degree of satisfaction they anticipate from those rewards动机被解释为人们所具有的期望(1)通过努力极有可能完成工作(2)完成工作后会获得奖励(3)奖励带来满足 MBO – More support to team, not more power (remain to PM)对团队给与更多的支持而非更多的权力
12
ESSENCE OF PMBOK & PMP EXAM Leadership Theories:领导者理论
McGregor麦克雷戈 – Theory X (employee lack ambition) and Theory Y (org structure are responsible for motivation) X理论(员工缺乏雄心)Y理论(组织可以以赖于来源于员工的自信的动力)
Tannenabaum-Schmidt model – Continuum of leadership styles between the autocratic and participative styles是独裁领导风格和参与性风格的统一体
Blake and Mouton – ref to managerial grid (Concern for People Vs Concern for Production), whereas 1,1 is laissez faire mgmnt, 1,9 is Country Club mgmnt, 9,1 is Task oriented mgmnt, 5,5 is Compromise mgmnt and 9,9 is team mgmnt. Forms of Organization组织形式 Functional职能 Groups people by specialization. Project manager has no formal authority of resources and must rely on informal power structure and his own interpersonal skills to obtain resource commitments from functional managers.专业化分组。项目管理者没有对资源的控制权力,必须依靠非正式权利及自身的沟通能力从职能经理处获取资源 Project Expeditor Retains functional but adds a Project Expeditor who serves as a communications link and coordinator for the project 项目联络员 across functional units保留职能,添加一个能在项目各职能部门起联络作用的项目联系人 Project CoordinatorSimilar to Project Expeditor except the Coordinator reports to a higher level manager and has some authority to assign 项目协调员 work与项目联系人相似,不同的是,项目协调员需要向更高层管理员汇报并有一些权利直接布置工作 Weak Matrix弱矩阵 Vertical functional lines of authority maintained with a relatively permanent horizontal structure containing managers for various projects. Balance of power leans toward the Functional Manager. Can cause a project to fall behind because functional managers are pulling resources away to perform non-project related tasks. The Project Manager may be able to make resource decision on his own but not technical decision.权力倾向于职能经理。由于职能经理将资源移到非项目工作中去,有可能导致项目落后。项目经理有可能依据自身而不是技术决策来决定资源决策 Strong Matrix Same as Weak except that the balance of power leans towards the Project Manager类似于弱矩阵,所不同的是,权力倾强矩阵 向于项目经理 Projectized项目性 A separate, vertical structure is established for each project. All the project team members report directly and solely to the project manager.为每一个项目所建立的单独的垂直的结构。所有项目团队成员直接地单独地向项目经理汇报 **Memorize PMBOK “Organizational Structure Influence on Projects”组织结构对项目的影响 Team building is most difficult in a matrix organization. Its main purpose is to improve team performance.团队建设在矩阵组织中是最困难的。它的主要目的是为了提高团队绩效 Team development is based on the individual development of each member.团队发展基于团队中每个成员的个人发展 Leadership Styles 领导风格 Autocratic专制 PM makes decision without soliciting information from team项目经理个人作出决定而不用考虑员工的意见,适用于紧急状况 Consultative咨询Intensive information solicited; PM makes decision最大程度的收集信息,项目经理制定决策 式管理 Consensus协商式Team makes decision; open discussion and information gathering by team团队做决策,开放式讨论并从团队收集信息,管理 主要决策由高层决定 Shareholder参与 Little or no information exchange; team has ultimate authority for final decision;团队有最终决定权 Roles of the Project Manager项目经理角色 Integrator集成者 Communicator沟通者 Team Leader团队领导 Decision Maker决策者 Climate Creator/Builde氛围营造者r
Documentation文件 ? ? ?
Staffing Management Plan人员配备管理计划– describes when resources will be brought into and taken off the project.描述何时及如何把人力资源投入或撤出项目团队
Employee Record Update 员工记录更新– as part of closure, the project manager should update employee’s record with the new skills acquired.作为收尾的一部分,项目团队需要更新员工对新的技能掌握程度的纪录
Resource calendar 资源日历– identifies period when work is allowed.确定资源可用时间段
Functions of the Project Manager项目经理的职能 Planning计划编制 Organizing组织 Leading领导 Controlling控制 13
ESSENCE OF PMBOK & PMP EXAM
COMMUNICATIONS沟通
Project Communications Management项目沟通管理 - process required to ensure proper collection and dissemination of project information.保证正确收集或发布项目信息的过程
Team Meetings团队例会 – periodic team meetings is the most effective way to accelerate the project integration process.定期的团队会议是加速项目综合进程的最有效的方法
Performance Reviews绩效审查 – meetings held to assess status and/or progress.评估项目状态和进度的会议 Communications Model沟通模型 Communicator发报者 The originator of the message消息的产生者(确保信息清楚、无歧意并且完整) Message消息 Thoughts, feelings, or ideas reduced to \以编码输出的发报者与收报者都能理解的思想、意见、感觉 Medium媒介 The vehicle or method used to convey the message用来传达消息的工作或方法 Receiver收报者 The person for whom the message is intended完成或打断通信过程的参与者 [Sender] -- Encoding ? Transmission ? Decoding -- [Receiver] ? Feedback 发送者---编码----〉发送-----〉解码-----〉接收-------〉反馈 Communications Channels沟通渠道 = (n2- n)/2 or n(n-1)/2 …the fact that two team members are working “directly” together does not reduce the number of communication channels.事实就是即便两个团队成员直接地工作也不能减少沟通渠道的数目
Tight Matrix紧密矩阵 - all team members allocated in a single office space所有团队成员集中在一个办公区域
A variance is considered to be significant if it jeopardizes project objectives.一个分歧如果可能危及到项目目标就应该得到重视
The purpose of project plan development is to create a document to guide project execution and control.项目计划编制的目的是制定一个指导项目执行和控制的文件
The output of project plan execution consists of work results and change requests.项目计划执行的输出由工作结果和变更请求组成 Types of Communications沟通方法 Formal Written正式书面 Project Charter, Management Plan (this is the best type of communication method to use when there are cultural differences and distance between team members)项目章程、管理计划(这是跨文化和远程团队交流所需要的最好的沟通方法) Informal Written非正式书面 Notes, memos笔记,备忘录 Formal Verbal正式口头 Presentations介绍、讲演 Informal Verbal非正式口头 Conversations交谈 Note: 55% of communications is non-verbal (it is the most important aspect of a conversation)55%的沟通是非语言的(这是交流最重要的组成部分) 90% of Project Manager's time is spent acquiring and communicating information项目经理90%的时间用于传递和获取信息 Objectives of a Kickoff Meeting项目启动会的目标 Get to know each other相互了解 Set team goals and objectives设置团队目标 Review project status审查项目状态 Review project plans审查项目计划 Identify problem areas确定问题领域 Establish responsibilities and accountabilities确立责任和义务 Obtain commitments得到承诺 Barriers to Communications (which lead to conflict)沟通的障碍(导致分歧的因素) Lack of clear communication channels缺乏清晰的沟通渠道 Physical or temporal distance物理或时间距离 Difficulties with technical language不懂技术术语 14
ESSENCE OF PMBOK & PMP EXAM
Distracting environmental factors分散注意力(噪声) Detrimental attitudes有害的态度(敌对、不信任) The most likely results of communication blocker and miscommunication as a whole is conflict.沟通障碍或错误信息导致冲突升级
Building Effective Team Communications营造有效的团队沟通 Be an effective communicator成为一个有效的沟通者 Be a communications expeditor成为一个沟通联络员 Avoid communication blockers避免沟通障碍 Use a \ce space)使用紧密矩阵(作战室) Make meetings effective (meeting during execution is the best format to communicate)有效会议(实施期间最好的沟通方法是开会 ) Management Styles 管理风格 Authoritarian独裁 Lets individuals know what is expected of them进行具体指导,并希望遵守规则与标准 Combative好斗 Eager to fight or be disagreeable over any situation喜欢对任何情况都进行挑战或持不同意态度 Conciliatory调和 Friendly and agreeable友好的、容易相处的 Disruptive分裂 Tends to disrupt unity and cause disorder倾向于破坏团结造成混乱 Ethical伦理 Honest and sincere诚实真诚(强调公平解决) Facilitating提供方便 Does not interfere with day-to-day tasks, but is available for help and guidance when needed不干扰日常任务,但在需要时提供帮助和干扰 Intimidating威胁 Reprimands employees for the sake of a \申斥那些制造麻烦的人 Judicial公正 Applies sound judgment应用合理判断 Promotional促进 Cultivates team spirit; rewards good work; encourages subordinates to realize their full potential培养团队精神;奖励出色的工作;鼓励下属了解他们所有的潜能 Secretive不公开的 Not open or outgoing in speech, activity, or purpose不公开介绍,活动,意图 Management Skills管理技能 Leading领导 Communicating沟通 Negotiating谈判 Problem Solving问题解决 Influencing the Organization对组织施加影响 Documentation项目文件 …the prevailing measurement of what information to accumulate and communicate on a project is that it contributes to its success.一个项目中知识的积累和传递的最有效测量方法是看它是否对项目的成功有利 ? ? ? ? ? ? ? ? ? ? Progress Report进度报告 - summarize project status. Preferred report to quickly review where a project now stands.总结项目状态。审查项目现状的首选报告方式 Trend Report趋势分析报告 – show performance over time (shows if it is improving or deteriorating)检查项目 结果(以确定绩效是提高了还是降低了) Variance Report偏差分析报告– compare project results, looks at specific project items or tasks比较项目结 果,关注特殊的项目条款或任务 Forecasting Report 预测报告– only looks into the future 对未来项目状况和进展作出预测 Status Report状态报告 – relating a moment in time (static)描述当前状况 Project Plan项目计划 Staffing Management Plan人员配置管理计划 Communications Management Plan沟通管理计划 - should cover all phases of the project应该包括项目的所有阶段 Performance reports 绩效报告– provide info on schedule performance, thereby alerting the team to problems that may arise in the future.提供进度绩效信息,提醒团队那些可能在未来引起问题的事项 Reports are a method to distribute information, not just to rep哦ort on progress报告是发布信息的一个方法,而不仅仅是报告进展情况 Establishing direction, aligning people, and motivating and inspiring确定方向,协调思想,激励与鼓舞 The exchange of information in a variety of dimensions在不同层面进行信息交流 Conferring with others in order to come to terms or reach an agreement与他人协商达成某种协议 A combination of problem definition and decision making问题的定义与决策制定的结合 The ability to get things done based on an understanding or the formal and informal structures of the organization基于对所有组织的正式或非正式结构的明确理解的“把事情办妥”的能力 15
ESSENCE OF PMBOK & PMP EXAM
TIME时间
Project Time Management项目时间管理 - processes required to ensure timely completion of the project确保项目按时完成
Activity Definition活动定义 – defines activities that must take place to produce project deliverables定义完成项目可交付产品必须进行的具体活动 Activity活动 – consumes time (eg testing)消耗时间(如:进行测试)
Events事件 – specified accomplishment / does not consume time (eg tested)指定要完成的任务/不消耗时间(如:测试工作)
PERT计划评审技术 Weighted Average = (O + 4M + P)/6 standard deviation = (P - O)/6 variance = standard deviation2 (To add standard
deviations: convert to variance then add; take the square root of the sum). Best method when you have no historical data for a similar task. Results is the 50% point (mean). 均值= (O + 4M + P)/6 ,标准差= (P - O)/6,方差=标准差2(累加标准差:转换成活动方差再累加;取和的平方根)类似任务中没有原始数据时的最好估算方法。结果是中值(平均数) Monte Carlo Analysis蒙特卡洛分析 - computer simulation of project outcomes using PERT estimates; result represented in S curve. Provides the
ability to compute the probability of completing a project on a specific day. Can also be used to assess feasibility of schedule under adverse
conditions (eg when a schedule constraint is identified)使用PERT估算的计算机模拟项目输出方式;结果描述成S曲线。提供在某一天项目能够完成的概率。同样可以被用于估计相反概率的可能性(当时间进度一定时) Heuristics启发式 - rules of thumb拇指原则
Critical Path关键路径 – longest path (almost always have no float)最长路经(通常没有时差时间) Variance偏差 - Plan minus Actual计划与实际的差距
Float / Slack时差/松弛时间 – Time an activity may be delayed from its early start without delaying the project finish date. Difference between the
required end date and the expected project completion date. A negative slack on the critical path means that the project is behind schedule.在不延误项目完成日期的情况下,活动自其最早开始的日期起可以推迟的时间量。项目要求结束时间和项目预期结束时间之间有差别。在关键路径上存在一个负时差说明项目落后于进度计划。 Free Float自由浮动时间 – Amount of time a task can be delayed without delaying the early start of its successor自由浮动时间是在不延误任何紧后活动
的最早开始时间的情况下,活动可以推迟的时间量。 Total Float 总时差– amount of time that an activity may be delayed from early start without delaying the project finish date在不延误项目完成日期的情况
下,活动自其最早开始的日期起可以推迟的总时间量 Lag滞后 – waiting time between two tasks (negative lead)两个任务之间的等待时间(负超前)
Schedule Baseline 进度基线- the original, approved project schedule; should never be changed without proper review and approval. Any approved
change should be documented in writing. Should be created at the beginning of the project and used during the project to gauge (measure) overall project performance, not just schedule. The project Performance Measurement Baseline should generally change only in response to a scope or deliverable change.原始的,被核准的项目进程;未经恰当的评估和正式批准永远不能改变。被核准的变化必须以文档纪录。在项目启动时制定,贯穿于整个项目进程以评估项目执行,而不仅仅是在计划阶段完成。项目绩效测量基线仅在范围变更时候或可交付成果发生变化时变更。 Corrective action纠正措施 - in project time management primarily concerns expediting to ensure that activities remain on schedule. Is anything done to bring expected future schedule performance in line with the project plan.项目时间管理主要关注确保进度表中的活动按时完成。使预期的未来项目绩效与计划保持一致所做的任何事情。 Revisions修订 are changes to the scheduled start and finish dates in the approved project schedule; generally revised only in response to scope
changes. Rebaselining may be needed to provide realistic data to measure performance.对已批准的项目进度计划的开始和结束时间的修改;只反映相应的项目范围变化时才进行修订。重新确定基准计划能提供测量进度绩效的真实数据。 Scheduling and allocating resources to multiple projects may affect schedule slippage and in-process inventory.多项目管理的进度计划和资源分配可能
会影响进度滑动和存货清单。 The most important element necessary for project control is clear requirements.项目控制中最重要的因素就是清晰的需求。
Duration Compression Methods 历时压缩方法– occurs after activity duration estimating and before finalizing the schedule. Include crashing, fast
track, 在活动历时评估之后,进度最终敲定之前发生。包括赶工和快速跟进。 Crashing赶工 – when you are worried about time, not so much about costs.通过加大成本缩短历时。
Fast Track 快速跟进– resources in parallel, involve increase rework. Fast track tasks should on the critical path (float = 0) in order to save time.串行改
并行,会带来返工。快速跟进一般在关键路径上进行以节省时间。 Resource Leveling 资源平衡– often results in a project duration that is longer than the preliminary schedule. Resource reallocation from non-critical
to critical path activities is a common way to bring the schedule back, or as close as possible, to the originally intended overall duration. 经常导致活动历时超过最初的进度计划。资源分配从非关键路径到关键路径的活动是导致进度滞后于最初拟定的完成时间的一般原因或最接近的原因, Finish to Finish结束结束关系 - activities must finish on a specific sequence 活动必须按照一定的次序结束
“Start no earlier than” & “Finish no later than” 不早于和不晚于– Respectively #1 and #2 most popular date constraint in project management
software.在项目管理软件中排名第一和第二的常见日期约束。 Root Cause Analysis 根源分析– used to identify the cause of the variation用于定义偏差的产生原因
Variance analysis偏差分析 – key element to time control. Float variance is an essential planning component for evaluating project time performance.
时间控制的关键部分。时差偏差是评估项目绩效的核心计划编制成分。 Revision修订 – category of schedule update that result in change to the project’s scheduled start or finish dates. New target schedule should be the
usual mode of schedule revision.导致项目拟定的开始或结束时间的变化的项目进度表更新。新的目标进度计划应该是项目进度修改的标准模式。
16
ESSENCE OF PMBOK & PMP EXAM
Schedule Management Plan 进度管理计划– defines how schedule changes will be managed; may be formal or informal.定义进度变更如何管理,可能
是正式的或非正式的 Schedule Change Control System 进度变化控制系统– defines procedures for changing the project schedule and includes the documentation, tracking
systems, and approval levels required for authorizing schedule changes.定义项目进度的变更程序包括文档工作,跟踪系统和对变更的审批批准层次
Project Time Management项目时间管理 Arrow Diagramming Method (ADM):PERT and CPM focuses on float duration, to determine which activities have the least scheduling 箭线图 flexibility. PERT计划评审技术 Program Evaluation and Review Technique程序评估和回顾技术 Emphasis on meeting schedules with flexibility on cost重点在于成本的计划与弹性相协调 Three time estimates per activity: pessimistic, most likely, and optimistic每项活动评估三次:悲观的,一般的,乐观的 The probability of completing a project at or later than its expected time is 50%按预计或晚于预计时间完成项目的概率为50% Event oriented; uses dummy; activity on arrow (AOA)事件为导向的;使用标志符;活动箭头 Finish-to-Start logical relationship结束即开始的逻辑关系 Time estimates appear on arrow时间评估出现在箭头上 Critical Path Method关键路径方法 Emphasis on controlling cost and leaving the schedule flexible重点在控制成本上,让计划保持灵活性 (CPM) One time estimate per activity每项活动评估一次 Activity oriented; uses dummy; activity on arrow活动为导向;使用标志符;活动箭头 Time estimates appear on arrow时间评估出现在箭头上 Precedence Diagram Method优先Represents improvement to PERT and CPM by adding lag relationships to activities 图方法 (PDM) [Start to Start; Start to Finish; Finish to Start; Finish to Finish]开始对开始;开始对结束;结束对开始;结束对结束 Work is done during activity. Arrow indicates dependancy在活动中完成工作。箭头指示依赖性 Activity on node; no dummy节点上的活动;没有标志符 GERT A network diagram drawing method that allows loops between tasks. It is a method of sequencing (e.g. a project requires redesign after completion of testing) 允许任务之间发生循环的网络图表制图方法。有先后次序的方法(例如:测试完成之后,项目需要重新设计) Dependencies依赖关系 Mandatory or Hard强制 Often involve physical or technological limitations (based on the nature of work being done)常常包括了物理及技术上的局限性(基于被完成任务的属性) Discretionary自由 Soft: desirable and customary (based on experience)软件:需要的,习惯性的(在经验基础之上) Preferential: preferred or mandated by a customer (also, need of the project sponsor)优先: External外部 Input needed from another project or source从其他项目或资源输入所需 Resource Planning Tools 资源分配工具 Responsibility Matrix责任矩阵 Identify who does what at what time/phase of the project定义谁在项目的什么时间/阶段做什么 Resource Spreadsheet资源表 Quantifies how much work is needed from each resource during each time period量化每段时间从各个资源所需的任务量 Resource Gantt Chart资源甘特图 Identify the periods of time (e.g. calendar date) when a particular resource is working on a particular task在一个特定的资源用于一个特定任务时,定义时间段(如:日历) Resource Histogram资源柱状图 Vertical bar chart showing the total number of resources needed during each time period显示在每一个时(Resource Loading Chart)(资源间段所需资源总量的垂直条状图 复合图) Scheduling Tools进度计划编制工具 Networks (PERT, CPM, PDM)网络 Barchart (Gantt)甘特图 Milestone Chart里程碑图
Interdependencies; how related相互依赖;相互关系的 Effective progress reporting tool; no logical relationships shown between activities有效的发展报告工具;在活动中不现实逻辑关系 Significant events; good for communicating status (used to track success)重要事件;对沟通情况有利(用于跟踪成功事件) COST
17
ESSENCE OF PMBOK & PMP EXAM
Project Cost Management Processes required to ensure that the project is completed within the approved budget.保证在批准的预算内完项目成本管理 成项目的过程 Benefit Cost Ratio Expected Revenues / Expected Costs. Measure benefits (payback) to costs; not just profits. The higher the 收益成本比率 better (if rating over 1, the benefits are greater than the costs) 期望收入/期望成本。测量相对于成本的收益(回报),不仅仅是利润。该比率越高越好(如果比率超过1,收益大于成本) Internal Rate of Return Interest Rate which makes the PV of costs equal to PV of benefits 内部收益率 使得成本的计划值等于收益的计划值的利率 Payback Period Number of time periods up to the point where cumulative revenues exceeds cumulative costs. Weakness in 回收期 this approach is the lack of emphasis on the magnitude of the profitability. Does not account for time value of money nor consider value benefits after payback. 累计收入超过累计成本时的周期数。这种方法的弱点是缺乏对收益数量的强调。既没有计算金钱的时间价值,也没有考虑回报后的收益价值。 Opportunity Cost Cost of choosing one alternative and therefore giving up the potential benefits of another alternative: it is the 机会成本 value of the project not selected (lost opportunity). 选择了可选方案的一种因此放弃了另一个可选方案的潜在收益的成本:它是没有被选择的项目的价值(失去机会)。 Sunk Cost Expended costs which should be ignored when making decisions about whether to continue investing in a 沉淀成本 project 已经花费的成本,并且该成本在做出是否继续投资一个项目的决策时不再考虑。 Law of Diminishing Returns The point beyond which the marginal addition of resources does not provide a proportional amount of utility. 收益递减率 资源边际增加不能提供成比率的效用数量。 Straight Line Depreciation Same amount each time period (e.g. 10 – 10 – 10) 直线折旧法 每一时间段折旧相同数量(例如:10 – 10 – 10) Contingency Reserve Separate quantity of time/money for known unknowns. Designed to cover specific risk events previously 应急储备 identified and measured in the Risk Management Process. 为已知的未知单独准备时间/金钱的数量。目的是为了应对之前在风险管理过程中已经确定和测量的特殊的风险事件。 Management Reserve Separate quantity of time/money for unknown unknowns 管理储备 为应对未知的未知风险而准备的单独的时间/金钱的数量。 Working Capital Current Assets - Current Liabilities 运营资本 当前的资产-当前的债务 Value Analysis Cost reduction tool that considers whether function is really necessary and whether it can be provided at a 价值分析 lower cost without degrading performance or quality. Finding the least expensive way to do the scope of work. 成本降低工具,它考虑了功能是否真正需要以及它是否能在不降低性能或质量的前提下适用较低的成本来实现。寻找到较少的花费来实现工作的范围。 Value Estimating Part of Cost Control 价值估算 成本控制的一部分 Value Engineering Tool Tool for analyzing a design, determining its function, and assessing how to provide those functions cost 价值工程工具 effectively. 分析设计,确定它的功能并评估如何使用有效的成本提供这些功能的工具。 50-50 Rule At beginning, charge 50% of its BCWS to the account. Charge remaining at completion. 50-50规则 在开始时,计计划值的50%,结束时计剩下部分。 Analogous Estimating Top down; based on similar projects. Represents a form of expert judgment. Gives project team an 类比估算 understanding of management’s expectations (part of cost budgeting and cost estimating) 从上自下的估算,基于简单的项目。代表专家判断的一种形式。给管理团队一个管理预期的理解(成本预算和成本估算的一部分)。 Bottom-up Estimating Detailed cost estimates of work packages are aggregated. Would provide best overall quality of the estimate. 自下而上的估算 工作包详细成本估算的总合。将提供最好的全局的估算质量。 Parametric Estimating Relies on knowledge of mathematical relationships; measured in $/unit (scalable, quantifiable). It does not 参数估算 make use of team estimate. (part of cost budgeting and cost estimating). Using a mathematical model to predict the duration of a task (e.g. taking the average duration of all past tasks) 依赖于数学关系的知识,测量每单位所花的金钱数$/单位(可测量的,可计量的)。它不能使用团队估算(是成本估算和成本预算的一部分)。使用数学模型预测任务的历时(例如:所有以前任务的平均历时)。 Regression Analysis Statistical technique graphically represented on scatter diagram 回归分析 在分散图表中的图形描绘的统计学工具 Learning Curve Mathematically models the intuitive notion that the more times we do something, the faster we will be able to 18
ESSENCE OF PMBOK & PMP EXAM
学习曲线 perform 数学模型,直觉概念是我们作某事的时间越长,我们将能够执行的更快。 Variable Costs Costs rise directly with the size and scope of the project 可变成本 随着项目规模和范围的增加,成本直接上升 Fixed Costs Costs do not change; non-recurring (e.g. project setup costs) 固定成本 成本不会变化,不再发生(如:项目设置成本) Direct Costs Incurred directly by a specific project. The PMI want the team to participate in the cost estimates to get their 直接成本 buy-in. 由一个特定项目引起的成本。PMI想让团队参与成本估算并达成共识。 Indirect Costs Part of the overall organization's cost of doing business and are shared by all projects. Usually computed as a 间接成本 percentage of the direct costs. 整个组织运营成本的一部分,是共享与所有项目的。通常用直接成本的百分比计算。 Cost accounts Represent the basic level at which project performance is measured and reported. The purpose of cost 控制帐户 accounts is to monitor and report on project performance. 代表着测量和报告项目绩效的基本层次。控制帐户的目的是监控和报告项目绩效。 Cost Change Control Includes the documentation, tracking systems, and approval levels needed to authorize a change. Systems 包括文档工作,跟踪系统,和批准变更必须的批准层次。 成本变更控制系统 Budget updates Should be the next steps after an approved cost baseline has changed because of a major change on a 预算更新 project. 将是在已被批准的成本基线由于项目的重大变更而发生变更的下一步骤。 Operating profit Amount of money earned: Revenue – (direct + indirect costs) 运营利润 赚得的钱数:收入-(直接成本+间接成本) Discounted cash-flow Present value method determines the net present value of all cash flow by discounting it by the required rate approach of return. 现金流量折现法 现值法通过使用必须的回报率折现来计算所有现金流量的净现值 Parametric modeling Involves using project characteristics (parameters) in a mathematical model to predict project costs. 参数模型 包括在数学模型中使用项目特征(参数)来预测项目成本。 Life-Cycle Cost Provide a picture of the total cost for the product (project, operations and maintenance). 生命周期成本 描绘项目全部成本(项目,运营和维护) Project Closeout (output to cost control) Process and procedures developed for the closing or canceling of projects 项目收尾 (成本控制的输出)确定结束或撤销项目的过程和程序。 Formulas Expected Value Probability * Impact 预期价值 概率*影响 Present Value FV / (1 + r)t 现值 Cost Variance EV – AC [BCWP – ACWP] Variance = planned – actual 成本偏差 EV – AC [BCWP – ACWP] 偏差=计划-实际 Schedule Variance EV – PV [BCWP – BCWS] (if <0; work completed is less than what was planned) 进度偏差 EV – PV [BCWP – BCWS](如果小于0,完成的比计划的少) Cost Performance Index EV/AC [BCWP / ACWP] I am getting ____ out of each dollar. (>1 good; <1 bad) 成本绩效指数 Schedule Performance Index EV/PV [BCWP / BCWS] I am progressing at ____% of the rate originally planned 进度绩效指数 Estimate at Completion (EAC) BAC / CPI 完工估算 AC+ETC (when original estimates are considered flawed) (当原始估算被认为是错误的) AC+BAC-EV (when everything is OK and variance will not occur in the future)(当一切都好并且偏差将不会在将来发生) AC+((BAC-EV)/CPI) (when everything is OK and variance will occur in the future)(当一切都好且偏差将会在以后发生) Estimate to Completion (ETC) EAC - AC or (BAC - EV) / CPI 19
ESSENCE OF PMBOK & PMP EXAM Formulas 完工估算 Variance at Completion (VAR) BAC – EAC 完工时的偏差 % Spent AC/BAC %花费 Cost Variance in % CV/EV 成本偏差的% Schedule Variance in % SV/PV 进度偏差的% BCWS (PV) How much should be done? This is the performance measurement baseline. 计划值 多少需要做的工作?这是绩效测量基线 BCWP (EV) How much work is done? (Progress) Budgeted cost of work performed. Value of the work completed in 挣值 terms of what you budgeted (your baseline) 多少工作应经完成?(发展)完成工作预算成本。工作完成的价值依据你的预算(你的基线)确定。 ACWP (AC) How much did the “is done” work cost? 实际成本 完成工作的成本是多少? BAC Budget at Completion – How much is budgeted for the total job? BAC would change every time there is a 完工时的预算 funded scope change approved for activity to be performed in the future. 完成时的预算——全部工作的预算是多少?每当固定范围变更时,完工预算将为以后活动的执行改变。 EAC Based on project performance and risk quantification 完工时的估算 基于项目绩效和风险量化 ETC Estimate to Completion 完工时的估算 到完成时的估算 CPI Cumulative CPI does not change by more than 10% once a project is approximately 20% complete. The 成本绩效指数 CPI provides a quick statistical forecast of final project costs. 一但项目完成了大约20%时,累积的CPI不能超过10%。CPI提供了一个最终项目成本的快速的统计预测。 EV=PV [BCWP=BCWS] EV equals PV when the project is completed. EV等于PV时项目完成。 AD Work Quantity(scope of the activity) / Production rate 工作数量(活动的范围)/生产率 Slope (crash cost - normal cost) / (crash time - normal time) ; if <0, as the time required for a project/task decrease, the cost increase (压缩成本-正常成本)/(压缩时间-正常时间);如果小于0。随着项目/任务计划时间的减少,成本上升。
Documentation ?
Cost Management Plan – (from Cost Estimating) The action taken by the project manager for all variances are described in the Cost Management Plan.成本管理计划-(来自成本估算)在成本管理计划中描述了所有项目经理为偏差所采取的行动。
RISK风险
Project Risk Management 项目风险管理– processes concerned with identifying, analyzing, and responding to uncertainty. The most likely cause of
poor risk management is lack of prioritized list of risks对风险进行识别、分析、应对的系统化过程。差的风险管理源于没有对风险进行分类排序 Types of Risk风险类型 Business商业风险 Pure / Insurable纯风险/可保险 Normal risks that offer gain and loss正常的风险可能会带来盈利或损失 Only loss: property damage, indirect consequential loss, legal liability, personnel. For risk we can outsource, we have contract. For pure risks, we obtain insurance.只带来损失:财产损害、间接损失、法律责任、人员损失。可通过购买保险、签订合同等手段将风险转移出去。 Risk Factors风险因素 Risk event风险事件 Risk probability风险概率 Amount at Stake得失量 Statistical Independence统计独立 来源,事件,征兆 Occurrence of one event is not related to occurrence of the other 一件事情的发生与其他事情的发生无关(期望值分析和决策数分析的必要条件) Purpose is to test the value of data (input to Qualitative Analysis)数值测量(质量分析的输入) 20
ESSENCE OF PMBOK & PMP EXAM Data Precision Ranking数据精确度等级 Secondary Risk二次风险 Path Convergence路径汇聚 Contingency Plan应急计划 Uncertainty不确定性 Workaround权变措施 Expected Monetary Value期望值 Risk Event风险事件 Tendency of parallel paths of equal duration to delay the completion of the milestone where they meet所有在此处的延迟会导致汇合于此处的任何路径的延迟 Planned action steps to be taken if an identified risk occurs. (e.g. developing alternative activity sequences)如果风险发生,应该采取计划措施的步骤(如:制定备选方案) An uncommon state of nature, characterized by the absence of any information related to a desired outcome.一个偶然事件,对未来事件缺乏认知 Unplanned response to negative risk events (requires to be impacted by the risk first)对不利的风险事件的未经计划的应对措施(首先要压缩风险) = Probability * Monetary Impact (used in Decision Tree Analysis)概率*得失量(用于决策树分析) A discrete occurrence that may affect the project for better or worse. After a risk event, the project manager’s role is to reassess the risk ranking. The risk owner is responsible to take action when an identified risk occurs.可能导致项目变好或者变坏的不连续事件。风险事件过后,项目管理者的任务是重新评估风险等级。当风险发生时,风险所有者有责任采取行动 A symptom of risk; indirect manifestation of actual risk event; output of risk identification; example is poor morale一种风险征兆;间接的表现出风险事件;风险鉴别的输出; Risk data assembled for the management of the project项目管理中的风险数据组合 Technique that characterizes an individual’s willingness to take risk描述个体承担风险意愿的方法 Places a value on the impact to the project plan by adjusting a single project variable; simplest form of analysis最简单最经济的定量分析方法(没考虑风险要素间关系及概率) Role is to investigate the effectiveness of the risk owner (which can cause potential conflict with risk owner) 任务就是调查风险所有者可能的影响力(可能引起潜在风险的风险所有者) Risk Taker, Risk Adverse, Risk Neutral; if you know the tolerance of the stakeholders, you can determine how they might react to different situation and risk events. You use this information to help assign levels of risk on each work package.风险承担者,风险转变者,风险中立者;如果你知道干系人的承受度,你就能判定他们在不同的情况和风险事件中在多大程度上给与反应。用这种方法帮助你确定每一个工作包中风险的等级 (part of Risk Response Planning)(风险应对计划的一部分) Risk Trigger风险触发器 Risk Portfolio Utility Theory效用理论 Sensitivity Analysis敏感性分析 Risk Auditor风险核对 Risk Tolerance风险容忍度 Responses to Risk风险应对措施 Avoidance Eliminating cause eliminates risk. Can be done by changing the Project Plan or protecting project objectives from its (elimination/abatement)impact.消除风险产生原因。通过修改项目计划来消除某些风险或使项目目标免受风险的影响(在项目早期风险可通过澄规避(消除/排除) 清要求获取信息,加强沟通,听专家的,来规避) Mitigation (reduction)缓Reduce the Expected Monetary Value. Float can be use to mitigate potential risks设法将负面风险事件的概率或带解(减轻) 来的不利后果减小到可接受范围内 Transfer转移 Deflect or share (eg. Insurance, warranties)转移或分担(保险,担保) Acceptance接受 Accept or retain consequences. 2 types: Active Acceptance (develop a contingency plan) or Passive Acceptance (no action).接受或保留结果。2种形式:主动接受(开发一个应急计划)或被动接受(不采取任何行动) Numbers to Know需要知道的数字 Cost Estimates:成本估算 Order of Magnitude (ballpark estimate)量级(棒球场估算) Budget预算 Definitive确定 1 sigma 2 sigma 3 sigma 6 sigma Documentation文档
Risk Management Plan 风险管理计划– would most likely be developed during scope planning phase of the scope management process.大多数情况下,风险管理计划是在范围管理进程的范围计划编制过程中开发出来的
The range of an estimate with the smallest range is the least risky.估算的范围越小引发的风险越小 -25% +75% -10% -5% 68.3% 95.5% 99.7% 99.99% +25% +10% 21
ESSENCE OF PMBOK & PMP EXAM
QUALITY Project Quality Management – processes required to ensure that the project will satisfy the needs for which it was undertaken. 项目质量管理-保证项目满足其承担需求所需要的过程。
Quality is the conformance to requirements/specifications and to fitness of use. 质量是与需求/规范的一致性,以及使用的适当性。
Quality function deployment – provide better product definition and product development. Its main feature are to capture the customer’s requirements,
ensure cross functional teamwork, and link the main phases of product development. 质量功能展开- 提供更好的产品定义和产品发展。它主要特征是捕捉客户需求,保证交叉功能的联合作业,并连接产品开发的主要阶段。 Rework – action taken to bring a non-conforming item into compliance. Rework is a frequent cause of project overruns. 返工- 为了使不一致的项达到一致而采取的行动。返工是项目超限的常见原因。 Quality Variable A quality characteristic that is measurable 质量变量 可以测量的质量特征 Quality Attribute A quality characteristic that is classified as either conforming or nonconforming 质量品质(属性) 被分类为一致或不一致的质量特征 Benchmarking Comparing practices of other projects. Provides a standard to measure performance (time consuming). (e.g. 基准比较分析(标杆) investigating quality standards that other companies are using) 与其它项目的实践进行对比。提供测量绩效(时间消耗)的标准。(如:调查其他公司正在使用的质量标准) Statistical Analysis Involves determining the probability of an occurrence 统计分析 包括确定一个事件发生的概率 Trend Analysis Uses mathematical techniques to forecast future outcomes based on historical results; used to measure technical, 趋势分析 cost, and schedule performance 使用数学工具基于历史结果来预测将来的结果;用于测量技术、成本和时间进度绩效 Quality Audit Structured review of other quality management activities performed to identify lessons learned (used for process 质量审计 improvement) Part of Quality Assurance. Provide management confidence that the project will satisfy relevant quality standards. 对其它质量管理活动结构化的审查,目的是识别质量保证部分的经验教训(用于过程改进)。提供项目将完成相关质量标准的管理信心。 Inspection Prevent errors from reaching the customer before delivery to the customer. Can be done throughout product 检查 development. 在产品交付到客户之前,阻止错误到达客户。可以在产品发展的整个过程实施检查 Design of A technique to identify which variables have the most influence on overall outcomes (part of Quality Planning) (e.g. Experiments analyze the color/size combination that will contribute most to the functionality of the new product). Can be applied to 试验设计 cost and schedule tradeoffs. 一种帮助识别对全部结果产生最大影响的变量因素的技术(质量计划编制的一部分)(如:分析不同的颜色/尺寸组合将是对新产品功能的最大贡献)。可以被用于对成本和时间进度的权衡。 Flow chart Help analyze how problems occurs 流程图 帮助分析问题如何产生 Attribute Sampling Measures whether or not the results conforms to specifications 属性(品质)抽样 测量结果是否符合规格。 Variable Sampling Are characteristic you want to measure (size, shape, weight, etc…). An attribute is what you are measuring. The 变量抽样 result is rated on a continuous scale that measures the degree of conformity. 你想测量的特征(尺寸,外型,重量等)。一个属性是你测量的对象。结果是在测量符合程度的连续坐标上排列表示。 Assignable Causes Data point on a control chart that requires investigation 非机遇原因 在控制图上需要调查研究的数据点 Specification Limit Shows customer’s expectations for quality (on a control chart) 规范界限 表示客户对质量的期望(在控制图中) Control Chart …help newly assigned project manager determine whether the project is out of control (in order to verify quality level). 控制图 Can be used to monitor project management processes such as coscard, schedule variance, volume and frequency of scope changes, and errors in project documents. 帮助新指派的项目经理确定项目是否失去控制(为了核实质量层次)。可以监控项目管理过程,比如,coscard,进度偏差,范围变更的幅度和频率,以及在项目文件中的错误。 Statistical Control Are used to monitor process variations overtime. Help people understand and control their process work. Chart 用于监控超时的过程变化。帮助人们了解和控制他们的过程工作。 统计控制图 22
ESSENCE OF PMBOK & PMP EXAM
“Out of Control” Non-random points that are still within the upper and lower control limit 失去控制 仍然在上下控制线内的非随机点。 Upper and Lower Acceptable range of variation of a process. [These limits are set based on the company’s quality standards. The Control Limit on a control limits are determined from data obtained from the process itself.] Control Chart 过程变化可接受的范围。[这些限制的设立是基于公司的质量标准的。控制限决定于包含在过程本身的数据。] 控制图的上下控制线 Specification Limit Fixed by the customer 规范界限 客户确定 Pareto Diagram Used to show how results were generated, by type or category of identified cause 帕累托图 用于显示被识别原因的类别或种类是如何产生结果的。 Ishikawa Made popular Pareto Chart, Cause-and-Effect Diagram and Control Chart Ishikawa逻辑图 通俗化的帕累托图,因果分析图,控制图 Taguchi Method Is used to estimate the loss associated with controlling or failing to control process variability. If you select good Taguchi方法 design parameters, you can produce products that are more forgiving and tolerant. The tool helps determine the value or break-even point of improving a process to reduce variability. 用于估算对过程变量的成功控制或失败控制与损失的关系。如果你选择了好的设计参数,你可以生产客户对其有更多宽容和忍耐的产品。这个工具帮助确定为减少可变性而改进过程所得到的价值或平衡点。 ISO 9000 Provides a basic set of requirements for a quality system, without specifying the particulars for implementation. ISO 9000 为质量系统提供了一套基本要求。对执行没有特殊的说明。 Checklists Used to verify that a set of required steps has been performed in quality control process 检查表 用于核实一系列要求的步骤在质量控制过程中是否已经实施 “Statistically Determine if problems are related before planning what to do about them Independent” 在计划去做之前确定问题之间是否有关联。 统计独立 Mutually Exclusive If two events cannot both occur in a single trial (?) 相互排斥 在同一个试验中两个事件是否不能同时发生(?) Special Cause Unusual event 特殊因素 特殊事件 Random Cause Normal process variation 随机因素 正常过程变动 Cause and Effect (1) Creative way to look at actual causes and potential causes of a problem Diagram (1) 查找问题的实际原因和潜在原因的创造性的方法 (Fishbone) (2) Process of constructing helps stimulate thinking about an issue; helps to organize thoughts; generates discussion 因果关系图 (2) 刺激关于问题的思考;帮助组织思路;产生讨论 (鱼骨图) (3) Used to explore a wide variety of topics (3) 用于探索主题的广泛多样性 (4) Also known as Ishikawa or Fishbone diagram (4) 也被称为Ishikawa或鱼骨图 Quality Planning Refers to potential problems. Although it usually occur during planning phase, it can occur during execution if there is 质量计划编制 a change. 涉及潜在的问题。尽管它通常发生在计划阶段,但是它可以发生在实施过程,如果产生变更的话。 Quality Control Refers to specific performance of a task (measuring quality and comparing results to the quality plan) 质量控制 涉及任务的特殊绩效(测量质量并比较质量结果和质量计划) Quality Assurance Refers to overall quality requirements (standards) (e.g. evaluating overall project performance regularly) 质量保证 涉及全部质量要求(标准)(如:有规律的评估全部项目绩效) Cost of Quality 质量成本 Planning 计划编制 Training 培训 Process Control 过程控制 Design and process validation 设计 Non-Conformance (most accurate) 不一致成本(非常精确) Scrap 废料 Rework and repair 返工和修理 Additional Material 额外材料 Repairs and service 修理和服务 Conformance 一致成本 23
ESSENCE OF PMBOK & PMP EXAM 和过程确认 Test and evaluation 测试和评估 Quality audits 质量审计 Maintenance and calibration 维护和校准 Inspection 审查 Field testing 实地测试 Impact of Poor Quality 质量差的影响 Increased cost 增加成本 Decreased productivity 降低生产率 Increased risk and uncertainty 增加风险和不确定性 Increased costs in monitoring 增加监控成本 Complaints 抱怨 Liability 责任 Product recalls 产品召回 Field service 现场服务 Expediting 加速处理
Goal of the cost of quality program should be 3 - 5% of total value.质量程序的目标成本占总成本的3-5% Cost of non-quality is estimated to be 12 - 20% of sales.非质量成本接近于销售的12-20%
Cost of Quality Includes Prevention Costs (training), Appraisals Costs (inspection/testing) and Internal (scrap, rework)/External (warranty) Failure costs
质量成本包括预防成本(培训),评估成本(检查/测试)和内(废料,返工)外(担保)部缺陷成本 Management is 85% responsible for quality. The team member is ultimately responsible for quality management. The project manager is primarily
responsible for quality management.管理层负责85%的质量成本。团队成员对质量管理负有最终责任。项目管理者对质量管理负有主要责任。 Two components of product availability are reliability and maintainability.构成产品有效性的两个成分是可靠性和可维护性
To effectively use statistical quality control, the project team should know the differences between special causes and random causes. 为了有效地使用统计质量控制,项目团队应该知道特殊因素和随机因素的区别。
Sampling and probability are the most important topics to understand in statistical process control. 样本和概率是了解统计过程控制最重要的概念。
Top management should direct continuous improvement. 高层管理应该指导持续改进。
Quality control measurement are records of quality control testing and measurement in a format for comparison and analysis (input to quality assurance).
质量控制测量是用某一格式所做的记录,目的是为对比和分析所作的质量控制测试和测量。 Documentation 文件 ? ?
Quality Management Plan – describes method for implementing quality policy project quality system and organizational structures, responsibilities, procedures, processes and resources needed to implement project quality management.
质量管理计划 – 描述了应用质量政策、项目质量系统的方法和运用组织结构、责任、程序、过程和所需资源来实现项目质量管理
PROCUREMENT采购
Project Procurement Management 项目获取管理- the processes required to acquire goods and services from outside the performing organization.此
过程需要从外部执行组织获取货物和服务。
Make or Buy Decision做出/购买决定 – it is generally better to do the work yourself if using an outside company means you have to turn over highly
confidential proprietary data to other company.如果你用外部公司有可能泄漏机密数据,那最好亲自执行此工作。 Contract Types and Risk合同类型和风险 Cost Plus Percentage of Cost No valid for federal contracts对政府合同无效? 成本加成本百分比(CPPC) Cost Plus Fixed Fee (CPFF)成Used for research and development contracts (which generally have low level of detail in the scope); fixed 本加固定费用 fee can change if there is a change to the contract (usually through change orders). The risk rests with the buyer.用于研究和发展合同(通常在范围细节上处于较低水平);如果合同有变化,固定费用可以变更(通常是贯穿变更订单始终)风险取决于购买者。 Cost Plus Incentive Fee Buyer and seller share in savings based on predetermined %s; long performance periods and substantial (CPIF)成本加激励费用 development and test requirements (incentive to the vendor to perform on or ahead of time)购买者和销售者根据预先制定的百分比分担储蓄;长时执行周期,实质发展和测试要求(激励卖主及时或提前完成任务) ? In Cost plus contract, the only firm figure is the fee在成本加合同中,唯一的硬性指标是费用 Fixed Price Plus Incentive High-value projects involving long performance periods高价值的项目包括长时执行周期 Fee (FPI)固定价格加激励费用 24
ESSENCE OF PMBOK & PMP EXAM
Firm Fixed Price (FFP)稳定的Reasonably definite specifications (e.g. SOW). Shift risk to seller. Good when deliverable is not a core 固定价格 competency.适度的明确说明书。将风险转嫁给销售者。可交付使用不是核心竞争力时很好。 Time & Material (T&M)时间和原Good if the buyer wants to be in full control and/or the scope is unclear/not detailed or work has to start 料 quickly. Profit factor into the hourly rate.购买者希望被完全控制,或范围划分不明确,或任务快速启动都很好。利润要素进入每小时速率。 Fixed Price Award Fee固定价格“bonus” to the seller based on performance (e.g. 100K + 10K for every designated incremental quality level 授予费用 reached. Purchase Order买卖订单 A form of contract that is normally unilateral and used for simple commodity purchases.用于一般消费品购买的单方面的合同形式 Contract type Vs Risk和同类型FFP – FPI – CPIF – CPFF – CPPC 和风险 Fixed Price – Cost Reimbursable – T&M Buyer’s risk from low to high购买者的风险从低到高 Seller’s risk from high to low销售者的风险从高到低 Elements of a Contract合同基础 Offer提议 Assent to certain terms by both parties双方一致同意一些条件 Acceptance接受 Agreement, written or spoken协议,书面的或口头的 Consideration报酬 Something of value有价值的东西 Legal Capacity法律能力 Able to contract有合同效力 Legal Purpose法律目的 No violation of public policy不违反公众政策 Stages of Contract Negotiation 合同谈判进程 Protocol草案 Introductions导言 Probing探通术 Identify concerns, strengths, weaknesses识别利害关系,强势,劣势 Scratch bargaining商讨 Actual bargaining实质性商讨 Closure收尾 Positions summed up决定合计 Agreement协议 Documenting文档 Specification 说明书- precise description of a physical item, procedure, or service. The SOW supplements the specification in describing what must be done to complete the project.关于物体、进程或服务的详细说明。SOW是描述项目完成所需工作的补充说明。 Privity默契- legal relationship that exists between any contracting parties (e.g. if company “A” hires “B” and “B” subcontract to “C”, “C” is not legally
bound by anything “A” can say; the privity is with “B”)存在于任何直接联系者之间的合法关系(例如:公司A雇用B,B转包给C,C对于A所说的任何事情不负有法律责任,C的默契人是B) Waiver弃权 - a party can relinquish rights that it otherwise has under the contract. Forebearance can mature into waiver. Retainage – withholding of funds under contract.依照合同扣除资金
Warranty 担保- assurance of the level of quality to be provided对所承诺质量水平的保证 A contract ends by: 合同终止于 Successful performance成功的业绩 Mutual agreement相互协商 Breach of contract违约 Last two are Termination最后两个是终止 Terms and Conditions期限和条件 – the project manager must uphold the Terms and Conditions of the contract, even if it meets the needs of the project, it has to also meet the requirement of the contract.项目管理者必须支持合同的期限和条件,即便要符合项目需求,也必须符合合同要求 Liquidated damages – 清算赔偿金
Contract Control System vs Project Control System 合同控制系统和项目控制系统– they both include procedures. The contract control system
requires more documentation and more signoff.它们都包括进程。合同控制系统需要更多的文件和签名。 Work Authorization Systems任务授权系统 – can be used to coordinate/control what time and sequence work is done. It helps with integrating tasks
into a whole.用于调整/控制工作在何时以何种次序进行。它帮助将任务集成于一体。 Performance Scope of Work 任务执行范围– describes the performance – not the functionality-- required by the customer描述而非泛泛而谈用户所要求
的执行情况 Independent Estimate独立评估 – most concern with costs, comparing cost estimates with in-house estimates or with outside assistance (part of
Source Selection)多数关注成本,在内部评估和外部补助(资源选择的一部分)之间比较成本估算 Procurement Audit获得审计
– structured review that flush out issues, and set-up lessons learned. Helps ensure problems are resolved for future projects. Identify successes and
failures that warrant transfer to other procurements.回顾所有涌现的问题,学到的经验教训。确保对于未来项目存在的问题都已经得到解决。区别成功与失败
25
ESSENCE OF PMBOK & PMP EXAM
Beneficial Efficiency 法律效力– when the work is being used for the intended purpose and has been certified当任务用于被确定的目的并已被鉴定 Terminating contract for Convenience为方便而定的终止合同 – if a project is terminated before it is complete, the level of extent of completion should
be established and documented.项目在完成之前终止,需要建立和记录项目完成程度的水平。 Contracting Centralized集中订立 + More economical更经济 + Easier to Control易控 + Higher degree of specialization (expertize)高度专业化 + Orders can be consolidated形成固定化订单 - May become a bottleneck可能形成瓶颈 - Less attention to special needs不太关注项目具体要求 Negotiating Tactics谈判策略 Deadline最终期限 Surprise吃惊 Limited Authority有限权力 Missing Man不露面的人 Fair and Reasonable公平合理
Documentation文件 ?
Statement of Work 工作说明– describes the procurement item in sufficient detail to allow prospective sellers to determine if they are capable of providing the item. (Scope Statement between Client and PM / SOW between PM and Seller)按合同的要求对产品提供详细的叙述性说明以使潜在供方判断是否有能力提供相应服务(范围说明存在于PM和客户之间/工作说明存在于PM和供应商之间)
Strategic Delay战略延迟 Reasoning Together一起论理 Withdrawal撤退 Unreasonable不合理 Suggesting Arbitration建议仲裁 Fait Accompli既成事实 Decentralized发散订立 + Project Manager has more control PM更大控制权 + Contracting personnel are more familiar with project 合同订立人员对项目需求更熟悉 + More flexible and adaptable to project needs针对项目需求,更具适应性和灵活性 - Duplication of contracting efforts合同工作重复性 - Higher costs高成本 - No standard policies没有形成标准化的合同政策
INTEGRATION综合
Project Baseline 项目基线– should be changed for all implemented changes. Sometimes, certain classification of changes get automatic approval on a
project and do not need Change Control Board approval.依所有执行中的变更而更新。有时,某种特定的变更分类可以不通过CCB 直接变更 Changes 变更- if the functional manager wants to make a change to time associated to a task (change in goals and objectives of the Charter) and there
is not enough reserve, senior management (not the Project Manager) should authorize the change. The best method to control changes on the project is to look for sources of change. The best method to deal with changes is to direct the changes to the Change Control Board.如果职能经理想作出一个与任务相关的时间变更(战略目标和章程的产品目标)并且没有足够的储备,高级管理层(不是PM)应该核准变更。项目中控制变更的最好方法是控制引起变更的原因。处理变更的最好方法是直接将变更呈给CCB。 Change Control System变更控制系统 – must also include procedures to handle changes that may be approved without prior review (e.g. result of an
emergency)必须也包括一个绿色通道(例如:紧急情况) Schedule Change Control System进度变更控制系统 – can include the paper, systems and approvals for authorizing changes. The project manager is
normally not the approval authority, and not all the changes approved可以包括文档,跟踪系统和变更的批准层次。项目管理者一般不是被公认的权威人士,不是所有的变更都能被批准。 Project Plan项目计划 – as an input to team development, the project plan describes the technical context within which the team operates.作为团队发展
的输入,项目计划描述团队工作的技术框架。
PROFESSIONAL RESPONSIBILITIES专业职责
Routine Government Fee (Transfer Fee)常规政府费用(转会费) – only government official can collect routine government fees (this is not a bribe)只
有政府官员可以收取常规政府费用(这不是贿赂) Company Policies公司政策 - It is the project manager’s professional responsibility to ensure that company policies are followed during the project.在项
目执行过程中遵循公司政策是项目管理者的专业职责。 Copyright laws版权法 – do not violate不能违反 Employee mistake职员错误
26
ESSENCE OF PMBOK & PMP EXAM
- when a team member makes a mistakes, allow him to save face and to fix the problem. Try to workout an issue before escalating. Exception: if it is
not considered a project related issue (e.g. harassment), it should be reported directly to the employee’s manager.当团队成员犯错误时,允许他们保留面子,处理问题。尽量在事态发展之前检测出问题。例外:如果不是考虑与项目相关的问题(如:折磨),应该直接向员工经理汇报。 Do not make illegal payments, report thefts不要进行非法付款,报告偷窃行为
Company and Customer’s Interest公司和用户的利益 - professional responsibility requires the investigation of any instances where the legitimate
interests of the customer may be compromised. If such compromise is found, action must be taken. Protect your company’s interests专业职责要求调查涉及用户合法利益的任何情况。如果此类情况被发现,必须采取行动。保护你公司的利益。 Budget tampering预算贿赂 - presenting anything besides your original estimate to allocate more to the budget is inaccurate and calls into question
your competence and integrity as project manager (e.g. if a customer ask to estimate “pessimistically”, you should add as a lump sum contingency fund to handle project risks)投入比最初评估预算多的任何费用都是不正确的,这将对项目管理者的能力和诚实人品带来质疑(例如:如果客户需要“悲观的”评估,你应该增加一小部分的意外资金应对项目风险) Rights权力 - do not do business with a country where there is a clear violation of the fundamental rights (e.g. non-discriminating treatment).不要和有明
显有违基本原则(例如:无差别待遇)的国家合作
POSSIBLE EXAM QUESTIONS考点 Scope Questions范围 Why is a careful and accurate needs analysis important? 为什么一个仔细的准确地需求分析是重要的? How is a change control board used? Can there be more than one? 如何使用变更控制委员会?它是唯一的么? What is the purpose of the project charter? How does it benefit the project manager? 项目章程的作用是什么?它对项目管理者有什么益处? To make sure customer or stakeholder expectations can be identified and satisfied.确保用户和干系人的需求能够被正确的识别和满足 To approve or reject change requests according to responsibilities defined and agreed upon by key stakeholders. Multiple CCBs may be used on large projects. 由项目干系人正式设立的组织,批准或拒绝变更需求。 多变更控制委员会可用于大型项目。 To formally document the existence of the project, including the business need that the project was undertaken to address and the product description. It provides the project manager with the authority to apply organizational resources to project activities. 它是项目存在的正式文档形式,包括商业需求和产品描述。授予项目经理为执行项目活动而使用组织资源的权利。 A forecasting technique used to gather information; it relies on gathering expert opinions. Usually goes three rounds. Obj.: Gain consensus of expert opinions. 通过收集信息对未来进行预测的工具;它依赖于收集专家意见。通常进行三次循环。目标是:获得专家意见的某种共识。 To describe how project scope will be managed and how scope change will be integrated into the project. 描述项目范围如何被管理及范围变更如何被整合到项目之中 To provide interested parties with work package descriptions and other planning information such as schedule date, cost budgets, and staff assignments for each WBS element. 有利于为可交付成果提供工作包的描述及其它计划编制信息,如任何一个工作分解结构要素的进度日期、成本预算、人员分配。 Each task should be broken down into work packages that require no more than 80 hours to complete. 每一项工作都应该被分解为完成时间不超过80小时的工作包 Scope verification is primarily concerned with acceptance of the work results; quality control is primarily concerned with the correctness of the work results. 范围确认主要是针对工作结果的可接受性;质量控制主要针对工作结果的正确性 (1) Establish unambiguous and realistic objectives 确定清晰的实际的目标 What is the Delphi Technique? 什么是德尔菲技术? What is the purpose of the scope management plan? 范围管理计划的作用是什么? What is the purpose of the WBS dictionary? 工作分解结构字典的作用是什么? What is the 80 hour rule? 什么是80小时规则? What is the difference between scope verification and quality control? 范围确认和质量控制之间的不同之处是什么? What are the three steps involved in MBO? 目标管理 27
ESSENCE OF PMBOK & PMP EXAM Scope Questions范围 的所包括的三步是什么? (2) Periodically evaluate whether project objectives are being achieved 阶段性评估项目目标是否完成 (3) Act on the results of the evaluation. 在评估结果的基础上采取措施 At the end of the project. 在项目收尾(管理收尾)的时候 Problem Solving/confrontation because both parties can be fully satisfied if the work together to find a solution that satisfies both their needs. 解决/面对问题,因为双方对他们共同选择的方法都会满意 (1) Organizational interfaces 组织界面 (2) Technical interfaces 技术界面 (3) Interpersonal interfaces 人际关系界面 They can occur simultaneously. 它们经常同时发生 Traditional approach: workers are self-centered, lazy, lacking ambition. Managers organize the elements of the productive enterprise in the interest of economic ends.传统的方法:工人自私,懒惰,没有上进心。管理者要广泛应用于以结果为导向的生产部门。 Workers are not by nature resistant to organizational needs; they are willing and eager to accept responsibilities and are concerned with self-growth and fulfillment. Managers should try to create an environment where workers can achieve their own goals.工人愿意工作;他们愿意和期望承担责任并关注自我实现和满足。管理者应该尽量创造能让工人实现他们目标的环境。 A specific type of organizational chart that shows which units are responsible for which work items组织图的一种具体类型用于显示哪一个部门负责哪块工作 It identifies when a particular resource is or will be working on a particular task 描述何时某项特殊的资源被消耗于某项特别的任务 It complicates team development because team members are accountable to both a functional manager and a project manager. 复杂化了团队发展因为团队成员既对职能经理负责也向项目经理负责。 Functional, Matrix, and Project zed职能型、矩阵型、项目型 It holds that people tend to be highly productive and motivated if they believe their efforts will lead to successful results and they will be rewarded for their success.人们如果相信他们的努力极可能得到成功的结果同时会因为成功而得到奖励,那么他们将被激励并具有很高的生产力 Addressing conflict directly by getting the parties to work together to define the problem, collect information, develop and analyze alternatives, and select the most appropriate alternative.直接面对冲突所有各方一起定义问题,收集信息,开发分析应对方案,选择最合适的方案 Pay, attitude of supervisor, and working conditions. 薪水、上级的态度、工作环境 Poor hygiene may destroy motivation, but improving hygiene factors in not likely to increase motivation. Motivators are an opportunity to achieve and experience self-actualization.恶劣的卫生因素可能损害动机,但改善的卫生因素并不能增强动机。激励理论促进工作完成、自我实现。 Senior and functional management高层和职能经理 Weak matrices are similar to functional organizations. Strong matrices are similar to projectized organizations (with balance of power tipped toward the project manager)若矩阵类似职能型组织,强矩阵类似项目型组织(权力天平倾向于项目经理) One in which a separate, functional organization is established for each project. Personnel are assigned on a full-time basis. 针对每一个项目制定的一个独立的职能型组织,成员被分配全时工作 Project manager’s concern is that the team may not be focused on completing the project (team looks for new mandate or tries to extend the length of the project). According to PMI, the biggest problem in Administrative Closure is retaining team members until closure of the project. 项目经理关注团队能否聚焦于项目的完成(团队成员经常寻找新的机会或试图延长项目历时)依照PMI的理论,管理收尾的最大难题是保留项目成员直至项目结束。 When should scope verification occur? 范围确认应何时发生? HR Questions Which are the five methods of managing conflict is recommended? Why? 在解决冲突的5种方法中哪一种是被推荐的?为什么? What are the three types of project interfaces that serve as inputs to the organizational planning process. When can they occur? 作为组织计划进程输入的三种项目界面是什么?它们什么时候出现? What is McGregor’s Theory X? What is management’s role in this approach? 什么是麦克格雷德的X理论? 管理在这个方法中所扮演的角色是什么? What is McGregor’s theory Y? What is management’s role in this approach? 什么是麦克格雷德的Y理论? 管理在这个方法中所扮演的角色是什么? What is an organizational breakdown structure (OBS)? 什么是组织分解结构? What is the purpose of a resource Gantt chart? 资源甘特图的作用是什么? Does the matrix form of project organization facilitate or complicate project team development? 项目组织的矩阵形式是简化了还是复杂化了项目团队发展? Name three major forms of project organizational structure. 命名项目组织结构的三种主要形式 What is the expectancy theory? 什么是期望理论? What is problem solving/confrontation? 什么是问题解决/面对? Give three examples of hygiene factors in Herzberg’s theory of motivation. How do they affect motivation. 给海兹伯格动机理论的卫生因素举三个例子。它们如何影响动机 Who is responsible for addressing individual performance problems? 谁对个体绩效问题描述负责? Describe the difference between a weak matrix and a strong matrix. 描述弱矩阵和强矩阵之间的差异 What is a projectized organization?什么是项目型的组织 28
ESSENCE OF PMBOK & PMP EXAM Communications Questions沟通 What is a project \benefit? 什么叫项目作战室?它的主要用处是什么? A single location for the team to get together for any purpose. It provides a repository for project artifacts, records, and up-to-date schedules and status reports. It gives an identity to the project team.为解决任何目标而使团队一起工作的专有的场所。它提供一个知识库存储项目信息、记录、更新的进度和状况报告。它提供给项目团队统一的标示。 (1) (2) (3) (4) (5) (6) What information will be collected收集什么信息 How the information will be collected怎样收集信息 How and to whom the information will be distributed信息怎样发布及谁发布,发布给谁 When the information will be communicated何时传达信息 How to obtain information between regular communications获得信息的途径(媒介) How the Communications Plan will be updated through the project沟通计划在项目中怎样被更新 Describe the six parts of a Communications Management Plan.描述沟通管理计划的六个部分 What is variance analysis? 什么是偏差分析 What are six actions project managers should take to ensure effective project team communications? 项目管理者确保项目团队进行有效沟通的六点措施是什么? Comparing actual project results to planned or expected results in terms of cost, schedule, scope, quality, and risk.将实际结果和计划进行对比 (1) (2) (3) (4) (5) (6) Be an effective communicator有效沟通者 Be a communications expeditor联络者 Avoid communications blockers避免沟通阻断器 Use a tight matrix使用紧密矩阵式结构(紧密矩阵不等于强矩阵) Have a project war room作战室 Make meetings effective有效会议 What is active listening? 有效倾听? What is major cause of conflict with functional managers? 导致职能经理间冲突的主要原因 What is most difficult conflict to deal with? 需要解决的最困难的冲突是什么 What is earned value analysis? How is it used in performance reporting? 什么是挣值分析?在绩效报告中如何使用? What is the tool for used for communication planning?沟通计划的工具是什么 What is the most important characteristic for a project manager? 项目管理者的最主要的特点是什么? What factor has the greatest effect on the project's communication requirements? 对项目沟通要求影响最大的因素是什么? What is the primary condition leading to conflict in both the weak and strong matrix organizations? 在弱矩阵和强矩阵组织中,导致冲突的主要条件是什么? When is a project considered closed?项目何时正式结束? Time Questions What is the critical path? 关键路径是什么? Listening in which the recipient is attentive and asks for clarification of ambiguous messages移情式聆听是专著和要求对不明确信息澄清的一种聆听方式。 Schedules进度 Personality conflicts个性冲突(人际问题) An analysis that integrates cost and schedule measures. It is used to help the project management team assess project performance.综合了成本和进度衡量标准的一种分析方法。帮助项目管理团队评价项目绩效。 Stakeholder analysis干系人分析 Ability to work well with others和其他人愉快的工作的能力 The project's organizational structure项目的组织结构 Ambiguous jurisdictions. They exist when two or more parties have related responsibilities, but their work boundaries and role definitions are unclear.不明确的权限。两个以上的职责关系,但它们的工作界限和角色定义不明确 When the archive is completed. All project docs goes into the archives; this is the last thing to create before releasing the team.存档完成。所有项目记录归档;最后一件工作是团队成员遣散 The longest path through the network which represents the shortest amount of time in which the project can be completed.项目网络图中最长的一条路径,项目完成历时时间最短。 Taking action to determine how to obtain the greatest amount of duration compression for the least incremental cost; generally increases cost.一种试图用最小的成本投入换取最大的历时压缩 Compressing the schedule by overlapping activities that would normally be done in sequence; may result in rework and increased risk; logical relationships are modified将原本顺序进行的活动通过并行实施而压缩进度的方法;通常造成返工并带来风险,改变逻辑关系 By using positive float available on non-critical paths, schedule by smoothing or leveling peaks and valleys of resource utilization利用非关键路径的可浮动时间,资源利用的负载水平情况调整进度表 Assessing the number of work periods likely to be needed to complete each activity评估每一必须完成活动的定量工作周期 What is crashing? 什么是赶工? What is fast tracking? 什么是快速跟进 How does resource-leveling work? 如何进行资源平衡? What is activity duration estimating? 什么是活动历时估算 29
ESSENCE OF PMBOK & PMP EXAM Communications Questions沟通 What is a dummy activity? 什么是虚活动? What is slack or float? Free float? 什么是时差?自由时差? One that consumes no time or resources; it shows only dependency一种不消耗时间和资源的活动,只代表依赖关系 Amount of time that an activity can be delayed without delaying project. Free float is the amount of time an activity can be delayed without delaying the early start of the next activity时差是活动在不延误项目情况下可以延迟的时间。自由浮动时间是活动再不延误紧后活动最早开始时间情况下的可延迟时间 Required waiting time between activities活动间必须等待的时间 Concept of including acquisition, operating, maintenance, and disposal costs; total cost of ownership包括获取,运行,维护和废弃成本;所有者的总成本 Contract Closure includes an audit.合同收尾包括采购审计 What is lag? 什么是滞后? Cost Questions What is life cycle costing? 什么是全生命周期成本? Which of the following includes an audit; Administrative Closure or Contract Closure? 下列哪一个包括采购审计:行政收尾还是合同收尾? What is \什么是会计科目表? Coding structure used to report financial information in general ledger. Code of accounts is numbering of WBS elements编码结构用于报告总账目表中的财务信息。编码结构是工作分解结构要素的唯一编码。 They represent the basic level at which project performance is measured and reported.它们描述了项目绩效报告和标准的基本水平 Initiation启动 What are cost accounts? 什么是成本账号? Risk Questions Generally speaking, in what project phase are risk and opportunity greater than the amount at stake by the widest margin? 总体来说,在哪一阶段风险带来的机遇最大? Describe the difference between an internal risk and an external risk.描述内部风险和外部风险的不同之处 What is purpose of a risk management plan? What should it include? 风险管理计划的目标是什么?它包括哪些? An internal risk is under the control or influence of the project team; external is beyond control or influence.项目团队对内部风险进行控制并施加影响,外部风险超出了控制和可施加影响的范围 To document the procedures that should be used to manage risk throughout the project. It should include the risk identification and risk quantification; how contingency plans will be implemented; how reserves will be allocated.贯穿于整个项目过程的说明如何管理风险的文档化程序。包括风险识别和量化;应对计划如何执行;如何分配储备。 A provision in the project plan to mitigate cost and/or schedule risk. Management reserves are for “unknown unknowns” and contingency reserves are for “known unknowns”.降低项目成本和进度风险的一种预防措施。管理储备应对“未知未知”,应急储备应对“已知未知” Cost and Schedule, used to reduce the chance of overruns in either area用于减小成本和进度任何一方的超限可能性 During Implementation and Close-out - the Amount at Stake is high though risk has decreased. Risk is highest during Initiation and Planning.执行和收尾期间—高风险数量减少。启动和规划阶段风险最大。 Project manager项目经理 Evaluate them on a qualitative basis. What is a reserve? 什么是储备资源? What are the two most common types of management reserves? How are they used? 管理储备的两个一般形式是什么?怎样使用它们? When is the highest risk impact generally occur? 一般而言,什么时候出现最高风险影响? Who is ultimately responsible for identifying and managing risk? 谁负责识别和管理风险? You are finding it difficult to evaluate the exact cost consequences of risks. You should:你发现准确地评估风险的成本原因很难。你应该: In what circumstance would you have to update the Risk Response Plan? 在什么情况下你要更新风险应对计划? What should be done after competing/updating the Risk Response Plan? 完成/更新风险应对计划之后应该做些什么? How do you address unknown risks? 怎样定位未知风险? What is a known-unknown risk? 什么是已知-未知风If a risk occurs and has a greater impact on the project than what was anticipated. (part of Risk Monitoring and Control)当风险发生后对项目所带来的影响大与预期时(风险监控的一部分) Add tasks to the WBS在工作分解结构上添加任务 By applying a general contingency based on past experience通过过去申请一般的偶然事件应对所积累的经验 Risk that can be identified as possibly happening (e.g. Flood if a business is located in 30
ESSENCE OF PMBOK & PMP EXAM Risk Questions 险? Quality Questions What are control limits as used in control charts? 控制图表中的控制界限是什么? Define \为kaizen定义 What is gold-plating? 什么是镀金? What is the effect of sample size on the standard deviation? 样本大小对偏差的影响是什么? What is the Rule of Seven? 七值定律是什么? Control limits describe the natural variation of a process. Assignable cause is a point outside the control limits.控制界限描述过程的正常偏差。可找出原因的特殊事件是超出控制限度的点。 Continuous improvement持续改进 Giving the customer more than what was required. It has no value.提供给客户超出他们需求范围的东西。是没有价值的。 Whenever sample size increases, the standard deviation decreases.随抽样数量的增加,标准偏差降低。 If seven or more observations in a row occur on the same side of the mean, even though within control limits, they should be investigated as an assignable cause.如果有七个以上的观测点落在均值的同一侧,虽然在控制限度之内,它们应该按特殊原因进行研究。 An inventory control approach that attempts to reduce work -in-process inventory; there is no extra stock kept in reserve通过减少库存物资(过程存货)降低成本,储备中没有多余的库存 Cost of conformance and cost of nonconformance一致性和非一致性成本 They show how various causes and subclasses relate to create potential problems. After these are identified, corrective action can be taken. 反映潜在问题与造成问题的因素间的联系。它们被确定后,纠正行动可以实施。 To describe how the project management team will implement its quality policy描述项目管理团队如何制订项目的质量方针。 A bar chart in which data are arranged in descending order of importance. It puts issues into an easily understood framework.一种柱状图,数据按重要性递减排序。它很容易清楚的反映问题。 A relatively small number (20%) of causes will typically produce a large majority (80%) of the problems or defects. 20%的原因造成80%项目问题。 The individual. The project manager has overall responsibility. 个人(谁干活谁负责)。项目经理对整体质量负责。 A technique used to determine whether a product can be produced cost effectively by the organization.判断组织生产某项产品总成本的一种技术(自己做和外购哪个更合适)。 Inducements provided by the buyer to the contractor in an attempt to ring the objectives and interests of the contractor in line with those of the buyer; positive and negative. Usually cost effective协调买卖双方目标和利益。分积极的和消极的,通常降低成本。 Meetings with prospective sellers to ensure that they have a clear, common understanding of the procurement; held before sellers prepare their proposals. 确保潜在供应商清晰的公平的理解需求。在供方提供他们的建议书前召开。 Proposal, Scope of Work, Terms and Conditions (which should be the result of a risk analysis), general provision, special provisions (which takes precedence over general provisions) 建议书,工作说明书,工期和约束条件(需要进行达到目标的风险分析),常规规范,特殊规范(优先于常规规范) Take action. (1) Contact seller and ask what’s going on. (2) let seller know he is in default (e.g. default letter). 采取行动(1)与合同供方联系询问原因(2)让供方知道已经违约了 (如:质询函) Integration Questions Lessons learned are completed by? 经验教训如何获得? Project team通过项目团队 a flood zone) 能被识别的可能发生的风险(例如:在洪水多发地区预测可能发生的洪灾) What is Just-In-Time? “零库存”是什么? What is meant by the cost of quality? 质量成本包括什么? How are cause and effect diagrams used? 因果图用于? What is the principal purpose of the Quality Management Plan? 质量管理计划的首要目标是什么? What is a Pareto Diagram? 什么是帕雷托图? What is the underlying concept of a Pareto Diagram?什么是帕雷托图的基本概念? Who is ultimately responsible for quality? 谁对质量最终负责? Procurement Questions What is make or buy analysis? 什么是自制或购买分析? What are contract incentives? 什么是合同激励? What is a bidder's conference? 什么是投标人会议? What is part of the contract document? 合同文件由什么组成? What do you do if a seller does not perform according to the contract? 如果供应商未按合同规定执行,你将怎么办? 31
ESSENCE OF PMBOK & PMP EXAM
What are the major constraints on a project? 项目的主要约束是什么? When many changes are made to a project, what should a project manager do? 当项目发生很多变化时,项目经理应该怎样做? What is the purpose of a Project Plan? 项目计划的目标是什么? Refers to the Triple Constraints: Cost, Time, Quality, along with customer satisfaction and scope of work.一般指三重约束:成本、进度、质量及客户满意度和工作范围 Make change as needed, but maintain a schedule baseline (baseline is there to determine how the project is progressing)根据需求进行变更,但要保持进度基线(基线决定项目如何进行) 1. 2. 3. 4. 5. 6. You are a new project manager. It is best to rely on ?? to improve your chances of success?你是一个新项目管理者。依靠什么可以提高成功几率?
STRATEGY FOR VARIOUS TYPES OF QUESTIONS:
#1: “What has the project manager FORGOTTEN to do?”项目管理者忘记了做了什么?
a) b) c) d)
determine what process they are referring to确定他们提到的进程
determine if answer choices are/should be input/output/tools (activities)确定答案选项是否是/应该是输入/输出/工具(活动) determine which input/output/tool the question is looking for确定问题寻找的输入/输出/工具 select the one missing选择缺少的一个
Guide the project execution执导项目执行 Document project planning assumption项目计划假设文档化 Document project planning decisions regarding alternatives chosen选择项目计划编制方案的决策文档化 Facilitate communications among stakeholders便于干系人沟通 Define key management review 定义关键管理回顾 Provide a baseline for progress measurement and project control为进展衡量方法和项目控制提供一个基线 Historical information历史信息
#2: “What is the BEST thing to do?”什么是必须做的?
The correct answer should resolve the underlying problem.正确的答案应该能解决潜在的问题。
#3 “The project manager must be MOST careful to / Which is the MOST important?”什么是项目管理者必须特别注意的/什么是最重要的? The easiest way to deal with these questions is to look for the choice that will have the highest impact on the project.处理这类问题的最容易的方法是寻找对项目有最大影响的选择。
#4 Tip: However accurate answer choice are, pick the one that answer the question.无论正确答案是什么,选择一个回答问题。
#5 Tip: Know problem solving processes (e.g. for a change: (1) Evaluate impact of the change with the team, (2) determine option and (3) go to management or customer.)了解问题解决过程(例如:针对一个变更(1)和团队一起评估变更的影响(2)确定选项(3)去管理者或用户处)
32
正在阅读:
延边朝鲜族自治州城镇供热条例04-09
配套K12冀教版六年级综合实践让地球所有的生命都欢唱教案03-18
Win32API函数大全04-01
大肠癌治疗前的注意事项?05-11
实验诊断学考试重点 txt09-27
万仙山09-19
现代控制理论第3版课后答案完善版08-10
- 多层物业服务方案
- (审判实务)习惯法与少数民族地区民间纠纷解决问题(孙 潋)
- 人教版新课标六年级下册语文全册教案
- 词语打卡
- photoshop实习报告
- 钢结构设计原理综合测试2
- 2014年期末练习题
- 高中数学中的逆向思维解题方法探讨
- 名师原创 全国通用2014-2015学年高二寒假作业 政治(一)Word版
- 北航《建筑结构检测鉴定与加固》在线作业三
- XX县卫生监督所工程建设项目可行性研究报告
- 小学四年级观察作文经典评语
- 浅谈110KV变电站电气一次设计-程泉焱(1)
- 安全员考试题库
- 国家电网公司变电运维管理规定(试行)
- 义务教育课程标准稿征求意见提纲
- 教学秘书面试技巧
- 钢结构工程施工组织设计
- 水利工程概论论文
- 09届九年级数学第四次模拟试卷
- 精要
- 中英文
- 项目管理
- 对照
- 图文
- PMP
- 对创新带兵观念的几点思考
- 基于单片机的可调直流稳压电源设计(1) - 图文
- 彬县城关小学教师公开遴选公告
- 国外英文导游词
- 声乐学习理论与实践的结合
- 做实 做细 做优 做强 做活 持续提升经营管理水平
- 村级环境卫生管理制度
- 目录 - 2017-2022年中国便携式PH计行业市场深度分析与投资战略规
- PetroMod盆地模拟软件教程
- 区煤管局领导干部廉洁从政“早发现、早提醒、早纠正”预警机制实
- 工程地质课程设计
- 算法设计与分析课后习题解答
- 塑料空气滤心外套项目可行性研究报告(发改立项备案+2013年最新
- 高二通用技术上学期期中试题
- 新媒体时代加强高校班级建设机制的研究
- 2018燕山大学电气工程学院考研参考书目
- 三年级下册语文教案集 - 3
- 实验六:关系图、索引和视图的定义及维护
- 企业组织与经营环境
- 6082--信息管理概论复习题题库