L-Concretework%201-new1
更新时间:2023-04-18 15:23:01 阅读量: 实用文档 文档下载
- concrete推荐度:
- 相关推荐
SYABAS’ STANDARD SPECIFICATION FOR PIPE LAYING WOKS
First Edition : May 2007
L–C O N C R E T E W O R K
1.0 CONCRETE
1.1 Scope
This section covers the supply of materials for concrete, design of concrete mixes,
quality control of concrete, mixing, transporting, placing and curing of concrete,
and testing of concrete.
The standard of materials and workmanship shall not be inferior to the
recommendations of the current:
British Standard 8110 : Structural Use of Concrete
British Standard Code of Practice BS 8007 1987: Design of Concrete Structures for Retaining Aqueous liquids.
Appropriate Malaysian Standards approved by the S.O.
Unless otherwise specified, all reinforced concrete for retaining aqueous liquids
shall comply with BS 8007 and shall be of Grade C35A designed to resist Class 2
Sulphate Conditions as defined in BS 5238: Part 1 Table 7.
1.2 Concrete Production at the Site
At the commencement of the Contract the Contractor shall submit for the approval
of the S.O. a method statement detailing with regard to the requirements of this
Specification his proposal for the organization of concreting activities at the site.
The method statement shall include the following items :-
(a) Plant proposed;
(b) Laying of concrete production facility;
(c) Proposed method of organisation of the concrete production facility;
(d) Quality control procedures for concrete and concrete materials;
(e) Method of transport and placing of concrete;
(f) Striking times for formwork and procedure for temporary support of beams
and slabs.
Certificates
1.3 Test
Unless otherwise directed by the S.O., manufacturer's test sheets shall be supplied
with each consignment of cement and admixture certifying compliance with the
relevant standard.
D:\TECHNICAL DEPARTMENT\SPECIFICATION\SPEC FINAL PDF\PDF New Folder Final\L-Concretework 1-new1.doc L.1
SYABAS’ STANDARD SPECIFICATION FOR PIPE LAYING WOKS
First Edition : May 2007
The Contractor shall also submit to the S.O. certificates of calibration for the
weighing and dispensing equipment on the concrete batch mixing plant, certified
test results for all tests carried out on aggregate, water, fresh concrete and hardened
concrete, all as specified.
Samples
1.4 Aggregate
Prior to the commencement of the trial mixes of concrete the Contractor shall
submit for approval samples 50 kg in weight of each aggregate which he proposes
to use.
The source of each aggregate shall be clearly marked on the container of each
sample.
Certified test results demonstrating compliance with the relevant quality standard
shall be submitted at the same time. Samples approved by the S.O. shall remain
preserved at site for reference.
1.5 Records of Concreting
An accurate and up to date record showing dates, times, weather and temperature
conditions when various sections of the works are concreted shall be kept by the
Contractor and shall be available for inspection by the S.O. The Contractor shall
also record the results of all tests of concrete and shall identify these results with the
parts of the works of which the samples material is representative.
For each grade of concrete, the Contractor shall submit to the S.O., not later than
twenty-four hours after concreting, a daily return of the number of batches mixed,
the number of batches and total volume of concrete placed, the number of batches
wasted or rejected and the weight of cement used.
The return shall also include specific details of each location in the works where
concrete is placed, together with the grade of concrete, total volume of concrete
placed and the number of batches used for each location.
Mixes
1.6 Concrete
At the commencement of the works the Contractor shall design a mix for each grade
of concrete which will be required for use in the works and shall submit full details
of the mix designs to the S.O. for his approval. Each mix design shall be according
to the requirements of BS 5328.
1.7 Construction Joints and Lifts
The Contractor shall submit to the S.O. for his approval, as soon as is practicable
after the acceptance of his tender and not less than three weeks before the
commencement of concreting, drawings showing his proposals for placing concrete
on which the position of all construction joints and lifts shall be shown. No
concreting shall be started until the S.O. has approved the method of placing, the
positions and form of the construction joints and the lifts. The construction joints
shall be located so as to impair the strength of the structure.
D:\TECHNICAL DEPARTMENT\SPECIFICATION\SPEC FINAL PDF\PDF New Folder Final\L-Concretework 1-new1.doc L.2
SYABAS’ STANDARD SPECIFICATION FOR PIPE LAYING WOKS
First Edition : May 2007
Rebates, keys or notches shall be formed and waterstops inserted as the S.O. may
require. The position of construction joints and the size of formwork panels shall be
so coordinated that where possible the line of any construction joint coincides with
the line of a formwork joint and that in any case all construction joint lines and
formwork joint lines appear as a regular and uniform series.
For all exposed horizontal joints and purposely inclined joints, a uniform joint shall
be formed with a batten of approved dimensions to give a straight and neat joint
line.
1.8 Cement
The cement used for any particular mix shall comply with whichever of the
following standards is relevant :-
cement
12
BS
Ordinary
Portland
Sulphate-resisting Portland cement BS 4027
Portland Pulverised-Fuel Ash cement MS 1227
Portland Blastfurnace Cement MS 1389
For water retaining structures, the cement used shall be a blended cement
comprising ordinary portland cement from an approved source and conforming to
BS12 and containing 25%, by mass, of pulverised fly ash (PFA) to the requirement of
MS 1227, or containing 50%, by mass, of ground granulated blast furnaced slag
(GGBS) to the requirement of MS 1389. The cement used shall be an approved
brand of Malaysian manufacture unless otherwise approved.
In addition to the requirements for soundness of cement given in the relevant British
Standard for the type of cement being used, the cement shall also be tested for
soundness in accordance with ASTM C151-77 `Standard Test Method for Autoclave
Expansion of Portland Cement'. The expansion of the cement bar resulting from this
test shall not exceed 0.8 percent.
The Contractor shall provide from each consignment of cement delivered to the site
such samples as the S.O. may require for testing. Any cement which is, in the
opinion of the S.O., lumpy and partially set shall be rejected and the contractor
shall promptly remove such cement from the site. Cement which has been stored
on the site for more than forth days and cement which in the opinion of the S.O. is
of doubtful quality shall not be used in the works unless it is retested and the test
results show that it complies in all respects with the relevant standard.
1.9 Storage of Cement
Immediately upon arrival at the site, cement shall be stored in silos designed for the
purpose or in dry weather-tight and properly ventilated structures with floors raised
500 mm above ground level with adequate provision to prevent absorption of
moisture. All storage facilities shall be subject to approval by the S.O. and shall be
such as to permit each access for inspection and identification. Each consignment of D:\TECHNICAL DEPARTMENT\SPECIFICATION\SPEC FINAL PDF\PDF New Folder Final\L-Concretework 1-new1.doc L.3
SYABAS’ STANDARD SPECIFICATION FOR PIPE LAYING WOKS
First Edition : May 2007
cement shall be kept separately and the Contractor shall use the consignments in the
order in which they are received.
Cement of different types and from different sources shall be kept in clearly marked
separate storage facilities. Cement delivered to the site in drums or bags provided
by the supplier or manufacturer shall be stored in the unopened drums or bags until
used in the works.
Any cement in drums or bags which have been opened on the site shall be used
immediately or shall be disposed of.
1.10 Aggregates
Aggregates for concrete shall be obtained from an approved source and shall
conform with the requirements of BS 882.
Sampling and testing of aggregates shall be carried out as required by S.O in
accordance with the requirements of the appropriate clauses of BS 812. Water
absorption of aggregates when tested in accordance with the standard procedure
prescribed in Part 2 of BS 812, shall not exceed 3%.
The aggregates to be supplied shall not give rise to any alkali reaction with the
cement, whether silica or carbonate. Potential reactivity or otherwise of aggregates
shall be determined in accordance with ASTM C 289.
In addition, the soluble chlorides and sulphates content of the aggregates shall be
such that the concrete mix as a whole complies with the specified limits of salt
content.
Tests for chlorides and sulphates and for potential alkali reaction shall be carried out
when required by the S.O.
Notwithstanding any provisions contained herein, limestone aggregates shall not be
used in underground and water retaining structures.
1.11 Storage of Aggregates
The Contractor shall provide means of storing the aggregates at each point where
concrete is made such that :
(i) Each nominal size of coarse aggregate and fine aggregate shall be kept
separated at all times;
(ii) Contamination of the aggregates by the ground or other foreign matter shall be effectively prevented at all times;
(iii) Each heap of aggregate shall be capable of draining freely.
D:\TECHNICAL DEPARTMENT\SPECIFICATION\SPEC FINAL PDF\PDF New Folder Final\L-Concretework 1-new1.doc L.4
SYABAS’ STANDARD SPECIFICATION FOR PIPE LAYING WOKS
First Edition : May 2007
The Contractor shall ensure that graded coarse aggregates are tipped, stored and
removed from store in a manner that does not cause segregation.
Wet fine aggregate shall not be used until, in the opinion of the S.O., it has drained
to a constant and uniform moisture content of the fine aggregate continuously and
adjusts the amounts of fine aggregate and added water in each batch of concrete
mixed to allow for the water contained in the fine aggregate. If necessary to meet
the requirements of this clause, the Contractor shall protect the heaps of fine
aggregate against inclement weather.
1.12 Water
Water for washing aggregates and for mixing concrete and curing shall be clean and
free from harmful matter and shall satisfy the recommendations in the Appendix to
BS 3148. When required by the S.O. the Contractor shall take samples of the water
being used for which it is proposed to use for mixing concrete and test them for
quality, including determining the concentration of sulphates and chlorides, which
shall be such that the concrete mix as a whole complies with the specified limit for
salt content.
1.13 Admixtures
Admixtures shall mean material added to the concrete materials during mixing for
the purpose of altering the properties of the concrete mix.
Admixture containing calcium chloride shall not be used.
Admixtures shall not be used unless the S.O. has given his prior approval in writing
for each instance. Both the amount added and the method of use shall be to the
approval of the S.O. who shall also be provided with the following information :-
(i) The typical amount added and the detrimental effects if any, due to an
increase or decrease in this amount;
(ii) The chemical name(s) of the main active ingredient(s) in the admixture;
(iii) Whether or not the admixture leads to the entrainment of air when used at the amount the manufacturer recommends.
Any approved admixture shall conform to whichever of the following standards is
appropriate :-
- Air entraining admixtures BS 5075 Part 2
- Water reducing admixtures BS 5075 Part 1
- Retarding admixtures BS 5075 Part 1
- Fly ash and raw or calcined natural
pozzolans for use as a mineral admixture ASTM C 618
D:\TECHNICAL DEPARTMENT\SPECIFICATION\SPEC FINAL PDF\PDF New Folder Final\L-Concretework 1-new1.doc L.5
SYABAS’ STANDARD SPECIFICATION FOR PIPE LAYING WOKS
First Edition : May 2007
1.14 Test
Equipment
The contractor shall furnish all equipment and materials necessary for collecting
samples and carrying out field laboratory tests on materials for concrete and on fresh
and hardened concrete. Laboratory equipment shall be housed in a suitable
laboratory building on the site, which shall also incorporate space for storage of
field test equipment, and for curing of concrete test cubes in an orderly manner so
that they are readily accessible for testing on the due date. The contractor shall also
furnish all weights, containers and other equipment necessary for testing the weight-
batching equipment for concrete materials and the dispensers for admixtures.
1.15 Grades of Concrete
Grades of concrete for use in the work shall be as shown in the table below:-
Concrete grade Maximum
aggregate
size (mm)
Characteristic
strength at 28 days
(N/sq.mm)
Minimum
cement
content (kg/cu.m)
Maximum
Cement
content
(kg/cu.m)
Maximum
free
water/cement
ratio
C40 C35A** C35A** C30 C25 C20 C15 20
20
40
20
20
20
20
40
35
35
30
25
20
15
325
325
300
275
250
225
205
550
400*
550
550
550
550
550
0.55
0.55**
0.60
0.65
0.70
-
-
* Maximum cement content 400 kg/m3 where OPC or cement containing GGBS is used. Maximum cement content 450 kg/m3 where cement
containing PFA is used.
** Maximum free water cement ratio is 0.55 where OPC or cement containing GGBS is used. Maximum free water cement ratio is 0.50 where cement
containing PFA is used.
*** Blended cement comprising Portland cement and PFA or PFA as specified
Concrete grade is that number which represents its 28 day characteristic strength
expressed in N/sq.mm.
Characteristic strength is that value of cube crushing strength below which none of
all test results fail. This condition shall be deemed to be satisfied when test results
comply with the specified test requirements.
D:\TECHNICAL DEPARTMENT\SPECIFICATION\SPEC FINAL PDF\PDF New Folder Final\L-Concretework 1-new1.doc L.6
SYABAS’ STANDARD SPECIFICATION FOR PIPE LAYING WOKS
First Edition : May 2007
Maximum free water/cement ratios shall be based on aggregates being in a surface-
dry condition.
1.16 Free Water/Cement Ratio
In designing and establishing approved mixes of concrete for any part of the works
the contractor shall keep strictly within the limitations on free water/cement ratios
which may be shown on the drawings or expressly stated elsewhere as applying to
concrete for particular parts of the works.
1.17 Limits of Salt Content
No concrete shall contain more than the following total quantities of substances
expressed as percentages by weight of cement :-
(a) For mixes containing ordinary Portland cement to BS 12 :
Total water soluble chlorides 0.4% (as chloride ions)
b) For mixes containing cements complying with BS 4027 :
Total chlorides 0.2% (as chloride ions)
c) For mixes used for pre-stressed concrete (all cement types) :
Total chlorides 0.1% (as chloride ions)
d) For all mixes :
Total acid soluble sulphates 4.0% (as SO3 ions)
Tests shall be carried out in accordance with the following standards :-
Chlorides in aggregates ASTM D 1411
Sulphates in aggregates BS 1377 Test 9
Chloride ion in mixing water ASTM D 512
Sulphates in mixing water ASTM D 516
Workability
1.18
The workability of each grade of concrete shall be such that satisfactory compaction
can be obtained when the concrete is placed and vibrated and that there is no
tendency to segregate when it is handled, transported and compacted by the
methods which the contractor proposes to use in the works.
For reinforced concrete, the compacting factor, determined by the method
described in BS 1881, shall not be less than 0.85 nor greater than 0.92. For
unreinforced concrete the compacting factor shall be not greater than 0.85. Where D:\TECHNICAL DEPARTMENT\SPECIFICATION\SPEC FINAL PDF\PDF New Folder Final\L-Concretework 1-new1.doc L.7
SYABAS’ STANDARD SPECIFICATION FOR PIPE LAYING WOKS
First Edition : May 2007
pumping of concrete is permitted, the compacting factor may be increased to 0.95,
provided that the conditions are not varied. In any case no pumped concrete shall
be used for all water retaining structures.
1.19 Design of Concrete Mixes
Each mix design shall be such that :
(i) The aggregate shall comprise both fine aggregate and coarse aggregate. The
maximum size of coarse aggregate shall be 20 mm or 40 mm as approved by
the S.O.
(ii) The cement content shall not be below the minimum specified for the grade of concrete.
(iii) The maximum free water/cement ratio shall be the maximum water/cement ratio when the aggregate is saturated but surface dry.
(iv) The mixes shall be designed to produce a targeted mean concrete cube strength at 28 days after manufacture and shall be greater than the
characteristic strength at 28 days by a margin of at least 10 N/sq.mm for Grade
15 and 15 N/sq.mm for Grade 20, 25, 30, 35A and 40.
(v) Where sufficient data can be produced by the contractor to show that the standard of acceptance for characteristic strength can be maintained using a
lower margin, the mix may be redesigned to have such reduced margin.
Sufficient data shall consist of cube test results from at least 40 separate
batches of concrete produced over a same plant under similar supervision.
The reduced margin shall be 1.64 times the standard deviation of the test
results considered, but not less than 5 N/sq.mm for Grade 15 and 7.5
M/sq.mm for Grades 20, 25, 30, 35A and 40.
For any concrete containing admixtures, the strengths shall not be less than those
specified but the mixes for the grade of concrete shall be separately designed to take
account of the effects of the admixtures, and shall have separate trial mixes made
and tested.
Mixes
1.20 Trial
As soon as the S.O. has approved each of the concrete mix designs, two batches
from a trial mix for each grade shall be produced in laboratory using cement and
surface dry aggregates known to be typical of the proposed source of supply. The
proposed mix proportions of each grade shall be approved only if both batches have
the correct cement content and free water cement ratio at or below the maximum
value for the proposed degree of workability.
When mix proportions have been approved by the S.O., three further batches of
concrete for each grade shall be made at site under full scale production conditions
using the same mixing time and handles by means of the same plant which the
Contractor proposes to use in the works.
D:\TECHNICAL DEPARTMENT\SPECIFICATION\SPEC FINAL PDF\PDF New Folder Final\L-Concretework 1-new1.doc L.8
SYABAS’ STANDARD SPECIFICATION FOR PIPE LAYING WOKS
First Edition : May 2007
The proportions of cement, aggregates and water, shall be carefully determined by
weight in accordance with the contractor's approved mix design, and sieve analyses
shall be made, by the method described in BS 812, of fine aggregate and each
nominal size of coarse aggregate used.
The compacting factor of each batch of each trial mix shall be determined
immediately after mixing by the method described in BS 1881 and shall not be
outside the limits specified in clause 2.3.18.
Three 150 mm compression test cubes from each of the three batches shall be made
by the Contractor in the presence of the S.O. from each trial mix. The cubes shall be
made, cured, stored and tested at 28 days after manufacture in accordance with the
method described in BS 1881. If the average value of the compressive strength of
the nine cubes taken from any trial mix is less than the target mean strength used in
the mix design or if any inpidual cube test result falls below 85% of the target
mean strength, the Contractor shall redesign that mix and make a further trial mix
and set of test cubes.
A full scale test of the workability of each trial mix of each grade of concrete shall
be made by the contractor in the presence of the S.O. The trial mix of each grade of
concrete shall be batched, mixed and then transported a representative distance in
the manner that the contractor proposes to batch, mix and transport the concrete to
be placed in the works. After discarding the first batch so made, the concrete from
later batches shall be placed and compacted in trial moulds both for reinforced and
mass concrete with dimensions typical of the works in accordance with the
procedures described in later clauses, the sided of the moulds being capable of
being stripped without undue disturbance of the concrete placed therein. The sides
of the moulds shall be stripped after the concrete has set and the workability judged
by the surface appearance and compaction obtained. If the workability test shows
that the workability required is not attained for any trial mix for any grade of
concrete, the trial mix shall be re-designed by the Contractor and a further full scale
workability test undertaken for that trial mix.
The re-design of the concrete mixes and the making and testing of trial mixes of
concrete shall be repeated for each grade of concrete until trial mixes of concrete
have been established which meet the specified requirements and have the required
workability as demonstrated in the full scale workability test described above.
If at any time during the construction of the works the S.O. approves a change in the
source of cement or aggregate or if the grading of the aggregate alters to such an
extent that the fraction of aggregate retained on any sieve cannot be maintained
within two percent of the total quantity of fine and coarse aggregate when adjusted
as specified for sampling and testing of aggregates, then further trial mixes of
concrete shall be made, tested and approved for use.
Batching
1.21 Material
All cement used in the manufacture of concrete shall be measured by weight either
with an approved weighing machine or by making the size of each batch of
concrete such as to require an integral number of complete bags or drums of
cement.
D:\TECHNICAL DEPARTMENT\SPECIFICATION\SPEC FINAL PDF\PDF New Folder Final\L-Concretework 1-new1.doc L.9
SYABAS’ STANDARD SPECIFICATION FOR PIPE LAYING WOKS
First Edition : May 2007
For concrete of Grades 20, 25, 30, 35A and 40, the fine aggregate and the several
nominal sizes of coarse aggregates shall be measured singly or cumulatively by
weight using weight-batching machines.
For concrete of Grade 15, the fine and coarse aggregate shall be measured
separately either by weight using weight-batching machines or by volume in gauge
boxes.
Weight-batching machines shall provide facilities for the accurate control and
measurement of the aggregates either singly or cumulatively and shall be capable of
immediate adjustment by semi-skilled operators in order to permit variations to be
made to the mix. All weigh dials shall be easily visible from the place at which
filling and emptying of the hoppers is controlled.
Every concrete mixing machine shall be fitted with a device to measure added water
by weight and shall be so constructed that the water inlet and outlet valves are
interlocked so that either one of them cannot be opened unless the other is fully
closed. The weighing device shall be provided with an overflow with a cross-
sectional area at least four times that of the inlet pipe and with its discharge point
clear of the mixing plant. The entire water system shall be maintained free of leaks
at all times and the measuring device shall be fitted with a drain pipe which allows
the full quantity of water being measured to be drained off for checking the
measurement. The outlet arrangement of the measuring device shall be such that
between five and ten percent of the water enters the mixer before the other
materials and further five to ten percent of the water enters the mixer after the other
materials. The remainder of the water shall be added at a uniform rate with the
other materials. The water measuring device shall be readily adjustable so that the
quantity of water added to the mixer can, if necessary, be varied for each batch.
Where volume batching is permitted by the Specification, gauge boxes shall be
soundly constructed of timber or steel to contain exactly the volume of the various
aggregates required for one batch of each mix. They shall have closed bottoms and
shall be clearly marked with the mix and aggregate for which they are intended.
When calculating the size of the gauge box for fine aggregate, an allowance shall be
made for the bulking of the fine aggregate due to the average amount of moisture
contained in the stockpiles on the site. Before the contractor puts any gauge box
into use on the site he shall obtain the approval of the S.O. of the size and
construction of such gauge box.
Any admixtures which may be used shall be measured separately in calibrated
dispensers.
All mixing and batching plants shall be maintained free of set concrete or cement
and shall be clean before commencing mixing. The accuracy of calibration of any
weighing plant, water measuring plant and admixture dispenser, shall be checked
before carrying out trial mixes, before mixing concrete for inclusion in the work,
after each service or adjustment to the mixing plant, and in any case at least once
per month.
D:\TECHNICAL DEPARTMENT\SPECIFICATION\SPEC FINAL PDF\PDF New Folder Final\L-Concretework 1-new1.doc L.10
SYABAS’ STANDARD SPECIFICATION FOR PIPE LAYING WOKS
First Edition : May 2007
Concrete
1.22 Mixing
Concrete shall be mixed in batches in plant capable of combining the aggregates,
cement and water (including admixtures, if any) into a mixture uniform in colour
and consistency, and of discharging the mixture without segregation.
On commencing work with a clean mixer, the first batch shall contain only half the
normal quantity of coarse aggregate to compensate for the adhesion of the other
materials to the drum.
The moisture contents of the aggregates shall be determined before the
commencement of each day's concreting and at such intervals during each day as
may be necessary. The Contractor shall make due allowance for the water
contained in the aggregates when determining the quantity of water to be added to
each mix, and shall adjust the amount of water added to each mix to maintain
constant the approved free water/cement ratio of the mixed concrete.
Concrete
1.23 Ready-Mixed
Ready-mixed concrete shall not be used in any part of the works without the S.O.'s
written approval, which may be withdrawn at any time.
The Contractor shall satisfy the S.O. that ready-mixed concrete complies with the
Specification in all respects, add that the manufacturing and delivery resources of
the proposed supplier are adequate to ensure proper and timely completion of each
concreting operation.
The specified requirements as to the sampling, trial-mixing, testing and quality of
concrete of various grades shall apply equally to ready-mixed concrete which shall
furthermore be made and delivered in accordance with BS 5328 : 1981.
Any additional facility, which the S.O. may require for the supervision and
inspection of the batching, mixing and transporting of ready-mixed concrete shall be
allowed to be used after 45 minutes of initial mixing.
1.24 High Alumina Cement
The composition of high alumina cement shall comply with B.S. 915 Part Two. It
shall consist of a minimum of 32% of alumina and the minimum compressive
strengths of mortar cubes at one and three days shall be 42 N/sq.mm and 48
N/sq.mm respectively.
High alumina cement shall be refrained from being used in structural concrete
including foundations as a substantial reductions in strengths is observed under the
vulnerable tropical conditions.
D:\TECHNICAL DEPARTMENT\SPECIFICATION\SPEC FINAL PDF\PDF New Folder Final\L-Concretework 1-new1.doc L.11
SYABAS’ STANDARD SPECIFICATION FOR PIPE LAYING WOKS
First Edition : May 2007
1.25 Preparing for Concreting
Before placing concrete the contractor shall remove from the surface of the
foundations or previously placed concrete, all oil, loose fragments of rock, earth,
mud, timber and other debris, and standing water, to the satisfaction of the S.O.
Where specified and elsewhere as ordered by the S.O., the excavated surfaces shall
be prepared as specified under concrete protection.
Concrete
1.26 Transporting
Concrete shall be conveyed from the mixer to its place in the works as rapidly as
possible by methods which will prevent segregation or drying out and ensure that
the concrete is of the required workability at the time of placing. If segregation has
nevertheless occurred in any instance, the materials shall be remixed or rejected.
Concrete
1.27 Placing
Concrete shall be placed and compacted before the initial set has occurred and, in
any event, not later than 45 minutes from the time of mixing.
When pneumatic placers are used, if the end of the placer pipe is not equipped with
an energy absorbing device, it shall be kept as close to the work as practicable.
Mortar or water used at the beginning or end of a run shall be discharged outside
the formwork..
When pumps are used, the end of the supply pipe shall be kept immersed in the
concrete during placing to assist compaction. Mortar and water used at the
beginning or end or a run shall be discharged outside the formwork.
1.28 Concreting in Hot Weather
In hot weather, the contractor shall take steps to ensure that the temperature of the
concrete as placed shall not exceed 32 deg. C and that the maximum internal
temperature attained during setting does not exceed 70 deg. C.
To achieve this, the contractor shall provide sun shades over stockpiles of aggregate,
cement silos, mixing water tanks and pipelines and in addition shall carry out the
first and as necessary other of the following procedures which shall be submitted to
the S.O. for approval :
(i) Cool the mixing water and replace part of the water by chipped ice. The ice
shall be completely melted by the time mixing is completed.
(ii) Spray clean cool water over the aggregate stockpiles. The Contractor shall carry out regular tests on the aggregates to ensure that concentrations of
sulphates or chlorides do not rise to unacceptable levels, and to ensure that
moisture content determinations allow for such spraying.
(iii) Shade or wet outside of the formwork.
D:\TECHNICAL DEPARTMENT\SPECIFICATION\SPEC FINAL PDF\PDF New Folder Final\L-Concretework 1-new1.doc L.12
SYABAS’ STANDARD SPECIFICATION FOR PIPE LAYING WOKS
First Edition : May 2007
(iv) Apply a fine moisture (fog) spray of clean cool water to shaded areas immediately prior to placing concrete.
(v) Pour concrete at night.
1.29 Compaction
All concrete placed in-situ shall be compacted with power driven internal type
vibrators supplemented by hand spading and tamping except as otherwise approved
by the S.O. The vibrators shall at all times be adequate in number, amplitude and
power to compact the concrete properly and quickly throughout the whole of the
volume being compacted. Spare vibrators shall be readily on hand in case of
breakdown.
Vibrators shall be inserted into the uncompacted concrete vertically and at regular
intervals. Where the uncompacted concrete is in a layer above freshly compacted
concrete the vibrator shall be allowed to penetrate vertically for about 100 mm into
the previous layer. In no circumstances shall vibrators be allowed to come into
contact with the reinforcement or formwork nor shall they be withdrawn quickly
from the mass of concrete but shall be drawn back slowly so as not to leave voids.
Internal type vibrators shall not be placed in the concrete in a random or haphazard
manner nor shall concrete be moved from part of the work to another by means of
the vibrators.
The duration of vibration shall be limited to that required to produce satisfactory
compaction without causing segregation. Vibration shall on no account be
continued after water or excess grout has appeared on the surface.
1.30 Attendance of Steel Fixer and Carpenter
During the concreting of all reinforced concrete, including prestressed concrete, a
competent steel fixer and carpenter shall be in attendance on each concreting gang,
to ensure that the reinforcement, formwork and embedded fittings are kept in
position as work proceeds.
1.31 Curing of Concrete
Concrete shall be cured by protecting the surface from the effects of sunshine,
drying winds, frost, rain, running water or mechanical damage for a continuous
period of four days when the cement used in the concrete is sulphate-resisting
Portland cement, Portland Pulverised-Fuel Ash cement or Portland Blastfurnace
Cement. The protection shall be applied as soon as practicable after completion of
placing by one or more of the following methods as approved by the S.O.:
(a) By water sprays in continuous operation;
(b) By covering with hessian or similar absorbent material, or sand, kept
constantly wet;
(c) After thorough wetting, by covering with a layer of waterproof fabric kept in
contact with the concrete surface.
D:\TECHNICAL DEPARTMENT\SPECIFICATION\SPEC FINAL PDF\PDF New Folder Final\L-Concretework 1-new1.doc L.13
SYABAS’ STANDARD SPECIFICATION FOR PIPE LAYING WOKS
First Edition : May 2007
(d) By the application of an approved non-staining liquid curing membrane which
is either self-removing or easily removed following curing period and which
has a 75% moisture retention standard. The liquid shall be applied to formed
surfaces immediately after stripping the formwork.
Liquid curing membrane (d) shall not be used on Class U1 surfaces where laitance is
to be removed and aggregate exposed to provide a satisfactory bond for placing
further concrete or mortar screeds or on surfaces where the S.O. is of the opinion
that the appearance of the concrete surface will be affected.
Joints
1.32 Construction
A construction joint is defined as a joint in the concrete introduced for convenience
in construction at which special measures are taken to achieve subsequent
continuity without provision for further relative movement.
Concrete placed to form the face of a construction joint shall have all laitance
removed and the large aggregate exposed prior to the placing of fresh concrete.
The laitance shall wherever practicable be removed when the concrete has set but
not hardened by spraying the concrete surface with water under pressure or
brushing with a wire brush sufficient to remove the outer mortar skin and expose
the large aggregate without being disturbed. Where the laitance cannot be removed
due to hardening of the concrete, the whole of the concrete surface forming the
joint shall be treated by high pressure water jet, sand blasting, use of a needle gun
or a scaling hammer to remove the surface laitance.
Before concreting is resumed, all loose matter on the existing concrete surface shall
be removed and the surface slightly wetted.
1.33 Dimensions and Surfaces of Finished Concrete
Workmanship in formwork and concreting shall be such that concrete shall require
no making good, surfaces being perfectly compacted, smooth and with no
irregularities. Concrete surfaces for the various classes of unformed and formed
finishes shall in any event not exceed the maximum permitted tolerance which shall
be as shown in the table below except where expressly stated otherwise in the
Specification or Drawings.
In the table "line and level" and "dimension" shall mean the lines, levels and cross-
sectional dimensions shown on the Drawings.
Surface irregularities shall be classified as "abrupt" or "gradual". Abrupt
irregularities include, but shall not be limited to offsets and fins caused by displaced
or misplaced formwork, loose knots and other defects in formwork materials, and
shall be tested by direct measurement. Gradual irregularities shall be tested by
means of a straight, template for plane surfaces or its suitable equivalent for curved
surfaces, the template being 3.0 m long for unformed surfaces and 1.5 m long for
formed surfaces.
D:\TECHNICAL DEPARTMENT\SPECIFICATION\SPEC FINAL PDF\PDF New Folder Final\L-Concretework 1-new1.doc L.14
SYABAS’ STANDARD SPECIFICATION FOR PIPE LAYING WOKS First Edition : May 2007
Maximum tolerance (mm) in :
Class of finish Line and
level
Abrupt
irregularity
Gradual
irregularity
Dimension
U1 U2 U3 F1 F2 F3 +/-12
+/ -6
+/ -6
+/-12
+/ -6
+/ -3
6
3
3
6
6
3
+/ -6
+/ -3
+/ -3
+/ -6
+/ -6
+/ -3
-
-
-
+12, -6
+12, -6
+6/ -6
1.34 Unformed
Surfaces
Finishes to unformed surfaces of concrete shall be classified as U1, U2, U3, spaded'
or `bonded concrete' or such other special finish as may be particularly specified.
Where the class of finish is not specified, the concrete shall be finished to Class U1.
Class U1 finish is the first stage for Class U2 and U3 finishes and for a bonded
concrete surface. Class U2 finish shall be a leveled and screeded, uniform plain or
ridged finish, which (unless it is being converted to Class U2, U3 or bonded
concrete) shall not be disturbed in any way after the initial set and during the period
of curing, surplus concrete being struck off immediately after compaction.
Where a bonded concrete surface is specified, the laitance shall be removed from
the Class U1 finish surface and the aggregate exposed while the concrete is still
green.
A spaded finish shall be a surface free from voids and brought to a reasonably
uniform appearance by the use of shovels as it is placed in the works.
Class U2 finish shall be produced by manual or mechanical floating of the concrete
surface after the initial set has taken place and the surface has hardened sufficiently.
The concrete shall be worked no more than is necessary to produce a uniform
`sandpaper' finish free from screedmarks.
Class U3 finish shall be a hard smooth steel-trowelled finish. Trowelling shall not
commence until the moisture film has disappeared and the concrete has hardened
sufficiently to prevent excess laitance from being worked into the surface. The
surface shall be trowelled under firm pressure and left free from trowel marks.
The addition of dry cement, mortar or water will not be permitted during any of the
above operations.
D:\TECHNICAL DEPARTMENT\SPECIFICATION\SPEC FINAL PDF\PDF New Folder Final\L-Concretework 1-new1.doc L.15
SYABAS’ STANDARD SPECIFICATION FOR PIPE LAYING WOKS
First Edition : May 2007
Exposed aggregate finish shall be achieved by exposure of the coarse aggregate
using a method approved by S.O. The average depth of exposure shall be 6 mm for
concrete with a maximum aggregate size of 20 mm and between 6 mm and 12 mm
for concrete with a maximum aggregate size of 40 mm.
The Contractor shall prepare sample panels 1000 mm x 500 mm of concrete with
an exposed aggregate finish for inspection and approval by the S.O. at the site.
1.35 Building in Plant and Grouting- in
Wherever possible, pipes and other items of plant passing through concrete
structures shall be installed and connected to the remainder of the pipework system
to ensure proper fit, and shall be built into the structure as work proceeds.
Where this procedure is impracticable due to programme or other requirements,
holes shall be formed for the items of plant to allow them to be built in later after
complete installation of the plant.
In no case shall inpidual pipes of a complicated pipework system including
flanged joints be built into concrete structures before accurate fit of the whole
system can be checked after the complete installation.
Where holes are formed these shall be of size and shape sufficient to permit proper
placing and compaction of concrete or grout. The surfaces of the holes shall be
treated to produce a `bonded' surface before installation of plant.
Before grouting-in commences the plant shall be adequately supported in position
to prevent movement or damage during grouting-in.
Concrete used for building-in shall be of the same grade as concrete of the member
into which the plant is being built, except that the mix shall also incorporate an
approved expanding additive used in accordance with the manufacturer's
instructions. Concrete used for water retaining structures shall be non shrink in
nature to ensure water tightness. Concrete, mortar and grout shall be carefully
placed and compacted around the plant to avoid damaging or moving the plant.
1.36 Structural Pre-Cast Concrete
Structural units of pre-cast concrete shall be manufactured in the grade of concrete
and to the sizes and details shown on the Drawings. The concrete shall comply in
every aspect with the provisions of the Contract whether such units are
manufactured on the site or obtained from other manufacturers.
All cement, aggregate and other materials for pre-cast concrete units with faces
which are exposed either internally or externally shall be from the same sources
throughout. Exposed surfaces of the units shall be uniform in colour and in texture.
Formwork and unformed surfaces for pre-cast concrete units shall comply with the
requirements for F3 formed surfaces and U3 unformed surfaces except that the
dimensional variations shall not exceed the values listed below, unless otherwise
detailed on the Drawings.
D:\TECHNICAL DEPARTMENT\SPECIFICATION\SPEC FINAL PDF\PDF New Folder Final\L-Concretework 1-new1.doc L.16
SYABAS’ STANDARD SPECIFICATION FOR PIPE LAYING WOKS
First Edition : May 2007
+/-6
mm
Length
Cross-section +/6 mm each direction
Straightness 6 mm (deviation from intended line)
Flatness 3 mm (deviation from a 1.5 m straight edge placed in any position on a
nominally plane surface)
Squareness when considering the squareness of a corner, the longer of the two
adjacent sides being checked shall be taken as the baseline, and the shorter side
shall not vary in its distance from the normal so that the differences between the
greatest and the shortest dimension exceeds 6 mm. When the nominal angle is
other than 90 degrees, the included angle between the check line shall be varied
accordingly.
Twist any corner on any nominally plane surface shall not be more than 6 mm from
the plane containing the other three corners.
The positions of inpidual connecting bolts, bolt holes, projecting steel and other
devices in any associated group (eg. the joint of two pre-cast units) shall be within 3
mm of their true position in the group in which they are cast. The location of any
such group shall be within 6 mm of its true position in the unit in which it is cast,
provided that such deviation does not adversely affect the proper assembly of the
whole structure.
The Contractor shall submit to the S.O. for approval, full details of his proposed
method of carrying out all operations connected with the manufacture and assembly
of precast concrete structural members, including :
A description of the types of casting bed, mould and formwork for the various
types of members;
The procedure for concrete casting and the method of curing the concrete;
The procedure for transporting, handling, hoisting and placing of each type of pre-cast structural member;
Full details of temporary supports necessary to ensure adequate stability during erection, due account be taken of construction loads, including wind.
1.37 Installation of Pre-Cast Concrete Units
At all stages and until completion of the work, pre-cast members shall be adequately
protected to preserve all permanently exposed surfaces, arises and architectural
features. The protection shall not mark or otherwise disfigure the concrete.
All units shall be laid, bedded, jointed and fixed in accordance with the lines, levels
and other details shown on the Drawings.
D:\TECHNICAL DEPARTMENT\SPECIFICATION\SPEC FINAL PDF\PDF New Folder Final\L-Concretework 1-new1.doc L.17
SYABAS’ STANDARD SPECIFICATION FOR PIPE LAYING WOKS
First Edition : May 2007
Dry-pack mortar jointing for packing shall consist of one part of volume ordinary
Portland cement and two and half parts by volume of fine aggregate passing a 1 mm
sieve. The mortar shall be mixed with only sufficient water to make the materials
stick together when being moulded in the hands. The mortar is thoroughly
compacted.
Any pre-cast concrete structural member which is found to be cracked, damaged or
otherwise inferior in quality either before or after erection shall be rejected and
replaced by the Contractor.
1.38 Pr-Sstressed
Concrete
The Contractor shall submit to the S.O. for approval his proposed method of carrying
out all operations connected with pre-stressed concrete work and his proposals for
handling, hoisting and placing a position any pre-cast pre-stressed concrete units.
Pre-stressed concrete work whether pre-cast or cast in-situ shall be as detailed on the
Drawings and the Contractor shall provide full details of his proposed method of
carrying out all operations connected with pre-stressing including :-
(a) Design of concrete mix
(b) Description of concrete casting and curing operations
(c) Procedure for pre-stressing and method of checking and recording the pre-
stress, wire extension and anchorage slip.
(d) Procedure for handling, hoisting and placing of any pre-cast units.
(e) Grouting of ducts
All tendons, duct forming devices, anchorages and other components shall be kept
free of mud, oil (except water soluble oil applied for protection), paint, retarders,
loose rust, or other foreign matter. They shall be placed with a tolerance of +/-3
mm in concrete dimensions of 300 mm of less or ± 6 mm in concrete dimensions
over 300 mm.
Concrete
1.39 No-Fines
No-fines concrete shall be made using a coarse natural aggregate conforming with
BS 882 and cement to BS 4027. No fine aggregate shall be used. The grading of
the coarse aggregate shall be;
Not less than 95% by weight passing a 19 mm BS sieve;
Not more than 5% by weight passing a 10 mm BS sieve.
The proportion of aggregate, cement and water shall be determined by trial mixes
by the Contractor starting with a cement : aggregate particles ratio of one to eight by
volume.
D:\TECHNICAL DEPARTMENT\SPECIFICATION\SPEC FINAL PDF\PDF New Folder Final\L-Concretework 1-new1.doc L.18
SYABAS’ STANDARD SPECIFICATION FOR PIPE LAYING WOKS
First Edition : May 2007
The trial mix shall be considered suitable when all the aggregate particles are coated
with a film of cement grout. The water content shall be just adequate. The concrete
when placed shall contain no layers of laitance.
No-fines concrete shall not be mixed by hand.
Vibration shall not be used to compact the concrete. Three test cubes of no-fines
concrete shall be made of each trial mix. The minimum crushing strength of the
chosen mix shall be 3 N/sq,mm at 28 days.
1.40 Pre-Cast Concrete Products
(a) Pre-cast concrete products shall where appropriate be constructed in
accordance with British Standards as follows, being hydraulically pressed
where possible :
Type of Unit Standard
Concrete blocks BS 6073 : Pt 1 : 1981
Concrete kerbs, etc. BS 7261 : Part 1 : 1990
Concrete flags BS 7263 : Pt 1 : 1990
Concrete
5642
sills BS
BS
5977
lintels
Concrete
The concrete shall comply in every aspect with the provisions of the
Specification whether such products are manufactured on the site or
obtained from other manufacturers.
(b) Interlocking concrete paving shall include supply and laying of pavers,
preparation of surface, supply of sand and casting of edge restraint beams.
The pavers shall comply with the requirement of MA 20, Specification for
concrete segmental Paving Units, published by the Concrete Masonry
Association of Australia.
1.41 Sampling and Testing of Aggregate
The Contractor shall sample and carry out a mechanical analysis of the fine
aggregate and each nominal size of coarse aggregate in use employing the methods
described in BS 1881 at least once in each week when concreting is in progress and
at such more frequent intervals as the S.O. may require.
The grading of all aggregates shall be within specified limits and should the fraction
of aggregate retained on any sieve differ from the corresponding fraction of
aggregate in the approved mix by more than 2% of the total quantity of fine and
coarse aggregate, S.O may instruct the contractor to alter the relative proportions of
the aggregates in the mix to allow for such difference.
D:\TECHNICAL DEPARTMENT\SPECIFICATION\SPEC FINAL PDF\PDF New Folder Final\L-Concretework 1-new1.doc L.19
SYABAS’ STANDARD SPECIFICATION FOR PIPE LAYING WOKS
First Edition : May 2007
1.42 Sampling and Testing of Concrete
The Contractor shall provide the equipment necessary to determine the compacting
factor of freshly mixed concrete at each place where concrete is being made and
shall determine the compacting factor of the freshly mixed concrete by the method
described in BS 1881 on each day or as the S.O. may direct.
For each grade concrete, works test cubes shall be made whenever required by the
S.O. but not less frequently than as follows unless otherwise particularly specified :-
for concrete of one set of cubes per 25 cu.m
Grades 25, 30, 35A, 40 or part thereof concreted per day;
for concrete of one set of cubes per 50 cu.m
Grades 15 or 20 or part thereof concreted per day
Each set of cubes (six cubes per set) shall be made from a single sample taken from
a randomly selected batch of concrete. Three cubes shall be tested 7 days after
manufacture and three cubes 28 days after manufacture.
1.43 Compliance with Specified Requirements
The concrete shall be deemed satisfactory provided that :
(i) The average 28 days strength determined from any group of four consecutive
sets of three test cubes exceeds the specified characteristic strength by not less
than 7.5 N/sq.mm for Grade 15 concrete and 10 N/sq.mm for Grades 20, 25,
30, 35A and 40.
(ii) The average of each set of three test cube results is greater than 100% of the specified characteristic strength.
If only one set of three cube results fails to meet the second requirement, those
results may be considered to represent only the particular batch of concrete from
which the cubes were taken, provided that the average strength of the group satisfies
the first requirement.
If more than one set of three cube results in a group fails to meet the second
requirement or if the average strength of any group of four consecutive sets of three
test cubes fails to meet the first requirement then all the concrete in all the batches
represented by all such cubes shall be deemed not to comply with the strength
requirements.
1.44 Non-Compliance
When the average strength of four sets of three consecutive test cubes fails to meet
the first requirement, no further concrete from that mix shall be placed in the work
and the contractor shall establish the cause of the failure and apply such remedies as
are necessary. The Contractor shall demonstrate by trial mixes and test cube results
that the revised mix is in accordance with the specified requirements.
D:\TECHNICAL DEPARTMENT\SPECIFICATION\SPEC FINAL PDF\PDF New Folder Final\L-Concretework 1-new1.doc L.20
SYABAS’ STANDARD SPECIFICATION FOR PIPE LAYING WOKS
First Edition : May 2007
The Contractor shall within 24 hours of the date of test make proposals for
agreement with the S.O. about action to be taken in respect of any concrete
represented by test cubes which fail to meet either of the requirements. These
proposals may include, but shall not be limited to, cutting and testing cores.
Concrete which is ultimately found not be comply with any of the requirements of
the Specification shall be rejected and shall be broken out and replaced or
otherwise dealt with as agreed with the S.O.
1.45 Cutting and Testing of Core Samples
As and where discussed by the S.O. cylindrical core specimens of 150 mm nominal
diameter shall be cut normal to the face of the hardened concrete for the purpose of
examination and testing. The procedure for drilling, examination, measurement and
testing for comprehensive strength shall be in accordance with BS 1881. Prior to
preparation for testing, the specimen shall be made available for examination by the
S.O. If the crushing strength of the specimen determined in accordance with
paragraph 114 of BS 1881 is less than the characteristic strength at 28 days for the
grade requirements in other respect, the concrete in that part of the works of which
it is a sample shall be considered not to comply with the specified requirements.
Procedures
1.46 Inspection
Before any concrete is placed, the Contractor shall carry out an inspection to ensure
that all preparations are complete, including the provision of the necessary
equipment and personnel, and shall ensure that sufficient materials are available to
complete the work proposed.
After completion of this inspection the work shall be offered for inspection by the
S.O., sufficient time being allowed for inspection and correction of any defects. no
concrete shall be placed until the S.O. has inspected and approved the surfaces
upon which the concrete is to be placed the formwork and the reinforcing steel.
Where required by the S.O. the Contractor shall institute a `pour card' system in
which a card is made out for each lift of concrete and is initialed by the Contractor
and S.O. indicating that the inspections have been carried out.
The `pour card' shall include spaces to identify the concrete being placed and to
signify completion of the inspections by the Contractor and S.O. of the following
items:
Preparation of surface on which concrete is to be placed;
Formwork;
Reinforcement;
Ready for concrete placing;
Inspection after removal of formwork (any remedial work shall be agreed and noted);
D:\TECHNICAL DEPARTMENT\SPECIFICATION\SPEC FINAL PDF\PDF New Folder Final\L-Concretework 1-new1.doc L.21
正在阅读:
二年级口算每天道05-13
08年英语六级(含答案)12-26
苏州大学社会学历年考研真题 - 图文05-26
教师转正自我鉴定02-24
活动合作协议模板(20171110起草)06-09
人生因梦而美好作文500字06-22
- 教学能力大赛决赛获奖-教学实施报告-(完整图文版)
- 互联网+数据中心行业分析报告
- 2017上海杨浦区高三一模数学试题及答案
- 招商部差旅接待管理制度(4-25)
- 学生游玩安全注意事项
- 学生信息管理系统(文档模板供参考)
- 叉车门架有限元分析及系统设计
- 2014帮助残疾人志愿者服务情况记录
- 叶绿体中色素的提取和分离实验
- 中国食物成分表2020年最新权威完整改进版
- 推动国土资源领域生态文明建设
- 给水管道冲洗和消毒记录
- 计算机软件专业自我评价
- 高中数学必修1-5知识点归纳
- 2018-2022年中国第五代移动通信技术(5G)产业深度分析及发展前景研究报告发展趋势(目录)
- 生产车间巡查制度
- 2018版中国光热发电行业深度研究报告目录
- (通用)2019年中考数学总复习 第一章 第四节 数的开方与二次根式课件
- 2017_2018学年高中语文第二单元第4课说数课件粤教版
- 上市新药Lumateperone(卢美哌隆)合成检索总结报告
- Concretework
- 201
- new
- 2013最新时事政治:富丽堂皇的“官衙”让人不舒服
- 全国中小学“教学中的互联网搜索”优秀教学案例评选《小河与青草
- 六年级上册科学教案第一单元3鸟类动物的特征|冀教版
- 甘肃公务员行测数学运算习题答案解析
- 高中英语导学案与练习选修六Unit5 The power of nature Period 2
- 2022年淮北师范大学中国文化史导论考研复试核心题库
- 电力建设施工质量验收及评价规程-锅炉机组6附录
- 旅馆转让协议示范文本
- 人教版补充岳麓版I
- 中考数学 平行四边形 培优 易错 难题练习(含答案)及详细答案
- 行政管理毕业论文选题
- CA6140A型车床的基本操作
- 西餐服务程序规范 - 制度大全
- 2022年山东大学威海校区915细胞生物学考研题库
- 华师版六年级信息技术教案
- 2005-2011注册暖通专业考试真题及解析
- 横河2013测量仪器产品样本
- 安全生产反违章大反思大讨论心得体会【深刻版】文档2篇
- 全国计算机一级考试试题大全
- 三年高考高考物理真题分项汇编专题16机械振动和机械波含解析1127