连续刚构箱梁挂篮施工技术

更新时间:2023-10-24 22:16:01 阅读量: 综合文库 文档下载

说明:文章内容仅供预览,部分内容可能不全。下载后的文档,内容与下面显示的完全一致。下载之前请确认下面内容是否您想要的,是否完整无缺。

连续刚构箱梁挂篮施工技术探索

摘要: 随着连续刚构桥梁施工技术逐渐比较熟练,但施工过程中同样会忽视某些重要工序的施工质量;通过结合某连续刚构桥梁挂篮悬臂现浇施工实例,提出其在施工过程中重点施工工序,如主桥挂篮施工的质量控制技术措施等,提出了相关的对策。 关 键 词:连续刚构 箱梁施工 挂篮施工 挂篮拼装 中图分类号: u448 文献标识码:a 文章编号:

abstract:along with the continuous rigid frame bridge construction technology gradually more skilled, but the construction process also will ignore some important process of the construction quality; through a combination of a continuous rigid frame bridge hanging basket cantilever cast-in-place construction examples, puts forward the key construction process in the construction process, such as the main bridge hanging basket construction quality control measures, put forward relevant countermeasures.

key words:continuous rigid frame; box girder construction; hanging basket construction; hanging basket 1引言

某主桥上部结构采用(73+125+73)m pc 连续刚构,共分为 19 种梁段。其中 0~2#梁段为立托架现浇,3~17#梁段采用挂篮悬臂现浇施工,18#梁段为合龙段,19#梁段为边跨现浇段。箱梁纵向分块为

本文来源:https://www.bwwdw.com/article/8292.html

Top