清淤、护岸工程施工组织设计

更新时间:2024-06-29 01:45:01 阅读量: 综合文库 文档下载

说明:文章内容仅供预览,部分内容可能不全。下载后的文档,内容与下面显示的完全一致。下载之前请确认下面内容是否您想要的,是否完整无缺。

目 录

1、总 则 ································································································· 4

1.1 编制依据 ·················································································································· 4 1.2 编制原则 ·················································································································· 4

2、工程概述 ······························································································ 6

2.1 工程概况 ·················································································································· 6

3、施工总体布置 ······················································································· 12

3.1施工总平面布置 ········································································································· 12 3.2项目经理部布置 ········································································································· 12

4、施工方案总体说明 ················································································· 15

4.1主要分项工程 ············································································································ 15 4.2、施工方案总体安排 ···································································································· 15 4.3、本工程总施工流程图 ································································································· 16 4.4、主要项目施工顺序一览表 ··························································································· 17

5、主要工程项目的施工方案、施工方法 ························································· 24

5.1、施工测量 ················································································································ 24 5.2、开挖清淤(包括老海堤拆除)及陆域形成施工 ································································ 25 5.3、防渗帷幕 ················································································································ 27 5.4、截流排污、施工排水及雨水涵洞施工 ············································································ 28 5.5、护岸施工 ················································································································ 30

6、施工计划总体安排 ················································································· 41

6.1施工进度计划 ············································································································ 41 6.2人员计划 ·················································································································· 42

1

6.3 材料的准备计划 ········································································································ 43

7、项目组织管理机构 ················································································· 44

7.1 项目组织机构框图 ····································································································· 44 7.2管理职责 ·················································································································· 45 7.3主要施工管理人员及简历表 ·························································································· 48

8、施工进度保证措施 ················································································· 49

8.1组织保证措施 ············································································································ 49 8.2 物资保证措施 ··········································································································· 50 8.3人员、设备保证措施 ··································································································· 50 8.4 雨季施工安排及抗台风措施 ························································································· 50

9、质量保证体系与措施 ·············································································· 52

9.1质量保证体系概述 ······································································································ 52 9.2工程质量保证体系及质量目标: ···················································································· 52 9.3质量保证措施 ············································································································ 55

10、安全保证体系与保证措施 ······································································ 60

10.1、安全生产的原则和目标 ···························································································· 60 10.2、安全保证体系 ········································································································ 60 10.3、安全保证措施 ········································································································ 63

11、环境保护与文明施工措施 ······································································ 68

11.1、环境保护原则与目标 ······························································································· 68 11.2、环境保护管理体系 ·································································································· 68 11.3、管理职责 ·············································································································· 69 11.4、环境保护措施 ········································································································ 69 11.5、文明施工管理措施 ·································································································· 70

12、施工总平面图及施工进度计划 ································································ 71

12.1施工总平面图(附图) ··································································································· 71

2

12.2施工进度计划(横道图) ································································································ 71 12.3施工进度计划(网络图) ································································································ 71

3

1、总 则

1.1 编制依据

1.1.1《**钟宅湾清淤整治及环湾旅游休闲道路工程(清淤、护岸部分)招标文件》,**市路桥建设投资总公司--2004年3月;

1.1.2《**钟宅湾清淤整治及环湾旅游休闲道路工程A标段(施工图设计文件)》,中交第二航务工程勘察设计院--2004年2月;

1.1.3与本工程有关的(第1号补遗书及第2号补遗书,**市路桥建设投资总公司--2004年4月。

1.1.4主要施工规范及验评标准 ? 《海港水文规范》JTJ212-98; ? 《港口工程荷载规范》JTJ214-98; ? 《港口工程地基规范》JTJ240-98; ? 《疏浚工程技术规范》JTJ219-99; ? 《城市防洪工程设计规范》CJJ40-92;

? 《港口及航道护岸工程设计与施工规范》(JTJ200-2000); ? 《堤防工程设计规范》GB40285-98; ? 《水闸设计规范》SD254-2001;

? 《港口工程质量检验评定标准》JTJ221-98; ? 《塑料排水施工规范》JTJ245-95;

? 《真空预压法加固软土低级施工技术规程》HG/T20468-94; ? 《水运工程混凝土施工规范》(JTJ258-95); ? 《水运工程测量规范》(JTJ202-2001); ? 国家和行业其他有关技术规范和标准;

? 广州建港工程公司有关管理制度、质量体系文件。

1.2 编制原则

1.2.1 遵守规定的原则。在编制施工组织设计时,对本工程的招标范围、工程质量标准、工期安排及工程实施等要求严格按规定的格式和内容编写。

4

1.2.2 严格按设计要求及施工规范、质量检验评定标准组织施工的原则。在编写施工方法时,严格按照设计要求,严格执行施工技术规范和工程质量检验评定标准,精心组织、科学施工,坚持工程质量高标准,创优质精品工程。

1.2.3 结合现场实际情况施工的原则。根据现场实际情况合理进行施工布置,安排施工顺序。在安全生产的前提下,做到各项目施工工序兼顾,衔接合理,彼此减少互相干扰,合理调配人力和财力资源,减少施工成本,保证施工质量,创建环保和优化文明施工的环境。

1.2.4 采用先进施工设备和施工技术原则。在编制施工工艺和施工方法时,充分利用我联合体和国内外先进的生产设备和船机设备,组织机械化和专业化施工,确保工期和工程质量。