136电缆敷设工程作业指导书 - 2012 -
更新时间:2024-06-14 22:09:01 阅读量: 综合文库 文档下载
- 电缆敷设工程量推荐度:
- 相关推荐
第8部分:配网工程
电缆敷设工程作业指导书
编码:DLFS-01
DLFS-01电缆敷设工程作业指导书
目
次
1适用范围···················································································································83 2编写依据···················································································································83 3作业流程图················································································································83 4安全风险辨析与预控····································································································83 5作业准备···················································································································85 6作业方法···················································································································6 7质量控制措施及检验标准······························································································9
101
中国南方电网有限责任公司电网建设施工作业指导书第8部分:配网工程
1适用范围
1.1电压等级
35kV及以下配网工程。 1.2电气类别
电缆敷设。 2编写依据
表2 编写依据
序号 引用资料名称 GB50168—2006《电气装置安装工程电缆线路施工及验收规范》 GB50217—2007《电力工程电缆设计规范》 DL/T5161.5—2002《电气装置安装工程质量检验及评定规程第5部分:电缆线路施工质量检验》 Q/CSG11105—2008《南方电网工程施工工艺控制规范》 《中国南方电网有限责任公司基建工程质量控制作业标准(WHS)》 1 2 3 4 5
3作业流程图
图3作业流程图
4安全风险辨析与预控
4.1电缆敷设工程作业前,施工项目部根据该项目作业任务、施工条件,参照《电网建设施工安全基准风险指南》(下简称《指南》)开展针对性安全风险评估工作,形成该任务的风险分析表。
4.2按《指南》中与电缆敷设工程作业相关联的《电网建设安全施工作业票》(编码:DLFS-01-01/01),结合现场实际情况进行差异化分析,确定风险等级,现场技术员填写安全施工作业票,安全员审核,施
102
DLFS-01电缆敷设工程作业指导书
工负责人签发。
4.3施工负责人核对风险控制措施,并在日站班会上对全体作业人员进行安全交底,接受交底的作业 人员负责将安全措施落实到各作业任务和步骤中。
4.4安全施工作业票由施工负责人现场持有,工作内容、地点不变时可连续使用10天,超过10天须重新办理作业票,在工作完成后上交项目部保存备查。
表4.1作业任务安全基准风险指南
序号 危害名称 风险种类 坠落 摔绊 扭伤 打击 打击 风险等级 风险控制措施 1 施工区域安全围蔽措施不足 吊点选择不正确 中等风险 施工区域必须做好安全围蔽及警示标志措施,晚上设置夜间警示灯,防止外人误入工作区域 1.司索人员必须持证上岗; 2.电缆盘装卸起吊点选择要合适、绑扎牢固 2 中等风险
5作业准备
5.1作业前施工条件
表5.1作业前施工条件
序号 1 2 3 4 5 项目 任务单 图纸 预算材料表 施工方案 相关证照 内容 根据本单位实际设置内容(包含本项工作) 设备变更单、设计图纸 含主、辅材料 施工措施、安全技术交底(项目部级) 根据需要办理涉及进入工作场所的手续、证件 (1)预埋件符合设计,安置牢固。 (2)电缆沟、隧道、竖井及人孔等处的地坪及抹面工作结束。 (3)电缆层、电缆沟、隧道等处的施工临时设施、模板 及建筑废料等清理干净,施工用道路畅通,盖板齐全。 (4)电缆沟排水畅通。 (5)检查电缆路径转弯处弯曲半径不小于电缆最小允许弯曲半径。 (6)对设计图指定的排管和过路孔进行疏通检查,所用管孔应双向畅通。 (7)电缆桥架转弯处的转弯半径,不应小于该桥架上的电缆最小允许弯曲半径的最大值。 (8)金属电缆支架、桥架全长均应有良好的接地。 (9)桥架(托盘)在每个支吊架上应固定牢固;桥架(托盘)连接板的螺栓应紧固,螺母应位于桥架(托盘)的外 侧。铝合金桥架在钢制支吊架上固定时,应有防电化腐蚀 的措施。 (10)当直线段钢制电缆桥架超过30m、铝合金或玻璃钢 制电缆桥架超过15m时,应有伸缩缝,其连接宜采用伸缩 连接板;电缆桥架跨越建筑物伸缩缝处应设置伸缩缝。 (11)钢绞线及电杆无锈蚀、没有松股、交叉、折叠、断裂及破损等缺陷。 (12)钢绞线应满足荷载要求,并全线有良好接地,在 转弯处需打拉线或顶杆 确认人 本工序施工负责人 本工序施工负责人 本工序施工负责人 本工序施工负责人 本工序施工负责人 说明 经审批 经审批 经审批 经审批 有效 6 确认上一道工序检查合格 现场施工负责人 合格
103
中国南方电网有限责任公司电网建设施工作业指导书第8部分:配网工程
5.2人员、主要工器具及仪器仪表配置
表5.2人员、主要工器具及仪器仪表配置
序号 项目 内容 根据工程量的大小配备足够施工人员。施工现场明确施工负责人、技术负责人、质安员、安装施工作业人员组织到位 说明 技术岗位必须持有与作业工 种、相应、有效的上岗证。辅助 工不得从事电气设备安装等专业 工作 (1)电缆型号、电压、规格符合设计要求。 (2)应检查电缆盘和电缆外护 层的质量。对电缆质量有怀疑时,应取样检验或测试,并做好详细 记录。 (3)收集电缆出厂证件、技术资料 1 人员配置 2 施工内容相对应的设备 电力电缆 3 施工内容相对应的机械、工器具及仪表 工器具:施工电源盘、电缆滑轮、放线架、盘轴、装卸电 缆的钢丝绳、牵引钢丝绳、千斤顶、通管器、电缆盘制动装 置、安全带、登杆工具、梯头、防捻器、拉力表、入水槽、 根据现场情况使用的工器具、退扭架、潜水设备、车内胎、电缆牵引套、管口保护喇叭、 绳索、皮尺、钢锯、抽排风机、手锤、凿子、对讲机、彩旗、 机械符合相关要求。 钢丝绳荷重,需保证其安全系销子、安全文明施工用具等。 机械:卷扬机、吊车、大车等、敷设施工船、履带牵引机、数,根据吊车臂角度确定荷载, 不得超载使用 埋设机、高压水泵等。 仪表:入水角测量仪、测距仪、长度记录仪、DGPS定位 系统等 4 技术准备 (1)敷设前应按设计和实际路径计算每根电缆长度,合理 安排每盘电缆,减少电缆接头。接头位置应选择在直线部分, 与管口的距离应在3m以上,应避免设置在道路交叉口、有车辆进出的建筑门口、电缆线路转弯处及地下管线密集处。 (2)计算电缆牵引力,制定牵引方向及牵引方式 工作负责人向项目负责人报开工,由项目负责人完成向监理单位开工报审手续 施工准备完成可报开工,当施 工准备不足时,上报该项目负责 人协调解决
5 完成开工程序 6作业方法
表6作业方法
序号 项目 内容 说明 1 (1)现场施工负责人向进入本施工范围的所有工作人员明 确交待本次施工设备状态、作业内容、作业范围、进度要求、 特殊项目施工要求、作业标准、安全注意事项、危险点及控 制措施、危害环境的相应预防控制措施、人员分工,并签署 (班组级)安全技术交底表。 按安规规定统一着装,佩戴安全帽,佩戴有个人照片的作业证(或作业前工作 (2)工作负责人负责办理相关的工作许可手续,开工前做胸卡证) 好现场施工防围警示措施。 (3)现场施工负责人检查确认进入本施工范围的所有工作人员正确使用劳保用品和着装并带领施工作业人员进入作业现场。 (4)在带电区域内或邻近带电区域内敷设电缆,应有可靠 的安全措施 2 开始主要作业 现场施工负责人发出许可开工命令 104
DLFS-01电缆敷设工程作业指导书
3 作业程序 现场施工负责人正确、安全地组 织作业,现场施工质安员负责现场 作业全过程的安全、质量监控 (1)电缆盘就位可用起重机或人工将电缆盘放置指定位置,电缆在装卸的过程中,设专人负责统一指挥,指挥人员发出 的指挥信号必须清晰、准确。 电缆放线架应放置稳妥,钢轴的(2)采用吊车装卸时,装卸电缆盘孔中应有盘轴,起吊钢长度应与电缆盘重量和宽度相配丝绳套在轴的两端,不应直接穿在盘孔中起吊。人工移动电合,电缆盘的平衡要以钢轴是否平缆盘前,应检查线盘是否牢固,电缆两端应固定,线圈不应衡为准。电缆盘离开地面高度应为 松弛,电缆盘只允许短距离滚动,滚动时滚动方向必须与线50~100mm 盘上箭头指示方向一致。 4 一般规定
105
中国南方电网有限责任公司电网建设施工作业指导书第8部分:配网工程
4 一般规定 允许最小弯曲半径 电缆类型 单芯 多芯 无铠装 20D 15D 交联聚乙烯绝 缘电缆 有铠装 15D 12D 铝包 30D 油浸纸绝 有铠装 铅缘电缆 20D 15D 包 无铠装 20D 注:D表示电缆直径,mm。 (4)电缆敷设时,不应损坏电缆沟、隧道、电缆井和人井的 防水层。 (3)根据电缆长度和截面,选用的牵引绳长度比电缆长30~ 50m。牵引绳连接必须牢固。其连接点应选用防捻器。布放缆电滑轮,直线部分应每隔2.5~3m设置直线滑轮,确保电缆与地面摩擦,所有滑轮必须形成直线。弯曲部分采用转弯滑轮,并控不 制电缆弯曲半径和侧压力。电缆允许最小弯曲半径应符合下表规 定。在关键部位应有专人监视(如转弯位、管口、与其 他管道交叉的部位)。 牵引方式 牵引头 钢丝网套 受力部拉 钢导体 铝导体 铅护套 铝护套 塑料 护套 允许牵引 强度 70 40 10 40 7 N/mm2 (5)电力电缆在终端头与接头附近宜留有备用长度。 (6)并联使用的电力电缆,如设计没要求时,其长度、型号、 规格应相同。 电缆放线架应放置稳妥,钢轴的(7)电缆敷设时,可用人力拉引或机械牵引,电缆应从电缆 长度应与电缆盘重量和宽度相配盘的上端引出,不应使电缆在支架上及地面磨擦拖拉。对于较合,电缆盘的平衡要以钢轴是否平重的电缆盘,应考虑加装电缆盘制动装置。电缆走动时,严禁 衡为准。电缆盘离开地面高度应为 用手搬动电缆及滑轮。50~100mm (8)敷设电缆时,机械敷设电缆速度不宜超过15m/min,并 监测侧压力和拉力不超过允许强度。在较复杂的路径上敷设电 缆时,其速度应适当放缓。机械敷设时电缆最大允许牵引强度 不宜大于下表数值。 (9)电力电缆在切断后,应将端头立即做好防潮密封,以免水分侵入电缆内部。 (10)若电缆沟内并列敷设多条电缆,其中间接头位置应错开。其净距不应小于0.5m。 (11)垂直敷设或超过45°倾斜敷设的电缆在每个支架及桥 架上每隔2m处;水平敷设的电缆,在电缆首末两端及转弯、电缆头的两端处;当对电缆间距有要求时,每隔5~10m处; 应将电缆加以固定。 (12)电缆敷设后,应及时排列整齐,避免交叉重叠,并在 电缆终端、中间接头、电缆拐弯处、管口等地方的电缆上装设 标志牌,标志牌上应注明电缆编号、电缆型号、规格与起讫地 点。 (13)沿电气化铁路或有电气化铁路通过的桥梁上明敷电缆的金属护层或电缆金属管道,应沿其全长与金属支架或桥梁的金属构件绝缘。 4 一般规定 (14)敷设完毕后,应及时清除杂物,盖好盖板。必要时, 电缆放线架应放置稳妥,钢轴的 106
DLFS-01电缆敷设工程作业指导书
还要将盖板缝隙密封。在施工完的隧道、电缆沟、竖井、电房出入口、管口进行密封 长度应与电缆盘重量和宽度相配合,电缆盘的平衡要以钢轴是否平 衡为准。电缆盘离开地面高度应为 50~100mm 5 敷设方式分解 各种敷设方式的特点、技术要求 根据不同敷设方式除符合一般规定外,还应注意各种敷设方式的特点、技术要求 6 直埋敷设 电缆直埋敷设施工除符合一般规定外,还应注意以下几点: (1)沟底距地面的距离应满足设计要求。 (2)电缆沟底应平整,并按设计要求铺上软土或沙。电缆敷设完后,上面应盖一层软土或沙,盖上保护盖板。也可把电缆放入预制钢筋混凝土槽盒内填满砂,然后盖上槽盒盖。 (3)电缆之间,电缆与其他管道、道路、建筑要求,不得将电缆平行敷设于管道的上方或下方,最小允许净距。 (4)电缆与铁路、公路等交叉以及穿过建筑物时,可将电缆 穿入电缆管中,以防止电缆受到机械损伤,同时也便于日后拆换电缆。 (5)在电缆路径的土壤中,如发现有化学腐蚀、电解腐蚀、白蚁危害等,应采取相应的保护措施。 (6)人工敷设电缆。电缆的人工拉引一般是人力、滚轮和人 工相结合的方法,这种方法需要施工人员较多,特别注意的是 人力分布要均匀合理,负载适当,并要统一指挥。电缆敷设时, 在电缆盘两侧须有协助推盘及负责刹盘滚动的人员。为避免电 缆拖伤,可把电缆放在滚轮上,敷设电缆的速度要均匀。 (7)缆在直线段每隔15~30m处、电缆接头处、转弯处、进入建筑物等处,应设置明显的方位标志或标桩 7 排管敷设 排管敷设电缆施工除符合一般规定外,还应注意以下几点: (1)对设计图纸规定的管孔进行疏通检查,清除管道内可能 漏浆形成的水泥结块或其他残留物,并检查管道连接处是否平 滑,以确保电缆传入排管时不遭受伤。必要时应用管道内窥镜探测检查。 (2)试牵引,经过检查后的管道,可用一段3m长与本工程电缆规格相同的电缆作模拟牵引,观察电缆表面的磨损是否属于许可范围。 (3)电缆进入排管前,可在其表面涂上与其护层不起化学作用的润滑物。管道口应套以光滑的喇叭管,井坑口应装有适当的滑轮组,以确保电缆敷设牵引时的弯曲半径,减小牵引时的磨擦阻力。 (4)一条管道只能敷设一条电缆 (1)对设计图纸规定的管孔经过疏通检查,确定有杂物和淤泥堵塞不能使用时或管孔对电缆外护套有破损和卡阻时,要向设计及土建人员提出。 (2)电缆排管敷设范围内,在电缆没有进入的排管口要有专人进行监护 8 电缆沟敷设 电缆沟敷设电缆施工除符合一般规定外,还应注意以下几 点: (1)电缆沟敷设电缆可用人力或机械牵引,见表5-3中6直埋 敷设。 在电缆引入电缆沟和电缆沟转(2)敷设前,要用抽风机进行排气。 弯处,必须安装滑轮组和配有专人进行监护 (3)电缆在支架敷设时,电力电缆间距和不同电压等级电力电缆间及控制电缆间的最小净距应符合设计要求。 (4)电缆敷设完后,在电缆沟支条排列时按设计要求排列,金属支架应加塑料衬垫。如设计没有要求时应遵循电缆从下向上、从内到外的顺序排列原则 桥梁敷设电缆施工除符合一般规定外,还应注意以下几点: (1)桥梁敷设应取得桥梁管理部门认可,电缆和附件的全部 9 桥梁敷设
107
中国南方电网有限责任公司电网建设施工作业指导书第8部分:配网工程
重量在桥梁设计允许承载范围之内。 (2)在桥梁上敷设的电缆和附件,不得低于桥底距水面的高 度,不得有损桥梁结构和外观。悬吊架设的电缆与桥梁架构之 间的净距应符合设计要求。 (3)敷设在长跨距桥梁上的电缆与附件,应具有适应安装环境性能,如耐震动、耐热机械力、耐腐蚀、外护套具有一定的绝缘性能。 (4)在敷设牵引时,在桥堍处应有必要技术措施,使电缆承受的牵引力、侧压力、弯曲半径,都在允许值范围内,并经计算确认。 (5)电缆桥梁敷设,除填砂和穿管外,应在桥墩两端和伸缩缝部位电缆应留有裕度 10 隧道敷设 隧道敷设电缆施工除符合一般规定外,还应注意以下几点: (1)敷设前,要用抽风机进行排气。 (2)使用机械敷设时,应有可靠的通信联络措施、(如在隧 道增设对讲差转机等)照明设施、通风设施。 (3)使用机械敷设时,电缆从工作井引入时,搭建适当的滚 敷设电缆过程中,要防止电缆被轮支架,确保电缆不与地面及井口摩擦,并控制电缆弯曲半径、 电缆沟边或电缆支架刮伤。在一些扭转力和侧压力。防止电缆铠装压扁、电缆绞拧、护层折裂、 重要的部位,如转弯处、井口应配有经验的电缆工进行监护 绝缘破损等机械损伤。 (4)牵引钢丝绳如需用滑车转向,可选择隧道内位置合适的拉环。 (5)除以上四点,隧道敷设电缆可参照电缆沟敷设方式。 (6)在电缆隧道中应有必要的防火措施 11 水底敷设 (1)根据该项目设计要求和实际确定电缆登陆点和路径中心 线。在两岸竖立标示路径中心线和设计偏移幅度的道标。确定 过河或过江电缆长度及接头位置,并计算电缆牵引力制定牵引方 向及牵引方式。并办理封航手续。 (2)按设计要求在河两岸选择适当位置作为电缆出入水点。 通常浅滩较长的岸边为始端登陆处,末端登陆长度越短越好。 (3)在水域不太宽且流速小的河道施工,可将电缆盘放在岸 上,将电缆浮悬在水面上,由对岸钢丝绳牵引敷设;在江面宽、 流速大、航行船频繁处施工,应将电缆盘放在敷设船上,边航 施工前,选择符合要求的船只,行边敷设。 组织足够的施工人员,配备完备的(4)中间水域敷设时要控制三个环节: 机具、设备和仪器。 1)控制好消除铠装钢丝的退扭力。在牵引端上应装防捻器,敷设时,在船上的施工人员要穿散装敷设施工船上装退扭架。 好救生衣 2)控制好敷设船按设计路径航行,航行轨迹不应超过设计 允许的偏离范围。 3)控制好电缆敷设速度、入水角和电缆张力,以确保电缆敷设过程中不打小圈。 措(5)水底电缆引到岸上的部分应穿或加保护盖板等保护 到 施,其保护范围,下端应为最低水位时船只搁浅及撑篙达不 之处;上端高于最高洪水位。在保护范围的下端,电缆应固定。 水底敷设电缆施工除符合一般规定外,还应注意以下几点: (6)水底电缆敷设后,应作潜水检查,电缆应放平,河床起伏处电缆不得悬空。并测量电缆的确切位置。在两岸必须按设计设置标志牌。 108
DLFS-01电缆敷设工程作业指导书
12 架空敷设电缆施工除符合一般规定外,还应注意以下几点: (1)为保护电缆的外护层不受到伤害及减少摩擦力,在钢绞线 上吊装电缆滑轮。其间距与电缆单位长度的重量有关,一般每隔 2~3m距离安装一个,以不使电缆下垂碰地为原则,电缆滑车 成直线安装。牵引电缆时电缆网套与钢丝绳间必须加装防捻 器。 (2)电缆敷设分人工敷设和机械敷设两种。架空电缆线路均比较短,放线时可在地面将电缆放开量好长度把电缆锯断,分段将电缆挂至吊线上。吊挂电缆时防止电缆弯曲半径过小再 当地面障碍物较多无法采用此法时,可采用定滑轮法,放线时, 防止挂住定滑轮或其他障碍物。 , (3)架空电缆一般用挂钩托挂在吊线下,也可绑扎。对于铠 装电缆可每隔0.4m加以固定,若为无铠装电缆则挂钩距离应缩 短。 (4)架空电缆与公路、铁路、架空线路交叉跨越时应符合下表 架空电缆与公路、铁路、架空线路交叉跨越时最小允许距离。 架空敷设 交叉设施 铁路 公路 最小允许距离 m 只适用于10kV电压等级 备注 7.5 6 电车路 弱电流线路 电力线路 3/9 1 至承力索或接触线/至路面 电压:6~10kV 2 (5)钢绞线应满足荷载要求,并全线有良好接地,在转弯处需打拉线或顶杆。 (6)架空敷设的电缆不宜设置电缆接头 13 桥架敷设 桥架敷设电缆施工除符合一般规定外,还应注意以下几点: (1)敷设电缆可用人力或机械牵引,见直埋电缆牵引方式。 (2)桥架水平敷设时,应将电缆单层敷设,排列整齐。不得有交叉,拐弯处应按电缆允许弯曲半径为准。 (3)不同等级电压的电缆应分层敷设,高压电缆应敷设在最上层。 (4)同等级电压的电缆沿桥架敷设时,电缆水平净距不得小 于35mm。 (5)电缆敷设排列整齐,水平敷设的电缆,首尾两端、转弯两侧及每隔5~10m处设固定点。 (6)垂直敷设前,选好位置,架好电缆盘,电缆的向下弯曲部位用滑轮支撑电缆,在电缆轴附近和部分楼层应设制动和防 滑措施;敷设时,同截面电缆应先敷设低层,再敷设高层。 (7)如需自下而上敷设,低层小截面电缆可用滑轮绳索人力牵引敷设;高层大截面电缆宜用机械牵引敷设。 (8)对于敷设于垂直桥架内的电缆,每敷设一根应固定一根, 全塑型电缆的固定点为1m,其他电缆固定点为1.5m
109
中国南方电网有限责任公司电网建设施工作业指导书第8部分:配网工程
7质量控制措施及检验标准 7.1质量控制措施
7.1.1现场负责人应根据现场情况安排技术人员负责质量监控。
7.1.2作业人员必须熟悉工程作业流程和质量检验标准;技术岗位人员必须持有与作业相应、有效的上岗证。
7.1.3现场负责人在进行安全技术交底时必须详细介绍本作业质量控制要点、常见的质量通病及其防治 措施。
7.1.4作业现场必须有经审核批准的设计图纸和施工方案,作业人员必须按图施工。
7.1.5施工质量检验一般按以下方式进行。质量检验一般采用三级检验制,施工队(组)对所施工的分项工程应进行100%的质量自检;项目部对所负责施工的分部工程和单位工程组织质量检查,复检比例不宜低于50%;公司对单位工程组织检查,抽检比例不宜低于20%。
7.1.6隐蔽工程施工完成以及全部工序作业完成(转序)时,必须提前24小时通知监理现场验收。 7.2质量控制表
表7.2质量控制表
控制点 W 电缆线路安装工程 控制方式 H S ●
7.3检验标准
质量检验按《10kV~500kV输变电及配电工程质量验收与评定标准第8册:配网工程》中的Q/CSG表 8-7.4要求执行。
110
DLFS-01电缆敷设工程作业指导书
●附件1安全施工作业票
编码:DLFS-01-01/01
工作地点 技术员 现场安全员 现场负责人 工作时间 安全风险分析及控制措施 序号 危害名称 施工区域安全围蔽措施不足 吊装作业不设 专人指挥 起重设备回转 半径内站人 起重设备支腿 不稳* 电缆盘支架不稳 电缆敷设时电缆 盘没有可靠制动措施 防暑降温措施不足 没有正确使用安全带 电缆沿线与其他 地下管线交叉部位防护措施不足 未弄清地下管线 分布情况下就打入桩锚 敷设路径有白蚁 灾害 管口没有导入装置 损伤运行中的电缆 风险种类 风险等级 风险控制措施 1 坠落、摔绊、 □中等风险 扭伤、打击 打击 □中等风险 现场作业应严格执行相关安全规程及安全技术措施,并重点关注但不限于以下措施: 2 □施工区域必须做好安全围蔽及警示标示措施,晚上设置夜间警示灯,防止外人误入工作区域。 □起重作业设专人统一指挥,使用统一的指挥信号。 3 打击 □中等风险 □各腿支承点必须牢固可靠,土质松软的地方应加垫钢板。 打击、碰撞 打击 □中等风险 □中等风险 □敷设电缆时,禁止任何人员在牵引钢丝绳内角侧逗留。 4 5 打击 □高风险 □电缆盘应有可靠制动措施,应先停止牵引,再进行电缆、滑轮调整。 □在道路旁边施工时,施工人员要穿反光衣。 □施工人员严禁踩踏电缆,尤其是运行中的电缆、电缆中间接头。 □电缆敷设完毕,砍断电缆应及时做好密封防潮措施。 6 7 中暑 坠落 □中等风险 □中等风险 8 □炎热天气,配置太阳伞、风扇,现场配备应急药品和及时补充水分。 设备破损 □高风险 □电源箱按规定安装漏电保护开关,不得采用铜丝代替保险丝使用。 □施工现场临时电源线不得乱拉乱接,必须符合要求。 9 设备破损 □高风险 10 □施工人员应按规定穿好工作服,并正确佩戴安全帽。 □离地面高度超过2m时,按规定正确使用安全带。 11 12 13 设备破损 打击 触电 □中等风险 □高风险 □高风险 □线缆敷设进入电房、设备后及时对线缆进出口进行封堵,并检查可靠性。 □在敷设路径采取白蚁防治措施。 □敷设电缆时,所有管口部位必须使用导入装置。 14 进入电缆沟、井内 前,没采取通风排中毒、窒息 □中等风险 浊措施 □严禁在电缆坑内吸烟或向电缆坑内扔烟头、火柴等火种。 □电缆隧道内集水井必须装配盖板(栅格)的部位,防止人员坠落。 □穿越江河的电缆敷设前必须办理并落实封航措施,才能进行敷设作业 15 穿越江河电缆敷设期间没有采取封锁航道措施 淹溺、交通意外 □中等风险 注:“危害名称”一栏中,带有“*”标记的,说明此危害曾在公司基建系统引发过事故。
111
中国南方电网有限责任公司电网建设施工作业指导书第8部分:配网工程
安全补充事项/平面布置图 现场接受交底人员签名 备注 说明:(一)本票由现场技术员填写,现场安全员审核,现场负责人签发生效。现场负责人开工前核对风险控制措施 并宣读。(二)工作内容、地点、安全措施不变时本票最长可使用十天,否则应重新办票,用后上交备查;当人员发生变更时,应在备注栏记录变更情况。对新增人员进行交底,并签名确认。(三)应根据现场条件、范围和环境,补充安全事项或平面布置图。(四)当风险等级与基准风险等级不一致时,项目部应组织相关人员重新进行风险评估并制定措施。(五)基准风险等级与风险控制措施在开工前现场打“√”。(六)签名不齐全(含代签名的)均作废票处理。
112
正在阅读:
写给男朋友的一句话02-10
一路成长一路歌02-14
加拿大风景09-04
新教科版三年级科学全册实验报告11-14
《物质的构成和组成》中考早体验05-23
安规及两票制度考试试题(电气)11-16
社护习题(专科)一11-24
2018-2024年中国高光谱成像仪市场分析及发展策略研究预测报告04-17
广州英语-上海牛津版-七年级下-重点语法06-11
- 多层物业服务方案
- (审判实务)习惯法与少数民族地区民间纠纷解决问题(孙 潋)
- 人教版新课标六年级下册语文全册教案
- 词语打卡
- photoshop实习报告
- 钢结构设计原理综合测试2
- 2014年期末练习题
- 高中数学中的逆向思维解题方法探讨
- 名师原创 全国通用2014-2015学年高二寒假作业 政治(一)Word版
- 北航《建筑结构检测鉴定与加固》在线作业三
- XX县卫生监督所工程建设项目可行性研究报告
- 小学四年级观察作文经典评语
- 浅谈110KV变电站电气一次设计-程泉焱(1)
- 安全员考试题库
- 国家电网公司变电运维管理规定(试行)
- 义务教育课程标准稿征求意见提纲
- 教学秘书面试技巧
- 钢结构工程施工组织设计
- 水利工程概论论文
- 09届九年级数学第四次模拟试卷
- 敷设
- 指导书
- 电缆
- 作业
- 工程
- 2012
- 136